This Circular specifies details on surveying, evaluating general information for Group IV minerals, and sample mining permits and related documents. It applies to state management agencies, organizations, and individuals involved in the exploitation of Group IV minerals.
Scope of application
State management agencies for geology and minerals; organizations, households, and individuals engaged in the exploitation of Group IV minerals.
Key points
- For areas not subject to auction for mining rights, organizations and individuals conducting surveys and evaluations of general information for Group IV minerals must obtain written approval from specialized geological and mineral management agencies after complying with the contents stipulated in Article 4 of this Circular.
- For areas subject to auction for mining rights, successful bidders must conduct surveys and evaluations of general information for Group IV minerals after the state management agency approves the auction results.
- The results of surveys and evaluations of general information for Group IV minerals must be confirmed by specialized geological and mineral management agencies, except in cases provided for in Clause 2 of Article 72 of the Law on Geology and Minerals.
- The deadlines for receiving applications, reviewing, approving, and confirming the results of surveys and evaluations of general information for Group IV minerals are specified in detail.
- Sample forms for requesting approval of surveys and evaluations of general information; confirmation of survey and evaluation results; issuance of mining permits for Group IV minerals and sample maps in permit application files are issued together with this Circular.
🌐 Social impact of this document
- Positive impact: Strengthening state management over geology and minerals; ensuring the accuracy of general information for Group IV minerals.
- Negative impact: Increased costs for organizations and individuals conducting surveys and evaluations of general information and mining activities.
❓ Frequently asked questions
How many types of sample documents are prescribed in this Circular?
This Circular prescribes five types of sample documents: Request for approval of surveys and evaluations of general information; Request for confirmation of survey and evaluation results; Request for issuance of mining permits for Group IV minerals; Maps in permit application files for mining permits for Group IV minerals; Mining permits for Group IV minerals.
What is the deadline for receiving applications and reviewing the results of surveys and evaluations of general information for Group IV minerals?
The deadline for receiving applications does not exceed five working days from the date of validity. The deadline for reviewing the results of surveys and evaluations of general information for Group IV minerals does not exceed ten days.
How many sample maps are prescribed in this Circular?
This Circular prescribes two sample maps: Maps in permit application files for mining permits for Group IV minerals and Mining permits for Group IV minerals.
How many types of permits are prescribed?
This Circular prescribes two types of permits: Mining permits for Group IV minerals and Mining permits for Group IV minerals (extension).
How many types of sample documents are prescribed in this Circular?
This Circular prescribes five types of sample documents: Request for approval of surveys and evaluations of general information; Request for confirmation of survey and evaluation results; Request for issuance of mining permits for Group IV minerals; Maps in permit application files for mining permits for Group IV minerals; Mining permits for Group IV minerals.
Full text
|
MINISTRY OF NATURAL RESOURCES AND ENVIRONMENT |
SOCIALIST REPUBLIC OF VIET NAM |
|
Number: 01/2025/TT-BTNMT |
Hanoi, on 15 of the Government stipulating the functions, tasks, powers, and organizational structure of1 Pursuant to Decree No. 32/2019/NĐ-CP dated April 10, 2019 of the Government on assigning tasks, procurement or tendering for the supply of products and services using state budget from regular operating expenses;25 |
CIRCULAR
DETAILING CERTAIN PROVISIONS OF THE GEOLOGY AND MINERALS LAW ON THE EXTRACTION OF GROUP IV MINERALS
Based on the Law on Geology and Minerals dated November 29, 2024;
Pursuant to the Law on Minerals dated November 17, 2010;
Pursuant to Decree No. 158/2016/NĐ-CP dated November 29, 2016 of the Government detailing the implementation of certain provisions of the Minerals Law;
Pursuant to Decree No. 68/2022/NĐ-CP dated September 22, 2022 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Natural Resources and Environment;
At the proposal of the Director of the Vietnam Minerals Administration;
The Minister of Natural Resources and Environment promulgates this Circular detailing certain provisions of the Geology and Minerals Law on the extraction of Group IV minerals.
PART I
GENERAL PROVISIONS
Article 1. Scope of Regulation
This Circular details Point a Clause 1, Point d Clause 2, Point h Clause 4 Article 73, Clause 3 Article 74 of the Geology and Minerals Law on surveying and evaluating general information for Group IV minerals, reports on the results of Group IV mineral extraction activities; specifies the model of the mining permit for Group IV minerals, the model of documents in the application dossier for the mining permit for Group IV minerals, the model of the mining plan for Group IV minerals.
Article 2. Applicability
This Circular applies to state management agencies for geology and minerals; agencies, organizations, households, and individuals involved in activities related to the contents stipulated in Article 1 of this Circular.
Chapter II
SURVEYING AND EVALUATING GENERAL INFORMATION FOR GROUP IV MINERALS AND SAMPLE DOCUMENTS, MAPS, PLANS IN THE EXTRACTION OF GROUP IV MINERALS
Article 3. Surveying and evaluating general information for Group IV minerals
1. For areas not auctioned for mining rights, organizations and individuals shall conduct surveys and evaluations of general information for Group IV minerals according to the contents specified in Article 4 of this Circular after receiving written approval from the specialized agency on geology and minerals under the provincial People's Committee, except in cases provided for in Clause 3 of this Article.
2. For areas auctioned for mining rights, organizations and individuals winning the auction for mining rights shall conduct surveys and evaluations of general information for Group IV minerals according to the contents specified in Article 4 of this Circular after the competent state management agency approves the auction results for mining rights, except in cases provided for in Clause 3 of this Article.
3. Areas that are not required to conduct general information surveys and assessments for Group IV minerals include:
a) Areas with approved and recognized results of Group IV mineral exploration;
b) Areas where there are already survey and evaluation results of general information for Group IV minerals that meet the contents specified in Article 4 of this Circular.
The issuance of mining permits for Group IV minerals is based on the results of Group IV mineral exploration and previous general information surveys and assessments for Group IV minerals.
4. The organization and implementation of general information surveys and assessments for Group IV minerals shall be carried out as follows:
a) Individuals specified in Clauses 1 and 2 of this Article must enter into a contract with an organization having sufficient capacity to conduct surveys and evaluations of general information for Group IV minerals according to the contents specified in Article 4 of this Circular;
b) Organizations specified in Clauses 1 and 2 of this Article having sufficient capacity to conduct surveys and evaluations of general information for Group IV minerals according to the contents specified in Article 4 of this Circular may conduct such activities themselves or enter into a contract with an organization having sufficient capacity to conduct such activities. In case they do not have sufficient capacity, they must enter into a contract with an organization having sufficient capacity to conduct surveys and evaluations of general information for Group IV minerals according to the contents specified in Article 4 of this Circular;
c) The organization conducting surveys and evaluations of general information for Group IV minerals shall bear full responsibility under the law for the results of such surveys and evaluations.
5. Prior to conducting surveys and evaluations of general information for Group IV minerals, organizations and individuals must notify the specialized agency on geology and minerals under the provincial People's Committee and the People's Committee of the commune where the surveys and evaluations will be conducted of the time of implementation.
6. The results of surveys and evaluations of general information for Group IV minerals must be confirmed by the specialized agency on geology and minerals under the provincial People's Committee, except in cases provided for in Clause 2 of Article 72 of the Geology and Minerals Law.
Article 4. Content of survey and evaluation of general information for Group IV minerals
1. The contents of general information surveys and assessments for Group IV minerals, except in cases provided for in Clause 2 of this Article, are as follows:
a) Conduct topographic mapping at a scale of 1:2,000;
b) The geological route shall be carried out as follows: the maximum distance between routes is 400 meters; the density of survey points ranges from 200 to 300 points per kilometer.2Each geological survey point on-site must describe the geological characteristics, composition, structure, and determine the boundaries of product layers and mineral bodies (if any) to serve as the basis for determining the average thickness of product layers and mineral bodies within the survey area.
c) Construction of geological works (outcrops, pits, wells, or drilling) must determine coordinates and elevations according to the national coordinate system and elevation system, control the entire thickness of product layers and mineral bodies or control up to the planned mining elevation, and shall be carried out as follows: the maximum distance between construction lines is 400 meters, and the maximum distance between works on the same line is 200 meters. For areas with an area of less than 1.0 hectares and a distribution length not exceeding 500 meters, there must be at least one representative geological work to ensure control over product layers and mineral bodies.
d) Hydrogeological and engineering geological surveys, collection of hydrological data, determination of rainfall in the survey area for the most recent three years;
d) Collecting and processing samples including: trench samples, core drilling samples, heavy sand samples (for placer deposits), rock samples, moisture samples, loose samples, soil mechanical samples, and radioactivity activity samples;
e) Sample analysis includes: basic chemical component analysis for trench samples and core drilling samples, and ICP 36 element analysis (taken from the basic chemical sample storage part, at least 10% of the basic chemical samples) to determine the beneficial and harmful elements in product layers and mineral bodies, mineral component analysis, comprehensive physical and mechanical index analysis, determination of moisture content, expansion coefficient, and radioactivity activity. including: basic chemical component analysis for trench samples, drill core samples, and ICP 36 elements (taken from the basic chemical sample storage section, at least 10% compared to the basic chemical sample) to determine the composition of beneficial and harmful elements in product layers, mineral bodies; mineralogical component analysis, comprehensive physical and mechanical index analysis, determination of moisture content, loose expansion coefficient, and radioactivity activity determination;
g) At least one sample per geological work, with a maximum sample length of 10 meters.
2. For cases provided for in Clause 2 of Article 72 of the Law on Geology and Minerals, the contents of general information surveys and assessments for Group IV minerals are as follows:
a) Conduct topographic mapping at a scale of 1:2,000;
b) Construct at least one representative geological work (outcrop, pit, well, or drilling) to ensure control over product layers and mineral bodies or up to the planned mining elevation; the geological work must determine coordinates and elevations according to the national coordinate system and elevation system.
c) Sampling, processing, and analysis of samples: ICP 36 elements to determine the beneficial and harmful element components in product layers and ore bodies; radioactivity activity sample.
3. Geological work construction techniques shall be implemented in accordance with Circular No. 16/2020/TT-BTNMT dated December 18, 2020, issued by the Ministry of Natural Resources and Environment, which stipulates technical requirements for excavation works and geological and mineral sampling; procedures for collecting, processing, analyzing samples and quality control and handling shall be carried out in accordance with current regulations; the method for calculating mineral volume shall be applied according to the methods for calculating reserves and resources and selected appropriately based on the characteristics of product layers and mineral bodies to ensure reliability, measured in cubic meters.3.
Article 5. Approval of survey and evaluation of general information for Group IV minerals in areas without auctioning mining rights
1. The selection of organizations and individuals to approve survey and evaluation of general information for Group IV minerals in areas without auctioning mining rights shall be carried out in the following priority order:
a) Organizations and individuals meeting the financial capacity conditions stipulated in Point c Clause 2 Article 53 of the Minerals Law;
b) In cases where more than one organization or individual meets the conditions stipulated in Point a of this clause, priority shall be given to approving survey and evaluation of general information for Group IV minerals for the organization or individual whose application meets the conditions stipulated in Clause 2 of this Article and was submitted first.
2. For the case provided for in Clause 1, Article 72 of the Law on Geology and Minerals, the components of the application documents for approval to survey and evaluate general information on Group IV minerals include:
a) Original: A request for approval to survey and evaluate general information on Group IV minerals;
b) A certified copy or a copy accompanied by the original for comparison or an electronically certified copy from the original: Documentation proving the owner's capital as prescribed in Article 9 of Decree No. 158/2016/NĐ-CP dated November 29, 2016, issued by the Government detailing the implementation of certain provisions of the Minerals Law.
3. For the case provided for in Clause 2, Article 72 of the Law on Geology and Minerals, the components of the application documents for approval to survey and evaluate general information on Group IV minerals include:
a) Original: Request for approval of survey and evaluation of general information for Group IV minerals; introduction letter from the project investor, construction project, construction item, and emergency mobilization measures as stipulated in Points a and b Clause 2 Article 72 of the Geology and Mineral Law;
b) Certified copy or copy with original for comparison or certified electronic copy from the original: A document approving the selection as a contractor.
4. The procedures for approving surveying and evaluating general information on Group IV minerals are carried out as follows:
a) Organizations and individuals requesting approval of survey and evaluation of general information for Group IV minerals shall submit one set of documents in accordance with Clause 2 and Clause 3 of this Article to the specialized agency on geology and minerals under the provincial People's Committee. If the documents are complete, the specialized agency on geology and minerals under the provincial People's Committee shall accept the documents in accordance with regulations. If the documents are incomplete, they will not be accepted, and the reasons for non-acceptance will be clearly stated in the supplementary and completion request form in accordance with the Government's regulations on accepting administrative procedures.
b) Within no more than five working days from the date of receiving complete documents, the specialized agency on geology and minerals under the provincial People's Committee shall be responsible for checking the coordinates and area of the proposed survey and evaluation site and conducting on-site inspections (if necessary); if necessary, send a document to seek opinions from relevant agencies regarding prohibited mining areas and temporarily prohibited mining areas for the proposed survey and evaluation site.
The time of on-site inspection (if any) shall be decided by the specialized agency on geology and minerals under the provincial People's Committee but must be completed before approving the survey and evaluation of general information for Group IV minerals as stipulated in Point d of this clause.
c) Within no more than three working days from the date the specialized agency on geology and minerals under the provincial People's Committee sends the document seeking opinions as stipulated in Point b of this clause, the agency sought for opinions shall be responsible for responding in writing to related issues. After the deadline specified in this clause, if the agency sought for opinions does not provide a written response, it shall be deemed to have agreed and shall bear responsibility for the relevant contents in the mining permit application.
d) Within no more than one working day from the completion of the contents specified in points b and c of this clause, the specialized agency on geology and minerals under the provincial People's Committee shall approve or disapprove the survey and evaluation of general information for Group IV minerals and notify the organization or individual applying for approval of the results of the survey and evaluation of general information for Group IV minerals. In case of non-approval, a written response must be provided with clear reasons stated.
Article 6. Confirmation of Survey and Evaluation Results for Group IV Minerals
1. The application dossier for confirmation of survey and evaluation results for Group IV minerals includes the original: Request for confirmation of survey and evaluation results for Group IV minerals; report on the results of survey and evaluation of general information for Group IV minerals (in cases where paper applications are submitted, an electronic copy must be attached).
2. The procedures for confirming survey and assessment results for common information on Group IV minerals shall be carried out as follows:
a) The organization or individual applying for confirmation of survey and evaluation results for Group IV minerals shall submit one set of application dossier in accordance with Clause 1 of this Article to the specialized agency on geology and minerals under the provincial People's Committee. If the dossier is complete, the specialized agency on geology and minerals under the provincial People's Committee shall accept it according to regulations. If the dossier is incomplete, it will not be accepted, and the reasons for non-acceptance will be clearly stated on the supplementary request form in accordance with the Government's regulations on administrative procedures.
b) Within no more than ten days from the date of receiving the dossier, the specialized agency on geology and minerals under the provincial People's Committee shall be responsible for checking, reviewing the dossier, and assessing the contents of the report on the results of survey and evaluation of general information for Group IV minerals.
