Decision No. 02/2019/QD-TTg amends and supplements certain articles of Decision No. 11/2017/QD-TTg on mechanisms to encourage the development of solar power projects in Vietnam. This document provides more detailed regulations on electricity purchase and sale prices for rooftop solar projects and guidelines for calculating and settling electricity payments based on fluctuating exchange rates.
Đối tượng áp dụng
Organizations and individuals participating in the development of solar power projects in Vietnam.
Các điểm cốt lõi
- Rooftop solar projects shall implement separate buy-sell electricity mechanisms for both import and export directions (Article 12).
- The electricity purchase and sale price for rooftop solar projects in the following year shall be determined based on the central exchange rate of the Vietnamese dong against the US dollar published by the State Bank of Vietnam (Article 12).
- Issuing technical standards for solar power, specifying grid connection and metering requirements for solar power projects (Article 13).
- Guidelines for calculating and settling electricity payments for solar power projects according to fluctuations of the Vietnamese dong against the US dollar (Article 13).
- Projects with the date of operation commencement and meter index confirmation before July 1, 2019 shall apply the electricity purchase and sale price mechanism for rooftop solar projects as stipulated in this Decision.
🌐 Tác động xã hội từ văn bản này
- Enhancing encouragement for the development of solar power projects, particularly rooftop solar projects.
- Facilitating project investors in calculating and settling electricity payments for rooftop solar projects.
- It may impose administrative procedural burdens on related units.
❓ Câu hỏi thường gặp
How is the electricity purchase and sale price for rooftop solar projects determined?
The electricity purchase and sale price for rooftop solar projects in the following year shall be determined based on the central exchange rate of the Vietnamese dong against the US dollar published by the State Bank of Vietnam.
Which projects are eligible for the electricity purchase and sale price mechanism for rooftop solar projects?
Projects with the date of operation commencement and meter index confirmation before July 1, 2019.
How are technical standards for solar power issued?
Issuing technical standards for solar power, specifying grid connection and metering requirements for solar power projects.
Toàn văn
|
PRIME MINISTER ___________________ |
SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness ___________________ |
| Number: 02/2019/QD-TTg |
Hanoi, January 8, 2019 |
Pursuant to …;
Amending and supplementing certain articles of Decision No. 11/2017/QD-TTg
dated April 11, 2017 of the Prime Minister on mechanisms to encourage the development of solar power projects in Vietnam
The Prime Minister promulgates this Decision amending and supplementing certain articles of Decision No. 11/2017/QD-TTg dated April 11, 2017 of the Prime Minister on mechanisms to encourage the development of solar power projects in Vietnam.
Pursuant to the Law on Government Organization dated June 19, 2015;
On the basis of Decree No. 17/2020/NĐ-CP dated February 5, 2020 of the Government amending and supplementing certain articles of related Decrees concerning investment and business conditions within the scope of management under the Ministry of Industry and Trade;
Pursuant to the Investment Law dated November 26, 2014;
Pursuant to the Construction Law dated June 18, 2014;
At the proposal of the Minister of Industry and Trade;
Article 1. Amending and supplementing certain articles of Decision No. 11/2017/QD-TTg dated April 11, 2017 of the Prime Minister on mechanisms to encourage the development of solar power projects in Vietnam (Decision No. 11/2017/QD-TTg).
"2. For rooftop projects
1. Amending Clause 2 of Article 12 as follows:
a) Rooftop projects shall implement the mechanism of separate metering for both import and export electricity. The seller of electricity shall settle the amount of electricity received from the grid according to current regulations. The buyer of electricity shall settle the amount of electricity supplied to the grid from rooftop projects at the price stipulated in Clause 1 of this Article. All parties are responsible for complying with current laws regarding tax and fees.
b) The price of electricity purchase and sale for rooftop projects for the following year shall be determined based on the central exchange rate of the Vietnamese dong against the US dollar published by the State Bank of Vietnam on the last day of the previous year."
2. Amend and supplement Point d Clause 1 Article 13 as follows:
"d) Issuing technical standards for solar power, regulations on interconnection and metering of solar power projects, and guidelines for interconnection procedures and installation of meters for rooftop solar power projects."
3. Amend and supplement Point h Clause 1 Article 13 as follows:
"h) Guiding the calculation and settlement of electricity charges for solar power projects based on fluctuations of the Vietnamese dong against the US dollar."
3. Repeal Clause 3 Article 13 of Decision No. 11/2017/QD-TTg.
12/2025/TT-BNNMT dated June 19, 2025 issued by the Minister of Agriculture and Environment2. Solar power rooftop projects that have reached their operational date and confirmed meter readings before July 1, 2019 shall apply the electricity purchase and sale price mechanism for solar power rooftop projects as prescribed in this Decision.
Article 3. Effectiveness
1. This Decision takes effect from the date of issuance.
3. Ministers, Heads of ministerial-level agencies, Heads of government-affiliated agencies, Chairpersons of provincial and centrally-administered city People's Committees; Heads of agencies, units, and organizations related to the development of solar power projects in Vietnam are responsible for implementing this Decision./.
3. The Ministers, Heads of ministerial-level agencies, Heads of government agencies, Chairpersons of provincial people's committees under the central government; Heads of agencies, units, and organizations related to the development of solar power projects in Vietnam shall be responsible for implementing this Decision./.
|
DEPUTY PRIME MINISTER DEPUTY PRIME MINISTER (Signed) |
|
| Trinh Dinh Dung |
Văn bản gốc (PDF)
Bản đồ quan hệ
Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.
Bản dịch
Văn bản này có sẵn ở các ngôn ngữ sau: