Circular No. 05/2023/TT-BCT stipulates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing, applicable to organizations and individuals involved in determining and managing investment construction costs. This Circular takes effect from May 8, 2023.
적용 범위
[Organizations and individuals related to the determination and management of costs for investment construction projects]
핵심 사항
- Organizations and individuals related to the determination and management of costs → must comply with the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing when determining and managing costs for investment construction projects → Article 1
- This Circular → takes effect from May 8, 2023 → Article 2
🌐 이 문서의 사회적 영향
- [Organizations and individuals related] → are specifically guided on how to determine and manage costs for investment construction projects involving power transmission line and substation testing
- [Organizations and individuals related] → must comply with this new regulation when performing their tasks
❓ 자주 묻는 질문
When does this Circular take effect?
This Circular takes effect from May 8, 2023.
Which organizations and individuals must comply with this Circular?
Organizations and individuals involved in the determination and management of costs for investment construction projects as prescribed in Decree No. 10/2021/NĐ-CP dated February 9, 2021.
What does this Circular regulate?
This Circular regulates the Industry Standards for Budget Estimates of Power Transmission Line and Substation Testing.
전문
|
MINISTRY OF INDUSTRY AND TRADE |
SOCIALIST REPUBLIC OF VIET NAM Independence - Freedom - Happiness |
|
Number: 05/2023/TT-BCT
|
Hanoi, March 16, 2023 |
CIRCULAR
Issuing the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing
thử nghiệm điện đường dây và trạm biến áp
Pursuant to the Law on Construction promulgated on June 18, 2014;
Based on the Law Amending and Supplementing Certain Articles of the Construction Law June 17 2020;
căn cứ Nghị địnhnumber 96/2022/NĐ-CP dated 29 the 11 Pursuant to Decree No. 32/2019/NĐ-CP dated April 10, 2019 of the Government on assigning tasks, procurement or tendering for the supply of products and services using state budget from regular operating expenses;22 /NĐ-CP dated March
Pursuant to Decree No. 10/2021/NĐ-CP dated February 9, 2021 of the Government on the management of construction investment costs;
Article 1. Amending and supplementing certain Articles of Circular No. 09/2024/TT-BCA dated March 13, 2024 issued by the Minister of Public Security regarding the implementation of mass mobilization work by the People's Public Security forceCDirector Department of Electricity and Renewable Energy;
The Minister ofThe Government issues this Decree issues the Circular issues the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing..
Article 1. Accompanying this Circular are the Industry Standard Budget Estimate Rates for Electrical Transmission Line and Substation Testing.
Article 2. This Circular takes effect from May 8, 2023.
Article 3. Organizations and individuals related to determining and managing costs of investment construction projects as prescribed in Government Decree No. 10/2021/NĐ-CP dated February 9, 2021 on management of construction investment costs shall be responsible for implementing this Circular./.
|
DEPUTY MINISTER DEPUTY MINISTER (Signed) Dang Hoang An |