When necessary, the specialized agency on geology and minerals under the provincial People's Committee may seek opinions from experts and related agencies regarding the contents of the report on the results of survey and evaluation of general information for Group IV minerals. The time taken to seek opinions does not count towards the dossier assessment period.
c) Within no more than five working days from the date the specialized agency on geology and minerals under the provincial People's Committee issues a document seeking opinions in accordance with point b of this clause (if applicable), the agency sought for opinions shall provide a written response on relevant issues. After the deadline stipulated in this clause, if the agency sought for opinions does not provide a written response, it will be deemed to have agreed and shall bear responsibility for the relevant contents.
d) In cases where the contents of the report on the results of survey and evaluation of general information for Group IV minerals need to be supplemented or completed, the specialized agency on geology and minerals under the provincial People's Committee shall issue a document requesting supplementation or completion, specifying the required contents. The request for supplementation or completion shall only be made once. If the report on the results of survey and evaluation of general information for Group IV minerals does not meet the initial requirements after supplementation or completion, further supplementation or completion may be requested, but no new requirements shall arise.
In cases where, after re-supplementation or re-completion, the report on the results of survey and evaluation of general information for Group IV minerals still fails to meet the requirements, the specialized agency on geology and minerals under the provincial People's Committee shall suspend the assessment and return the application dossier for confirmation of survey and evaluation results for Group IV minerals. Organizations or individuals in such cases have the right to resubmit the dossier, which will be treated as a new submission.
đ) Within no more than two working days from the completion of the contents specified in points b, c, and d of this clause, the specialized agency on geology and minerals under the provincial People's Committee shall decide whether to confirm or not confirm the results of survey and evaluation of general information for Group IV minerals and notify the organization or individual applying for confirmation of the results of the survey and evaluation of general information for Group IV minerals. In case of non-confirmation, a written response must be provided with clear reasons stated.
Article 7. Templates for documents, maps, and plans in the exploitation of Group IV minerals
1. The application form in the dossier related to the exploitation of Group IV minerals shall be carried out as follows:
a) The application form requesting approval for surveying and evaluating general information on Group IV minerals as stipulated in Form No. 01 attached to this Circular;
b) The application form requesting confirmation of the results of surveying and evaluating general information on Group IV minerals as stipulated in Form No. 02 attached to this Circular;
c) The application form requesting issuance of a Mining Exploitation Permit; as stipulated in Form No. 03 attached to this Circular;
2. The map templates in the dossier for issuing a mining exploitation permit for Group IV minerals shall be carried out as follows:
a) The map shall be prepared according to the provisions of Form No. 04 attached to this Circular;
b) The maps shall be prepared based on the VN-2000 coordinate system.
3. Templates for permits, decisions, approval documents, and confirmation documents in the exploitation of Group IV minerals shall be carried out as follows:
a) The Mining Exploitation Permit for Group IV minerals as stipulated in Form No. 05 attached to this Circular;
b) The Mining Exploitation Permit for Group IV minerals (extension) as stipulated in Form No. 06 attached to this Circular;
c) The approval document for surveying and evaluating general information on Group IV minerals as stipulated in Form No. 07 attached to this Circular;
d) The confirmation document for the results of surveying and evaluating general information on Group IV minerals as stipulated in Form No. 08 attached to this Circular;
4. Report templates in the exploitation of Group IV minerals shall be carried out as follows:
a) The report on the results of mineral exploitation activities for Group IV minerals as stipulated in Form No. 09 attached to this Circular;
b) The report on the results of surveying and evaluating general information on Group IV minerals as stipulated in Form No. 10 attached to this Circular;
c) Before February 1st each year, organizations and individuals must submit annual periodic reports on the results of mineral exploitation activities for Group IV minerals to the specialized agencies on geology and minerals under the provincial People's Committees. In cases where there are requirements from state management agencies on minerals, organizations and individuals engaged in mineral activities must prepare ad hoc reports.
5. The exploitation plan for Group IV minerals shall be carried out as stipulated at Form No. 11 attached to this Circular.
Chapter III
IMPLEMENTING PROVISIONS
Article 8. Effective Date
This Circular takes effect from January 15, 2025.
Article 9. Responsibility for Implementation
1. Ministries, ministerial-level agencies, government agencies, and all levels of People's Committees are responsible for directing the implementation of this Circular.
2. Specialized agencies on geology and minerals under provincial People's Committees are responsible for assisting the People's Committees in implementing this Circular locally.
3. Organizations and individuals concerned are responsible for implementing this Circular.
|
|
DEPUTY MINISTER |
ANNEX
TEMPLATE FOR THE MINING EXPLOITATION PERMIT FOR GROUP IV MINERALS, DOCUMENTS IN THE SURVEY AND ASSESSMENT Dossier OF GENERAL INFORMATION ON MINERALS, ISSUANCE OF MINING EXPLOITATION PERMITS FOR GROUP IV MINERALS
(Attached to Circular No. 01/2025/TT-BTNMT dated January 15, 2025 of the Minister of Natural Resources and Environment)
|
Form No. 01 |
Application form requesting approval for surveying and evaluating general information on Group IV minerals |
|
Form No. 02 |
Application form requesting confirmation of the results of surveying and evaluating general information on Group IV minerals |
|
Implementation Report of Production Projects of Supporting Industry Products Confirmed with Incentives |
Application form requesting issuance of a Mining Exploitation Permit for Group IV minerals |
|
Form number 04 |
Map in the dossier for issuing a Mining Exploitation Permit for Group IV minerals |
|
Form number 05 |
Mining Exploitation Permit for Group IV minerals |
|
Form number 06 |
Mining Exploitation Permit for Group IV minerals (extension) |
|
Form No. 07 |
Approval document for surveying and evaluating general information on Group IV minerals |
|
Form No. 08 |
Confirmation document for the results of surveying and evaluating general information on Group IV minerals |
|
Form No. 09 |
Report on the results of mineral exploitation activities for Group IV minerals |
|
Form No. 10 |
Report on the results of surveying and evaluating general information on Group IV minerals |
|
Form No. 11 |
Plan for exploiting Group IV minerals |
Form No. 01: Application form requesting approval for surveying and evaluating general information on Group IV minerals
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness
---------------
Place name, date... month... year...
APPLICATION FORM REQUESTING APPROVAL FOR SURVEYING AND EVALUATING
GENERAL INFORMATION ON GROUP IV MINERALS
Respected Department:1 ....................................
…………… (Name of organization, individual)……………
Headquartered at: …
Telephone: …Fax:…
Business Registration Certificate number …dated…… month ……year ……issued by (name of business registration certificate issuing agency) ……issued; or Investment License number…dated ……month……year ……issued by ……(name of investment license issuing agency) …issued.
Contractor for construction2 …(Project name, construction, construction component, emergency mobilization measures specified in point a, point b Clause 2 Article 72 of the Law on Geology and Minerals) ………………………………
Request to conduct surveys and evaluations of general information on Group IV minerals …(name of Group IV mineral) ……in the area …… belonging to commune…… district…… province…… with the following contents:
1. Survey and evaluation scope:… (area, coordinates of the proposed survey and evaluation area) …(A proposed survey and evaluation area map will be attached).
