Circular No. 05/2023/TT-BCT promulgates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing.

Circular No. 05/2023/TT-BCT stipulates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing, applicable to organizations and individuals involved in determining and managing investment construction costs. This Circular takes effect from May 8, 2023.

Số hiệu05/2023/TT-BCT
Loại văn bảnCircular
Cơ quan ban hànhMinistry of Industry and Trade
Người kýĐặng Hoàng An — Thứ trưởng
Cập nhật15/06/2026
Ngày ban hành16/03/2023
Ngày áp dụng08/05/2023
Ngày hết hiệu lực
Tình trạngIn effect
✦ Tóm lược thông minh

Circular No. 05/2023/TT-BCT stipulates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing, applicable to organizations and individuals involved in determining and managing investment construction costs. This Circular takes effect from May 8, 2023.

Đối tượng áp dụng

[Organizations and individuals related to the determination and management of costs for investment construction projects]

Các điểm cốt lõi

  • Organizations and individuals related to the determination and management of costs → must comply with the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing when determining and managing costs for investment construction projects → Article 1
  • This Circular → takes effect from May 8, 2023 → Article 2

🌐 Tác động xã hội từ văn bản này

  • [Organizations and individuals related] → are specifically guided on how to determine and manage costs for investment construction projects involving power transmission line and substation testing
  • [Organizations and individuals related] → must comply with this new regulation when performing their tasks

❓ Câu hỏi thường gặp

When does this Circular take effect?

This Circular takes effect from May 8, 2023.

Which organizations and individuals must comply with this Circular?

Organizations and individuals involved in the determination and management of costs for investment construction projects as prescribed in Decree No. 10/2021/NĐ-CP dated February 9, 2021.

What does this Circular regulate?

This Circular regulates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing.

Toàn văn

MINISTRY OF INDUSTRY AND TRADE

SOCIALIST REPUBLIC OF VIET NAM

Independence - Freedom - Happiness

Number: 05/2023/TT-BCT

 

Hanoi, March 16, 2023

CIRCULAR

Issuing the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing

thử nghiệm điện đường dây và trạm biến áp

Pursuant to the Law on Construction promulgated on June 18, 2014;

Based on the Law Amending and Supplementing Certain Articles of the Construction Law June 17 2020;

căn cứ Nghị địnhnumber 96/2022/NĐ-CP dated 29 the 11 Pursuant to Decree No. 32/2019/NĐ-CP dated April 10, 2019 of the Government on assigning tasks, procurement or tendering for the supply of products and services using state budget from regular operating expenses;22 /NĐ-CP dated March

Pursuant to Decree No. 10/2021/NĐ-CP dated February 9, 2021 of the Government on the management of construction investment costs;

Article 1. Amending and supplementing certain Articles of Circular No. 09/2024/TT-BCA dated March 13, 2024 issued by the Minister of Public Security regarding the implementation of mass mobilization work by the People's Public Security forceCDirector Department of Electricity and Renewable Energy;

The Minister ofThe Government issues this Decree issues the Circular issues the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing..

Article 1. Accompanying this Circular are the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing.

Article 2. This Circular takes effect from May 8, 2023.

Article 3. Organizations and individuals related to determining and managing costs of investment construction projects as prescribed in Government Decree No. 10/2021/NĐ-CP dated February 9, 2021 on management of construction investment costs shall be responsible for implementing this Circular./.

DEPUTY MINISTER

DEPUTY MINISTER

(Signed)

Dang Hoang An

 

 

 