Decision No. 08/2007/QD-BCT on the issuance of the Provision on the cost of stopping and resuming power supply

Decision No. 08/2007/QD-BCT of the Ministry of Industry stipulates the cost of stopping and resuming power supply, replacing the old decision. This decision shall take effect fifteen days from the date of publication in the Official Gazette.

Document No.08/2007/QĐ-BCN
Document typeDecision
Issuing authorityMinistry of Industry and Trade
Signed byHoàng Trung Hải — Bộ trưởng
Updated29/06/2026
SectorLabour, War Invalids and Social Affairs
FieldUncategorized
Issued date30/01/2007
Effective date07/03/2007
Expiry date25/09/2014
StatusExpired
✦ Smart summary

Decision No. 08/2007/QD-BCT of the Ministry of Industry stipulates the cost of stopping and resuming power supply, replacing the old decision. This decision shall take effect fifteen days from the date of publication in the Official Gazette.

Key points

  • The Electricity Regulatory Authority → proposes to issue the provision on the cost of stopping and resuming power supply
  • This decision replaces Decision No. 60/2001/QD-BCT of the Minister of Industry on the issuance of the Provision on the cost of stopping and resuming power supply
  • This decision shall take effect fifteen days from the date of publication in the Official Gazette

🌐 Social impact of this document

  • Enterprises will have to comply with the new regulations on the cost of stopping and resuming power supply, affecting operating costs
  • Citizens may be affected by changes in electricity usage costs

❓ Frequently asked questions

When does this decision come into effect?

This decision shall take effect fifteen days from the date of publication in the Official Gazette.

Which year's decision does this replace?

Replacing Decision No. 60/2001/QD-BCT of the Minister of Industry.

Does this decision take effect immediately upon issuance or after a period of time?

This decision shall take effect fifteen days from the date of publication in the Official Gazette.

Full text

MINISTRY OF INDUSTRY

SOCIALIST REPUBLIC OF VIETNAM
Independence – Freedom – Happiness

No.: 08/2007/QD-BCT

Hanoi, January 30, 2007

 

Pursuant to …;

REGARDING THE ISSUE OF REGULATIONS ON THE LEVELS OF COSTS FOR INTERRUPTION AND RECONNECTION OF ELECTRICITY SUPPLY

THE MINISTER OF INDUSTRY

Pursuant to Decree No. 55/2003/ND-CP dated May 28, 2003 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Industry;

Pursuant to the Electricity Law dated December 3, 2004;

Pursuant to Decree No. 105/2005/ND-CP dated August 17, 2005 of the Government detailing and guiding the implementation of certain provisions of the Electricity Law;

On the proposal of the Director of the Electricity Regulatory Authority.

DECISION:

Article 1. The attached Decision promulgates the Regulations on Levels of Costs for Interruption and Reconnection of Electricity Supply.

Article 2This Decision shall take effect 15 days from the date of publication in the Official Gazette and shall supersede Decision No. 60/2001/QD-BCT dated December 10, 2001 of the Minister of Industry regarding the issuance of the Regulations on Levels of Costs for Interruption and Reconnection of Electricity Supply.

Article 3The Heads of the Ministry's Office, the Inspectorate of the Ministry, the Heads of Departments, Directors of Agencies under the Ministry, General Directors of the Vietnam Electricity Corporation, Directors of Industry Departments of provinces and centrally-administered cities, Heads of relevant agencies and units are responsible for implementing this Decision./.

 

MINISTER

(Signed)

Hoang Trung Hai

 