2. Implementation period: from …day …month …year …to …day …month …year …
3. Methods and technical measures:
3.1. Field survey: …… (length of route)…… km route.
3.2. Construction works:…… (List of works, quantities)……
3.3. Sampling work: ……(number, type of samples) ………………
…… (Name of organization, individual) …… commits to comply with the regulations of the law on geology and minerals and other relevant laws./.
|
|
Organization, individual |
___________________
1 Name of the Department responsible for geology and mineral affairs.
2 Only applicable to organizations specified in Clause 2 Article 72 of the Law on Geology and Minerals.
Form No. 02: Application form requesting confirmation of the results of surveying and evaluating general information on Group IV minerals
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness
---------------
Place name, date... month... year...
APPLICATION FORM REQUESTING CONFIRMATION OF THE RESULTS OF SURVEYING AND EVALUATING
GENERAL INFORMATION ON GROUP IV MINERALS
Respected Department:3 ....................................
…… (Name of organization, individual)……
Headquartered at: …
Telephone: …Fax:…
Business Registration Certificate number …dated……month…… year…… issued by …… (name of business registration certificate issuing agency)…… issued; or Investment License number …dated ……month……year …… issued by…… (name of investment license issuing agency) …issued.
Contractor for construction4 ……………… (Project name, construction, construction component, emergency mobilization measures specified in point a, point b Clause 2 Article 72 of the Law on Geology and Minerals) …………………………
Based on Document No. …… dated…… month…… year…… of the Department5 …approving the survey and evaluation of general information on minerals (name of Group IV mineral) … at the area belonging to commune … district … province …
Request confirmation of the survey results and general information assessment for mineral … (name of Group IV mineral) … at the area … belonging to commune … district … province … with the main contents as follows:
1. Survey area scope: … (coordinates of the proposed survey area) …;
2. Quantity and quality of minerals in the survey area: …
There is a report on the survey results and general information assessment for mineral … (name of Group IV mineral) … at the area … attached
…… (Name of organization, individual)… commit that all figures and information in the report are truthful and accurate and bear full responsibility under the law for the contents, information, and figures in the survey and general information assessment report for mineral …(name of Group IV mineral) … at the area …
|
|
Organization, individual |
___________________
3 Name of the Department responsible for geology and mineral affairs.
4 Only applicable to organizations specified in Clause 2 Article 72 of the Law on Geology and Minerals.
5 Name of the Department responsible for geology and mineral affairs.
MODEL NUMBER 03: APPLICATION FOR ISSUE OF MINERAL EXPLORATION LICENSE GROUP IV
SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness
---------------
Place name, date... month... year...
APPLICATION FOR ISSUE OF EXPLORATION LICENSE
MINERAL GROUP IV
Respected: Provincial People's Committee (City People's Committee) …
………… (Name of organization, individual)…………
Headquartered at: …
Telephone: …Fax: …
Business Registration Certificate number … dated … month … year … issued by … (name of business registration certificate issuing agency)… issued; or Investment License number … dated … month … year … issued by …(name of investment license issuing agency) …issued.
Report on the survey results and general information assessment for mineral (report on the exploration results for mineral) …(name of Group IV mineral) … at commune … district … province … has been …(approving authority) … approved, recognized, or confirmed according to document number … dated … month … year …
Quantity (or reserve) …(name of mineral) … approved, recognized, or confirmed: … (tons, m3,...).
Request issuance of mineral exploitation license for … (name of Group IV mineral)… at the area … belonging to commune … district … province … with the following contents:
1. Exploitation area size: … (ha, km2), limited by corner points: … with coordinates determined on the mining area map attached.
2. Quantity (reserve) of mineral included in the exploitation design: … (tons, m3,...).
3. Quantity (reserve) of mineral to be exploited: … (tons, m3,...).
4. Exploitation method: Open-pit mining.
5. Exploitation capacity: … (tons, m3,...)/year.
6. Depth of exploitation: from level … m to level … m.
7. Exploitation period: … years (months), starting from the date of signing the license. Among which, the construction period of the mine is: … years (months).
8. Project, works, project components, emergency measures using minerals6: ………………………………………………………………………………
……(Name of organization, individual)…… commits to comply with the regulations of the law on geology and minerals and other relevant laws./.
|
|
Organization, individual |
___________________
6 Clearly state the name of the project, work, project component, and emergency measures. This section only applies to organizations specified in Clause 2 Article 72 of the Law on Geology and Minerals.
MODEL NUMBER 04: MAP IN THE APPLICATION FOR ISSUE OF MINERAL EXPLORATION LICENSE GROUP IV
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE)
The scale of the map shall be implemented as follows:
1. For areas with a size of 05 km2 or more, the area map is prepared based on the extract from the topographic map, VN-2000 coordinate system, with a scale not less than 1:50,000.
2. For areas with a size of 02 km2 to less than 5 km2, the area map is prepared based on the extract from the topographic map, VN-2000 coordinate system, with a scale not less than 1:25,000.
3. For areas with a size of 0.5 km2 to less than 2 km2, the area map is prepared based on the extract from the topographic map, VN-2000 coordinate system, with a scale not less than 1:10,000.
4. For areas with a size smaller than 0.5 km2, the area map is prepared based on the extract from the topographic map, VN-2000 coordinate system, with a scale not less than 1:5,000.
___________________
7 Name of the type of mineral permitted to be exploited as stipulated in the mineral exploitation license already issued.
8 Name of the mineral deposit as stipulated in the mineral exploitation license already issued.
MODEL NUMBER 05: MINERAL EXPLORATION LICENSE GROUP IV
|
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE) … |
SOCIALIST REPUBLIC OF VIET NAM |
|
Number: ……/GP-UBND |
Place name, date... month... year... |
MINERAL EXPLORATION LICENSE GROUP IV
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE) …
Pursuant to the Law on Organization of Local Administration dated June 19, 2015;
Pursuant to the Law on Geology and Minerals dated November 29, 2024;
Pursuant to the Law on Minerals dated November 17, 2010;
Pursuant to Decree No. 158/2016/NĐ-CP dated November 29, 2016 of the Government detailing the implementation of certain provisions of the Minerals Law;
Pursuant to Decree No. .../2025/NĐ-CP dated ... month ... year 2025 of the Government detailing some provisions of the Law on Geology and Minerals regarding the exploitation of mineral group IV;
Pursuant to Circular No. ... 2025/TT-BTNMT dated ... month ... year 2025 of the Minister of Natural Resources and Environment detailing some provisions of the Law on Geology and Minerals regarding the exploitation of mineral group IV;
Pursuant to the approval document, selection document as the contractor for the project (work, project component, emergency measures);9 …………………………;
Pursuant to the report on the survey results and general information assessment for the mineral to be exploited (report on the exploration results for mineral) approved, recognized, or confirmed at …;
Pursuant to the Investment Certificate (or Decision on Approval of Investment Orientation) No. ... dated ... month ... year ... issued by … for the investment project to exploit the … mine of …;10;
Pursuant to Decision No. …/QĐ-UBND dated … month … year … of the Provincial People's Committee (City People's Committee) … approving the environmental impact assessment report for the mineral exploitation project at the … mine (mine name) located in commune … district … province …; 11;
Pursuant to Decision No. …/QĐ-UBND dated … month … year … of the Provincial People's Committee (City People's Committee) … approving the non-auction area for mineral exploitation rights;12;
Pursuant to Decision No. ……./QĐ-UBND dated … month … year … of the Provincial People's Committee (City People's Committee) … approving the auction result for mineral exploitation rights at the … mine (mine name) … located in commune … district … province …; 13;
Considering the application for issuance of the mineral exploitation license dated … month … year … submitted by … (Name of organization, individual) …;
At the proposal of the Director of the Department14 ................
