Directive No. 08/2002/CT-TTg requires strengthening investment appraisal work to enhance the effectiveness of investment management and construction. The Directive stipulates the responsibilities of investors, investor management agencies, and ministries, sectors, and localities in implementing investment appraisals.
Đối tượng áp dụng
Ministries, sectors, localities, and investors of investment and construction projects.
Các điểm cốt lõi
- Investor → must organize the implementation of the project, prepare and submit periodic reports to the investment appraisal agency; promptly report difficulties and propose solutions; bear responsibility for any issues arising from non-compliance with regulations.
- Investor management agency → must monitor and urge compliance with investment appraisal regulations; compile situations to resolve difficulties for the project.
- Ministry of Planning and Investment → serves as the central agency assisting the Government in inspecting the organization and implementation of investment appraisal work, directly conducting appraisals for Group A projects.
🌐 Tác động xã hội từ văn bản này
- Positive impact: Enhance the effectiveness of investment management and construction, ensuring project quality;
- Negative impact: Increase time and human resource burdens on investors due to the need to comply with new regulations.
❓ Câu hỏi thường gặp
What should investors do to comply with this directive?
Investors must organize the implementation of the project, prepare and submit periodic reports to the investment appraisal agency; promptly report difficulties and propose solutions.
What responsibilities does the investor management agency have?
The investor management agency must monitor and urge compliance with investment appraisal regulations; compile situations to resolve difficulties for the project.
What role does the Ministry of Planning and Investment play in this directive?
The Ministry of Planning and Investment serves as the central agency assisting the Government in inspecting the organization and implementation of investment appraisal work, directly conducting appraisals for Group A projects.
What responsibility will investors bear if they fail to comply with the regulations?
Investors will be responsible for any issues arising from untimely handling and non-compliance with investment appraisal regulations; competent authorities will not adjust investment projects that have not undergone investment appraisal.
What is the deadline for compiling a report on the implementation results of this directive?
The Ministry of Planning and Investment will compile a report to the Prime Minister in July 2002 regarding the implementation results of this Directive by ministries, sectors, localities, and units.
Toàn văn
|
PRIME MINISTER
|
SOCIALIST REPUBLIC OF VIET NAM Hanoi, February 25, 2002 |
DIRECTIVE
On strengthening investment appraisal work
Investment appraisal work has been regulated under Article 20 of the Investment and Construction Management Regulation issued together with Decree No. 52/1999/NĐ-CP dated July 8, 1999 of the Government; the Ministry of Planning and Investment issued Circular No. 01/2000/TT-BKH dated January 10, 2000 to guide its implementation. However, this work has not received sufficient attention from ministries, sectors, and localities, thus limiting its effectiveness; some ministries, sectors, and localities have yet to organize its implementation.
In order to strengthen investment and construction management, ensure effective investment, and improve the quality of projects, the Prime Minister requests ministries, sectors, localities, and project sponsors to strictly implement the investment appraisal work stipulated in Decree No. 52/1999/NĐ-CP dated July 8, 1999, paying particular attention to the following tasks:
1. Project Proponents:
- Organize the implementation of projects, prepare and submit periodic reports on project implementation to the agency designated for investment appraisal oversight for monitoring, supervision, evaluation, and support in project management. The report content shall follow the guidance provided in Circular No. 01/2000/TT-BKH dated January 10, 2000 of the Ministry of Planning and Investment;
- Promptly report to the competent authority deciding on investment and the agency organizing investment appraisal about any difficulties encountered during project implementation; propose solutions for the agency organizing investment appraisal to compile, analyze, evaluate, and submit to the competent authority for resolution;
- Be responsible for all arising issues due to untimely handling and non-compliance with investment appraisal regulations; the competent authority will not resolve project investment adjustments when the project does not undergo investment appraisal.
2. Direct managing agencies of project sponsors:
- Monitor and urge project sponsors to fully comply with investment appraisal regulations;
- Compile the situation of project implementation, identify difficulties, collaborate with the investment appraisal agency to resolve issues to expedite project deployment progress.
3. Ministries, sectors, and localities:
- The Ministry of Planning and Investment serves as the lead agency assisting the Government in overseeing, guiding professional matters, inspecting the organization and implementation of investment appraisal work, directly conducting investment appraisal for Group A projects, and periodically compiling reports to the Prime Minister to address common investment issues.
- Ministries, sectors, and localities should not establish new specialized organizations but must immediately designate departments responsible for ongoing investment appraisal duties.
The Prime Minister requests ministers, heads of ministerial-level agencies, heads of government-affiliated agencies, chairpersons of provincial people's councils under central cities, chairpersons of boards of general corporations, and directors of enterprises to direct and organize the implementation of this Directive effectively. The Ministry of Planning and Investment will compile and report to the Prime Minister in July 2002 on the results of implementing this Directive by ministries, sectors, localities, and units.
|