Joint Circular No. 07/TTLB amends the guidance on delegating authority to approve technical design and total budget estimates as stipulated in Joint Circular No. 04-TTLB guiding the implementation of the investment and construction management regulations issued together with Decree No. 42/CP.

Joint Circular No. 07/TTLB amends Joint Circular No. 04/TTLB, abolishing the delegation of authority by the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects.

문서 번호07/TTLB
문서 유형Joint Circular
발행 기관Ministry of Finance
업데이트02. 07. 2026
산업Construction; Finance; Planning and Investment
분야Uncategorized
발행일25. 11. 1997
발효일25. 11. 1997
효력 만료일
상태In effect
✦ 스마트 요약

Joint Circular No. 07/TTLB amends Joint Circular No. 04/TTLB, abolishing the delegation of authority by the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects.

핵심 사항

  • The Chairman of the People's Committee of provinces and centrally governed cities shall not delegate authority to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects within their investment decision-making jurisdiction.

🌐 이 문서의 사회적 영향

  • Positive impact: Reduces the risk of violating regulations on approving technical designs and total budget estimates, enhancing transparency in investment and construction management.
  • Negative impact: May cause difficulties in implementing projects due to the loss of previous delegation rights.

❓ 자주 묻는 질문

What is the impact of abolishing the delegation of authority?

Abolishing the delegation of authority from the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects will reduce the risk of violations, but may also create difficulties in project implementation.

Who is directly affected?

The Chairman of the People's Committee of provinces and centrally governed cities and the Director of the specialized construction management department are directly affected by the loss of previous delegation rights.

How does this relate to investment construction projects?

Abolishing the delegation of authority from the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects will affect the implementation process of investment construction projects.

How does this relate to investors?

Abolishing the delegation of authority from the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects does not directly affect investors.

How does this relate to contractors?

Abolishing the delegation of authority from the Chairman of the People's Committee of provinces and centrally governed cities to the Director of the specialized construction management department to approve technical designs and total budget estimates for projects does not directly affect contractors.

전문

MINISTRY OF PLANNING AND INVESTMENT-MINISTRY OF FINANCE-MINISTRY OF CONSTRUCTION
No.: 07/TTLB
SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness

Hanoi, November 25, 1997

JOINT CIRCULAR

Regarding the amendment to the guidance on delegating authority to approve technical design and total estimated cost

of Circular Joint No. 04/TTLBguiding the implementation of the Investment and Construction Management Regulation

 issued together with Decree No. 42/CP To be consistent with the provisions of Government Decree No. 42/CP dated July 16, 1996 on the issuance of the Investment and Construction Management Regulation and Government Decree No. 92/CP dated August 23, 1997 on amending and supplementing certain articles of the Investment and Construction Management Regulation issued together with Decree No. 42/CP, the Joint Ministries of Construction, Planning and Investment, and Finance guide the cancellation of the content: "The Chairman of the People's Committee of provinces and centrally governed cities may delegate authority to the Director of the specialized construction management department to approve the technical design and total estimated cost of projects within the investment decision-making authority of the provinces and cities" stipulated at Point d, Clause 4, Section IV of Circular Joint No. 04/TTLB dated July 16, 1996 guiding the implementation of the Investment and Construction Management Regulation issued together with Government Decree No. 42/CP./.

To align with the provisions of Government Decree No. 42/CP dated July 16, 1996 on the issuance of the Investment and Construction Management Ordinance and Government Decree No. 92/CP dated August 23, 1997 amending and supplementing certain articles of the Investment and Construction Management Ordinance issued together with Government Decree No. 42/CP, the Ministry of Construction, the Ministry of Planning and Investment, and the Ministry of Finance guide the cancellation of the content: "The Chairman of the People's Committee of provinces and centrally-administered cities may delegate to the Director of the specialized construction management department to approve technical design and total budget estimates for projects within the investment decision-making authority of the provinces and centrally-administered cities," as stipulated in Point d, Clause 4, Section IV of Circular Joint No. 04/TTLB dated July 16, 1996 guiding the implementation of the Investment and Construction Management Ordinance issued together with Government Decree No. 42/CP./.

THE MINISTER OF CONSTRUCTION

(Signed)

Nguyen Manh Kiem

THE MINISTER OF PLANNING AND INVESTMENT

(Signed)

Tran Xuan Gia

THE MINISTER OF FINANCE

(Signed)

Nguyen Sinh Hung

이 문서의 원본 파일을 업데이트하는 중입니다. 전문을 먼저 확인하시고 나중에 다시 확인해 주세요.

관계도

07/TTLB
Joint Circular No. 07/TTLB amends the guidance on delegating authority to approve technical design and total budget estimates as stipulated in Joint Circular No. 04-TTLB guiding the implementation of the investment and construction management regulations issued together with Decree No. 42/CP.
In effect

문서를 클릭하면 열립니다. 빨간 테두리=효력을 변경하는 관계.