DECISION:
Article 1. Permit … (Name of organization, individual) … to exploit minerals at the … mine … (mine name) … located in commune … district … province … with the following contents:
1. Permitted minerals to be exploited: … (name of mineral) ........
2. Mineral exploitation method: … (open-pit, …).
3. Exploitation area size: … (ha, km2) limited by corner points … with coordinates determined according to Appendix 1 and Appendix 2 attached to this license.
4. Exploitation depth: from level … (m) to level … (m).
5. Quantity (reserve) of minerals permitted to be exploited: … (tons, m3,...).
6. Exploitation capacity: … (tons, m3,...)/year.
7. Exploitation period: … years … months.
8. Project, works, project components, emergency measures using minerals15: ....................................................................................
Article 2. ...................... (Name of organization, individual) … shall be responsible for:
1. Paying the fee for issuing the mineral exploitation license and related fees as prescribed.
2. Paying the fee for granting mineral exploitation rights as prescribed.
3. Depositing a guarantee fund for rehabilitation and environmental restoration during mineral exploitation activities.
4. Other necessary requirements for organizations and individuals granted the license (if any).
Article 3. This License becomes effective from the date of signature.
|
|
||| Signed by the PROVINCIAL PEOPLE'S COMMITTEE (Municipality) … |
___________________
9 Clearly state the name of the project, work, project component, and emergency measures. This section only applies to organizations specified in Clause 2 Article 72 of the Law on Geology and Minerals.
10 ||| In the case provided for in Clause 1, Article 72 of the Law on Geology and Mineral Resources.
11 ||| In the case provided for in Clause 1, Article 72 of the Law on Geology and Mineral Resources.
12 ||| In the case where there is no auction for the right to exploit mineral resources.
13 ||| In the case where there is an auction for the right to exploit mineral resources.
14 Name of the Department responsible for geology and mineral affairs.
15 ||| Clearly state the name of the project, construction works, sub-works, emergency mobilization measures. This section only applies to cases where permits are issued to organizations as specified in Clause 2, Article 72 of the Law on Geology and Mineral Resources.
||| PROVINCIAL PEOPLE'S COMMITTEE (Municipality) …
ANNEX 1
||| BOUNDARIES, COORDINATES OF THE MINERAL RESOURCES EXPLORATION AREA
||| (Attached to Mining Permit No. …/GP-UBND dated ... month ... year of the Provincial People's Committee (Municipality) …)
|
No. |
||| Name of corner point |
VN-2000 System |
|
|
X(m) |
Y(m) |
||
|
1 |
|
|
|
|
2 |
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE)
Appendix 2
___________________
16 ||| Name of mineral type permitted to be exploited as stipulated in the mining permit.
17 ||| Name of mineral deposit as stipulated in the mining permit.
||| FORM NO. 06: Mining Permit for Group IV Minerals (Renewal)
|
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE) … |
SOCIALIST REPUBLIC OF VIET NAM |
|
Number: ……/GP-UBND |
Place name, date... month... year... |
MINERAL EXPLORATION LICENSE GROUP IV
||| (RENEWAL)
||| PROVINCIAL PEOPLE'S COMMITTEE (Municipality) …
Pursuant to the Law on Organization of Local Administration dated June 19, 2015;
Pursuant to the Law on Geology and Minerals dated November 29, 2024;
Pursuant to the Law on Minerals dated November 17, 2010;
Pursuant to Decree No. 158/2016/NĐ-CP dated November 29, 2016 of the Government detailing the implementation of certain provisions of the Minerals Law;
||| Pursuant to Decree No. .../2025/NĐ-CP dated … month … year 2025 of the Government detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| Pursuant to Circular No. .../2025/TT-BTNMT dated … month … year 2025 of the Minister of Natural Resources and Environment detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| Pursuant to Mining Permit No. …/GP-UBND dated … month … year … of the Provincial People's Committee (Municipality) …;
||| Considering the application for renewal of the mining permit submitted by … (Name of organization, individual) … on … month … year …;
At the proposal of the Director of the Department18 ................................
DECISION:
Article 1. ||| Renew Mining Permit No. …/GP-UBND dated … month … year … to (Name of organization, individual) ||| … continue exploiting …(name of mineral) ||| … at commune ..., district ..., province ... until … day … month … year …
Article 2. …..(Name of organization, individual) … shall be responsible for:
||| 1. Pay the fee for renewing the mining permit and related fees according to current regulations.
||| 2. Continue to exploit the remaining volume (reserves) of minerals as stipulated in Mining Permit No. …/GP-UBND dated … month … year …
||| 3. Strictly comply with all provisions set forth in Mining Permit No. …/GP-UBND dated … month … year …
Article 3. ||| This permit takes effect from the date of signature and is an integral part of Mining Permit No. …/GP-UBND dated … month … year … of the Provincial People's Committee (Municipality)
|
Place of Receipt: |
||| Signed by the PROVINCIAL PEOPLE'S COMMITTEE (Municipality) … |
___________________
18 ||| Name of Department responsible for geology and mineral resources sector
||| FORM NO. 07: Document Approving Survey and General Assessment of Information for Group IV Minerals
|
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE) … |
SOCIALIST REPUBLIC OF VIET NAM |
|
||| No.: …/TB-… |
Place name, date... month... year... |
NOTICE
||| Regarding approval of survey and general assessment of information for Group IV minerals …
(name of Group IV mineral) ||| …in the area …
Respectfully submitted to: ... (Name of organization, individual) ……….
||| - Based on the Law on Geology and Mineral Resources dated November 29, 2024;
||| - Based on Decree No. …/2025/NĐ-CP dated … month … year 2025 of the Government detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| - Based on Circular No. …/2025/TT-BTNMT dated … month … year 2025 of the Minister of Natural Resources and Environment detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| - Considering the proposal of …(Name of organization, individual)||| …in the request for survey and general assessment of information for Group IV minerals (name of Group IV mineral) ||| …in the area … belonging to commune … district … province …;
Science and Technology in Report No.20 ||| … approve …(Name of organization, individual) ||| to conduct survey and general assessment of information for Group IV minerals … (name of Group IV mineral) ||| …in the area … belonging to commune … district … province … with the main contents as follows:
||| 1. Scope of survey and assessment: … (area, coordinates of the proposed survey and evaluation area) …(A proposed survey and evaluation area map will be attached).
2. Implementation period: from …day …month …year …to …day …month …year …
3. Methods and technical measures:
||| 3.1. Field survey: … (length of route) ||| …km route
||| 3.2. Construction works: … ||| (volume (m, m3)/number of works) ….…….….….
||| 3.3. Sampling work: … ||| (quantity, type of samples) ….….….….….….
….…. (Name of organization, individual)||| …is responsible for fully implementing the survey and assessment contents prescribed in Article 4 of Circular No. …/2025/TT-BTNMT dated … month … year 2025 of the Minister of Natural Resources and Environment detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals; bears full responsibility under the law for the truthfulness of the survey and assessment contents, information, and data.
