Decision No. 09/2007/QĐ-BCN of the Ministry of Industry amends Point a Clause 2 Article 23 concerning conditions, procedures, and formalities for issuing, amending, supplementing, revoking, and managing the use of power operation licenses. The new provision expands the scope of entities eligible to register for business in investment construction consultancy and construction supervision consultancy for transmission line and substation projects with voltage levels up to 35kV.
적용 범위
Organizations and individuals operating in the field of investment construction consultancy and construction supervision consultancy for transmission line and substation projects with voltage levels up to 35kV.
핵심 사항
- Investment construction consultancy and construction supervision consultancy for transmission line and substation projects with voltage levels up to 35kV → register for business at local level.
🌐 이 문서의 사회적 영향
- Positive impact: Expanding the scope of eligible entities to operate, creating favorable conditions for organizations and individuals in the field of construction consultancy for power.
- Negative impact: May lead to increased competition and management pressure on competent authorities.
❓ 자주 묻는 질문
Who is eligible to register for business?
Organizations and individuals providing investment construction consultancy and construction supervision consultancy for transmission line and substation projects with voltage levels up to 35kV.
What are the conditions for registering for business?
This document does not specify them clearly, but generally, they need to meet the legal entity requirements and operational capacity as stipulated by current regulations.
When does this decision take effect?
This decision takes effect fifteen days from the date of publication in the Official Gazette.
전문
|
MINISTRY OF INDUSTRY |
SOCIALIST REPUBLIC OF VIETNAM |
|
No.: 09/2007/QD-BCT |
Hanoi, February 6, 2007 |
Pursuant to …;
Decision No. 09/2007/QD-BCT of the Ministry of Industry Amending and Supplementing Point a Clause 2 Article 23 on conditions, procedures, and formalities for issuing, amending, supplementing, revoking, and managing the use of power business licenses issued pursuant to Decision No. 32/2006/QD-BCT dated September 6, 2006 of the Minister of IndustryClause 2 of Article 23 provides conditions, procedures, and formalities for issuing, amending, supplementing, revoking, and managing the use of licenses for electricity operations issued together with Decision No. 32/2006/QĐ-BCN dated September 6, 2006 of the Minister of Industry. to amend, supplement, revoke, and manage the use of licenses for electricity operations issued together with Decision No. 32/2006/QĐ-BCN dated September 6, 2006 of the Minister of Industry.
THE MINISTER OF INDUSTRY
Pursuant to Decree No. 55/2003/ND-CP dated May 28, 2003 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Industry;
Pursuant to the Electricity Law dated December 3, 2004;
Pursuant to Decree No. 105/2005/ND-CP dated August 17, 2005 of the Government detailing and guiding the implementation of certain provisions of the Electricity Law;
Pursuant to Decision No. 258/2005/QD-TTg dated October 19, 2005 of the Prime Minister on the establishment and stipulation of the functions, tasks, powers, and organizational structure of the Electricity Regulatory Agency under the Ministry of Industry;
At the proposal of the Director of the Electricity Regulatory Agency.
DECISION:
Article 1. Amending and Supplementing Point a Clause 2 Article 23 Provisions on conditions, procedures, and formalities for issuing, amending, supplementing, revoking, and managing the use of power business licenses issued pursuant to Decision No. 32/2006/QD-BCT dated September 6, 2006 as follows:
"Investment consulting and construction supervision for transmission lines and transformer stations with voltage levels from 35kV and below registered for business at local level"
Article 2. This Decision shall take effect 15 days from the date of publication in the Official Gazette.
Article 3. The Heads of the Ministry's Office, the Inspectorate, the Heads of Departments, Directors of Agencies under the Ministry, People's Committees of provinces and centrally governed cities, and organizations and individuals engaged in electricity activities are responsible for implementing this Decision./.
|
Place of Receipt: |
THE MINISTER |