….…. (Name of organization, individual) ||| …must notify the Department21 ||| …and the People's Committee of commune … ||| (Name of commune, ward, town where survey and assessment take place) ||| …before conducting the survey and assessment./.
|
|
DIRECTOR |
___________________
19 Name of the Department responsible for geology and mineral affairs.
20 Name of the Department responsible for geology and mineral affairs.
21 Name of the Department responsible for geology and mineral affairs.
||| DEPARTMENT22 ||| PROVINCIAL PEOPLE'S COMMITTEE (Municipality) …
ANNEX
||| BOUNDARIES, COORDINATES OF THE AREA
||| Survey and general assessment of information for Group IV minerals
......... (name of Group IV mineral)||| …in the area …
||| (Attached to Notification No. …/TB- dated … month … year
||| of the Department23.................................... )
|
No. |
Name ||| corner point |
VN-2000 System |
|
|
X(m) |
Y(m) |
||
|
1 |
|
|
|
|
2 |
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
___________________
22 Name of the Department responsible for geology and mineral affairs.
23 Name of the Department responsible for geology and mineral affairs.
||| FORM NO. 08: Document Confirming the Results of Survey and General Assessment of Information for Group IV Minerals
|
PROVINCE PEOPLE'S COMMITTEE (CITY PEOPLE'S COMMITTEE) … |
SOCIALIST REPUBLIC OF VIET NAM |
|
||| No.: …/XN-… |
Place name, date... month... year... |
Enterprise (in capital letters): ...
||| Results of survey and general assessment of information for Group IV minerals
......... (name of Group IV mineral) ||| …in the area …
Respectfully submitted to: ... (Name of organization, individual) .........
||| - Based on the Law on Geology and Mineral Resources dated November 29, 2024;
||| - Based on Decree No. …/2025/NĐ-CP dated … month … year 2025 of the Government detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| - Based on Circular No. …/2025/TT-BTNMT dated … month … year 2025 of the Minister of Natural Resources and Environment detailing certain provisions of the Law on Geology and Mineral Resources regarding the exploitation of Group IV minerals;
||| - Considering the proposal of … (Name of organization, individual)||| …in the request for confirmation of results of survey and general assessment of information for Group IV minerals … (name of Group IV mineral) ||| …in the area … belonging to commune … district … province …;
Science and Technology in Report No.25 ||| … confirm the results of survey and general assessment of information for Group IV minerals … (name of Group IV mineral)||| …in the area belonging to commune … district … province … with the main contents as follows:
||| 1. Report title: …
||| 2. Organization, individual conducting survey and assessment: …
||| 3. Type of mineral: … ||| (recorded according to the name of mineral specified in Point d, Clause 1, Article 6) .........
||| 4. Volume: …m3
||| 5. Quality of mineral: … ||| (mineral meets quality requirements for …).........
||| 6. Area determining mineral volume: …(ha, km2) defined by corner points …with coordinates determined in the attached appendix to this confirmation document.
||| 7. Depth determining mineral volume: from level …(m) to level …(m).
......... (Name of organization, individual)||| …may use these information and data for Group IV mineral exploitation activities in accordance with the law./.
|
|
DIRECTOR |
___________________
24 Name of the Department responsible for geology and mineral affairs.
25 Name of the Department responsible for geology and mineral affairs.
||| DEPARTMENT26 ||| PROVINCIAL PEOPLE'S COMMITTEE (Municipality) …
ANNEX
||| BOUNDARIES, COORDINATES OF THE AREA
Determination of mineral volume
………. (name of Group IV mineral)||| …in the area …
(Attached to Confirmation Document No. …/XN-…dated … month … year
||| of the Department27 ……….……….………. )
|
No. |
Name |
VN-2000 System |
|
|
X(m) |
Y(m) |
||
|
1 |
|
|
|
|
2 |
|
|
|
|
3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
___________________
26 Name of the Department responsible for geology and mineral affairs.
27 Name of the Department responsible for geology and mineral affairs.
FORM NO. 09: Report on Results of Mineral Exploitation Activities for Group IV Minerals
|
ORGANIZATION, INDIVIDUAL PERMITTED TO EXPLOIT MINERALS |
SOCIALIST REPUBLIC OF VIET NAM |
|
No. ……/BC-……. |
Place name, date... month... year... |
REPORT
Results of mineral exploitation activities
Respectfully submitted to: Provincial People's Committee (Municipality) …
I. General Part
1. Organization, individual: …
||| 2. Business form: …
||| 3. Address: …;
||| Telephone: …; Fax: …
4. Legal Representative:
||| - Full name …;
||| - Year of birth …
||| 5. Mining Permit No.: … dated … month … year … renewed according to Mining Permit (Renewal) No. … dated … month … year (if applicable):
||| - Type of mineral permitted to exploit: …;
||| - Issuing authority …;
- Location of the mine: village ..., commune (ward, town) ..., district (city, province) ..., province (city) ...;
- Method of exploitation: ...(open pit/mine shaft/ ...);
- Area of exploitation zone: ...(m2, ha, km2);
- Depth of exploitation: from level ...m to level ...m;
- Quantity (reserves) of minerals permitted for exploitation: ...;
- Permitted exploitation capacity: ...:(tons/year, m3/year, m3/day, night);
- Term of exploitation: ...(months, years).
II. Results of mineral exploitation activities
II.1. Results of exploitation activities from day ... month ... year ...28 This Labour Contract is made into (02) two copies:29:
1. Total payment for the right to exploit minerals according to the approved decision ... (VND).
2. Total amount deposited for environmental restoration during mineral exploitation (if applicable):...(VND).
3. Total amount refunded for basic geological investigation costs and mineral exploration costs according to the approved decision (if applicable): ...(VND).
4. Total investment capital: ...(VND).
5. Actual production volume of exploited minerals: ...(tons, m3).
6. Remaining quantity (reserves) of minerals permitted for exploitation at the time of reporting: ...(tons, m3).
7. Average exploitation cost: ...(VND/ton, m3).
8. Total volume of minerals consumed: ...(tons, m3).
9. Total revenue: ...(VND).
10. Total amount paid to the State budget: ...(VND).
Where:
- Resource tax: ...(VND);
- Environmental tax: ...(VND);
- Land rental fee: ...(VND)
- Payment for the right to exploit minerals: ...(VND);
- Environmental protection fee during mineral exploitation: ...(VND);
- Corporate income tax: ...(VND);
- Others (if applicable): ...
11. Compensation and resettlement support work for organizations and individuals currently using land that has been reclaimed for the implementation of the mineral exploitation project (if applicable) ...
12. Number of workers employed (clearly state the number of local workers in the commune where the mineral exploitation activity takes place) and average annual income ...
13. Funding for infrastructure construction support (if applicable)...(VND).
14. Funding for public works construction (schools, kindergartens...) (if applicable)...(VND).
16. Measures to reduce environmental pollution applied during exploitation /environmental recovery solutions after exploitation ...
II.2. Results of exploitation activities in the reporting year30
1. Actual production volume of exploited minerals in the year: ...(tons, m3),
2. Average exploitation cost: ...(VND/ton, m3),
3. Total volume of minerals consumed in the year:...(tons, m3),
4. Total revenue: ...(VND),
5. Total amount paid to the State budget: ...(VND),
Where:
- Resource tax: ...(VND);
- Environmental tax: ...(VND);
- Land rental fee: ...(VND)
- Payment for the right to exploit minerals: ...(VND);
- Environmental protection fee during mineral exploitation: ...(VND);
- Corporate income tax:...(VND);
- Others (if applicable): ...
6. Amount of deposit for environmental restoration during mineral exploitation already paid (if applicable): ...(VND).
7. Compensation and resettlement support work for organizations and individuals currently using land that has been reclaimed for the implementation of the mineral exploitation project (if applicable)...
8. Number of workers employed (clearly state the number of local workers in the commune where the mineral exploitation activity takes place) and average annual income ...
9. Funding for infrastructure construction support (if applicable) ...(VND).
10. Funding for public works construction (schools, kindergartens...) (if applicable) ...(VND).
11. Measures to reduce environmental pollution applied during exploitation /environmental recovery solutions after exploitation ...
II.3. General Evaluation
General evaluation on the application of technology and equipment in actual exploitation. Evaluation of changes in quality and quantity (reserves) of minerals actually in the reporting period compared to approved geological documents. If there are changes (increase/decrease) in quantity (reserves) or changes in quality discovered during exploitation, a report must be prepared with accompanying documents and tables to prove the findings.
|
|
Organization, individual |
___________________
28 Date of issuance of the mining exploitation permit
29 Reporting date
30Only applicable to periodic reports, this content does not need to be implemented in reports in the application dossier for extension, adjustment, or return of the Group IV mineral exploitation permit.
Form No. 10: Report on Survey and Assessment of General Information for Group IV Minerals
|
NAME OF THE ORGANIZATION, INDIVIDUAL
REPORT ON SURVEY AND ASSESSMENT OF GENERAL INFORMATION
for mineral ... (name of Group IV mineral) ........
Place name, month... year... |
|
NAME OF THE ORGANIZATION, INDIVIDUAL
REPORT ON SURVEY AND ASSESSMENT OF GENERAL INFORMATION for mineral ... (name of Group IV mineral) ........
Place name, month... year... |
CONTENTS OF THE REPORT
PART I
- Legal basis for establishing the report.
- Project proponent; consulting unit (if any).
- Objectives and tasks of the survey work, time frame for implementation.
- Methods, main completed works volume, achieved volume.
PART 1
OVERVIEW OF THE SURVEY AREA
- Administrative and geographical location of the survey area, boundaries and surveyed area size, evaluation;
- Overview of topography, river network, population situation, economy, culture; transportation conditions, industrial and agricultural infrastructure.
- Overview of research work, history of discovery, investigation, exploration or mining activities carried out previously (if any).
- General geological characteristics of the region, specific geological features of the survey area.
Chapter 2
METHODS AND VOLUME OF WORK COMPLETED
1. Surveying work
- Clearly state objectives, tasks, technical content, volume of each component implemented and results achieved.
- Products: Original measurement files, original field books of various types, coordinate and elevation assignment sheets for base points; comprehensive calculation tables, topographic maps and cross-sections.
2. Geological work:
2.1. Geological route (if applicable)
- Clearly state objectives, tasks, methods of implementation carried out in practice, results achieved and volume completed.
- Products: Original documents on geological diaries, route maps attached, and photographs of important outcrops.
2.2. Construction of survey works, assessment
- Excavation works (outcrops, pits, trenches): Clearly state purpose, tasks, and basis for arranging works; technical specifications applied; evaluate results, effectiveness of each type of work; quantity and volume completed.
- Drilling works: Clearly state purpose, tasks, and basis for arranging drilling networks; drilling equipment and technology; core recovery rate through product layers; evaluate drilling work effectiveness; quantity and volume completed.
- Products: Comprehensive original books of completed works; layout drawings of excavation works (outcrops, pits, trenches); geological log books of drill holes; drilling logs (drill logs); comprehensive drill hole layout drawings; photographs of excavation works, core samples.
2.3. Sampling, processing, and analysis work
- Clearly state objectives, tasks, methods of implementation, and specific volumes of each type of sample; sampling, processing, and analysis methods applied include:
+ Sampling: Accurately describe the sampling process carried out. For each type of sample, clearly state the purpose, location, method, sample volume (size), quantity completed (this process must be consistent with actual recording documentation).
+ Sample processing: Clearly describe the processing procedure, simplified diagram of actual sample processing.
+ Sample analysis: Fully describe analytical criteria, analysis methods, number of samples, laboratories conducting analysis for each type of sample.
+ Evaluate the quality of analysis results according to current regulations on control sample types, quantities, calculation tables, and error assessments.
- Evaluate the usability of analytical data in interpreting and calculating mineral volumes.
- Products: Original books on sampling, processing, and analysis work; sample submission forms; analysis result certification forms.
2.4. Hydrogeological and engineering geological work (if applicable)
- Clearly state objectives, tasks, methods of implementing actual work carried out (simple monitoring of hydrogeology-engineering geology; surface and groundwater level monitoring at stations) and volume completed.
- Products: Original books related to hydrogeology-engineering geology work carried out (Drilling and excavation hydrogeology-engineering geology monitoring logs; surface and groundwater level monitoring logs; soil mechanical property sample collection logs...).
3. Changes in area, methods, volume
Clearly state reasons and assess the impact of changes compared to approved survey information for Group IV minerals (if any).
Chapter 3
QUALITY CHARACTERISTICS AND MINERAL VOLUME CALCULATION WORK
- Evaluation of quality, usability of minerals.
- Evaluation of hydrogeological and engineering geological characteristics and mining conditions (if any).
- Mineral volume calculation methods.
- Volume …(m3).
CONCLUSION
- Summarize the main contents of work completed.
- Main results achieved regarding quality, properties, usability, and mineral volume).
ANNEX: ATTACHED DOCUMENTS
1. List of maps, drawings
|
No. |
Number signature of31 |
Drawing name |
Number of Sheets |
|
1 |
|
Topographic map and survey area, ratio 1:2,000 |
|
|
2 |
|
Geological and mineral resource map of the survey area, ratio 1:2,000 or 1:5,000 |
|
|
3 |
|
Plan for calculating mineral volumes, ratio 1:2,000 or 1:5,000 |
|
|
4 |
|
Geological cross-sections, ratio 1:2,000 or 1:5,000 |
|
2. List of records, documents
- Report on completion of surveying work.
- Original documents.
- Documents related to sampling work.
___________________
31 Map and drawing number signatures ensure consistency, ease of search and reference
Form 11: Mining Plan for Group IV Minerals
(NAME OF ORGANIZATION, INDIVIDUAL MINING MINERALS)
*****************
MINING PLAN FOR GROUP IV MINERALS
(name of mineral deposit, located in ..., district ..., province ...)
Place name, year ...
(NAME OF ORGANIZATION, INDIVIDUAL MINING MINERALS)
******************
MINING PLAN FOR GROUP IV MINERALS
(name of mineral deposit, located in ..., district ..., province ...)
|
ORGANIZATIONS AND INDIVIDUALS |
ENTITY PREPARING THE PLAN |
Place name, year ...
GENERAL INFORMATION
1. Information on mineral extraction organization
- Name of organization: …
- Contact address: …
- Telephone: …, Fax:…
- Business registration certificate: …
2. Basis for preparing the Plan
2.1. Legal basis
- Approval documents for land use planning and plans at the local project site (if any).
- Relevant documents from government agencies and project proponents.
- Applied standards and regulations: List relevant standards and regulations.
2.2. Base documents
- Survey and exploration documents for mines, hydrogeology, engineering geology (if any);
- Survey and general information assessment documents for Group IV minerals;
- Other technical documents.
3. Mineral demand
Analyze the mineral demand of projects, works, construction components stipulated in point a and point b, Clause 2, Article 72 of the Law on Geology and Minerals for Group IV minerals and specified in the mining permit issued as a contractor.
4. Necessity and objectives of mining
- Necessity.
- Objectives of exploitation.
5. Forms of investment, location, and land requirements
5.1. Forms of investment and project management
- Determining the form of investment: New investment, renovation, adjustment, or expansion of scale, increase in capacity, technological innovation.
- Determining the form of project management.
5.2. Mine location and land requirements
- Analysis and description of the mine location.
- Land requirements: Determine the need for land, total area, land use structure, and land use schedule.
PART I: ECONOMIC AND TECHNICAL REPORT
I. ECONOMIC AND SOCIAL CHARACTERISTICS AND GEOLOGICAL CHARACTERISTICS OF THE MINE
1. Location, natural geographic characteristics, and socio-economic conditions
Provide a general overview of the location, natural geographic characteristics, and socio-economic conditions of the project area.
2. Geological characteristics of the mine
Summarize the geological characteristics of the mineral deposits, hydrogeology, and engineering geology; supplement research results on hydrogeological and engineering geological features (if available).
3. Quantity (reserves) and quality of minerals
Compile information on the quantity (resources, reserves) and quality of minerals in the study area for the project.
4. Evaluation of the reliability of geological documentation
Evaluate the level of survey, assessment, exploration (if applicable), and the reliability of approved geological documentation serving design work and recommend additional supplements (if applicable).
II. TECHNICAL AND TECHNOLOGICAL SOLUTIONS
1. Boundaries and quantity (reserves) of the mining area
1.1. Mining area boundaries
Describe the principles and determine the boundaries of the mining area: coordinates, depth of extraction, area of the mining area.
1.2. Quantity (reserves) of the mining area
- Calculate the quantity (reserves) of the mining area including: geological quantity within the exploration, survey, and evaluation boundaries or within the permitted boundaries (for permitted mines); mobilized geological quantity; converted quantity according to raw mineral.
- Calculate the quantity of soil needed to be retained for rehabilitation and environmental restoration work.
- Prepare a summary table of technical parameters of the mining system.
2. Work regime, capacity, and mining time
- Determine the work regime of direct and indirect units in the mining stages.
- Determine the mining capacity.
- Time and mining regime: Based on the exploitable quantity (reserves) and designed mining capacity, calculate the appropriate mining time (including basic construction time and mining time).
3. Opening of seams and mining sequence
3.1. Seam opening
Select the position and method of seam opening.
3.2. Mining sequence
- Develop and establish a diagram of the mining work regime.
- Surface clearance work.
- Basic mine construction work (if applicable): Determine the volume, construction time of the mine; detailed calculation of volume, transport length, transportation volume measured in tons, kilometers, earth stripping for basic construction of each layer, each year, each area (if applicable).
- Mining sequence and mining schedule:
+ Establish a suitable mining sequence that complies with technical standards and regulations.
+ Develop annual schedules for earth stripping and mineral extraction.
4. Mining system and mining technology
- Describe the mining technology.
- Prepare a summary table of technical parameters of the mining system.
- List the equipment for mining, basic technical characteristics of major equipment.
5. Mine transportation
- Describe the volume of transportation and reasonable transportation methods. Describe the productivity and number of transportation equipment required annually.
- Describe the transportation route.
6. Waste disposal
- Determine the volume of waste rock unsuitable for use in projects and constructions during mining operations.
- Determine the location and scale of the waste dump; measures to ensure safety and surface drainage.
7. Ancillary facilities serving mining activities
- Power supply system and electrical equipment.
- Water supply and drainage systems.
- Environmental protection facilities.
8. Safety technology
- Describe measures to ensure safety for surrounding communities and structures requiring protection.
- Present technical solutions for safety in mining operations.
9. Production management organization and labor deployment
- Develop a management diagram, organize production units and product consumption.
- Develop staffing plans; labor productivity.
10. Land clearance and resettlement plan (if applicable)
- Calculate land requirements, compensation amounts, land clearance, and resettlement (if applicable).
- Develop a compensation, land clearance, and resettlement plan consistent with current state policies.
- Develop a plan to implement compensation, land clearance, and resettlement consistent with the project's investment schedule.
III. FINANCIAL ANALYSIS
1. Investment capital and basis for calculation
- Present the basis and grounds for establishing investment capital.
- Determine cost items and total investment amount.
- Calculate interest during the basic construction period.
2. Sources of investment funding
Specifically identify sources of investment capital and funding mobilization solutions.
3. Cost
Present the basis and method for determining product costs, calculation indicators, and cost calculation results based on production factors.
4. Taxes and financial obligations to the state
Present taxes, fees, and other financial obligations according to current regulations.
5. Economic and social benefits
Present indicators on labor utilization, contributions to central and local state budgets.
6. Summary economic and technical indicators
Main indicators include: Mobilized geological quantity, mining technology, raw mineral production volume, soil stripping volume, labor productivity, mining area area, basic construction time, total investment, number of workers, and other indicators.
PART II. ENVIRONMENT PROTECTION
1. Evaluation of the selection of technology, project components, and mineral extraction activities that have the potential to negatively impact the environment.
2. Natural conditions, socio-economic factors, biodiversity; assessment of current environmental status; identification of affected objects and sensitive environmental factors at the mineral extraction site.
3. Identification, evaluation, and prediction of major environmental impacts, waste generation during different phases of mineral extraction activities on the environment; scale and nature of waste; impact on biodiversity, natural heritage, historical and cultural relics, and other sensitive factors; impact due to land clearance, relocation, and resettlement (if applicable); impact on riverbeds, banks, and reservoir shores (for areas where mineral extraction affects riverbeds, banks, and reservoir shores); identification and evaluation of environmental incidents.
4. Construction works, measures for collecting, storing, and treating waste.
5. Measures to minimize other negative impacts on the environment; plans for environmental remediation and restoration; plans for compensating biodiversity (if applicable); plans for protecting and preventing landslides along riverbeds, banks, and reservoir shores (for areas where mineral extraction affects riverbeds, banks, and reservoir shores); plans for preventing and responding to environmental incidents.
6. Calculation and determination of funds required to implement environmental remediation and restoration.
7. Environmental remediation and restoration bond.
8. Conclusions, recommendations, and commitments of the mineral extraction organization.
|
|
Organization and individual preparing the Plan |
ANNEX 1: MAPS AND DESIGN DRAWINGS
|
No. |
Serial Number32 |
Drawing name |
Number of Sheets |
|
I |
|
Geological Section |
|
|
1 |
|
Map of the location of the mining area33 |
|
|
2 |
|
Geological and mineral deposit map of the mine, scale 1:2,000 or 1:5,000 |
|
|
3 |
|
Contour map of mineral quantity (reserves), scale 1:2,000 or 1:5,000 |
|
|
4 |
|
Geological cross-sections, ratio 1:2,000 or 1:5,000 |
|
|
II |
|
Mining Section |
|
|
1 |
|
Map of coal seam opening, scale 1:5,000 |
|
|
2 |
|
Map of basic construction phase (if applicable), scale 1:5,000 |
|
|
3 |
|
Map of mining year reaching design capacity, scale 1:5,000 |
|
|
4 |
|
Map of mine closure, scale 1:5,000 |
|
|
5 |
|
Layout diagram of the mining system |
|
|
6 |
|
General layout plan of the entire mine, scale 1:2,000 |
|
|
III |
|
Environmental Protection Section |
|
|
1 |
|
Layout diagram of environmental protection facilities, location of areas for remediation and restoration |
|
|
2 |
|
Map of reclamation of mined-out space, scale 1:5,000 |
|
_______________
32 Map and drawing number signatures ensure consistency, ease of search and reference
33 Prepared according to Model No. 04 of this Annex
ANNEX 2: ESTIMATE FOR CONSTRUCTION WORKS
The estimate for construction works includes the following contents:
1. Explanatory section
State the legal basis and grounds for preparing the construction work estimate.
2. Estimate section
- Determine the volume of construction work for the project component according to the design.
- Determine the budget unit price for construction work.
- Prepare the cost items of the construction work estimate according to the current regulations on investment construction cost management.
Download
The original file of this document is being updated. Please read the full text and check back later.
Relations map
Click a document to open. A red border = a relation that changes validity.
Translations
This document is available in the following languages: