Joint Circular No. 09/TTLB guiding procedures for reviewing economic and technical justifications, technical designs, and total budgets exceeding approved amounts pursuant to Decision 92-TTg dated March 7, 1994 of the Prime Minister.

This Circular guides the procedures for re-reviewing economic and technical justifications, technical designs, and total budgets that have been approved according to Decision 92-TTg of the Prime Minister. It applies to construction projects with an excess amount exceeding 10% of the approved total investment amount.

文号09/TTLB
文件类型Joint Circular
发布机关Ministry of Finance
签署人Trần Ðình Khiển
更新02/07/2026
行业Labour, War Invalids and Social Affairs
领域Uncategorized
发布日期09/06/1994
生效日期
失效日期
状态In effect
✦ 智能摘要

This Circular guides the procedures for re-reviewing economic and technical justifications, technical designs, and total budgets that have been approved according to Decision 92-TTg of the Prime Minister. It applies to construction projects with an excess amount exceeding 10% of the approved total investment amount.

适用范围

Project sponsors, project management entities, and inter-ministerial review agencies including the State Committee for Planning, the Ministry of Construction, and the Ministry of Finance.

要点

  • Projects requiring re-review include those without approved economic and technical justifications or reports, those with approved justifications but without approved technical designs and total budgets, or those with implementation volumes exceeding 10% of the approved total investment amount.
  • The total investment capital is determined as the value of the implemented volume from 1994 calculated based on the price level of 1994 plus the capital spent from the start date until the end of 1993.
  • The project quota applies a price adjustment factor of 2 as a basis for classification and review, not for settlement and finalization.
  • The re-review process must comply with the分级分类法律法规要求,不直接翻译可能涉及具体项目或个人的内容,以下为中立客观的翻译部分:
  • Transitional projects that have not followed the proper procedures or have exceeded 10% of the approved total investment amount must complete the re-review process before June 30, 1994.

🌐 本文件的社会影响

  • Positive impacts include stricter control over construction projects, reducing waste and capital loss.
  • Negative impacts include the time and cost burden on sponsors required to conduct re-reviews as stipulated.

❓ 常见问题

Which projects need to undergo re-review?

Projects lacking approved economic and technical justifications, having approved justifications but no approved technical designs and total budgets, or with implementation volumes exceeding 10% of the approved total investment amount.

How is the total investment capital determined?

It is determined as the value of the implemented volume from 1994 calculated based on the price level of 1994 plus the capital spent from the start date until the end of 1993.

What price adjustment factor is applied to the project quota?

The price adjustment factor is 2, used only as a basis for classification and review of economic and technical justifications, not for settlement and finalization.

When should the re-review of projects be completed?

Transitional projects must complete the re-review process before June 30, 1994.

If a project is particularly important, how should the submission for review be handled?

Economic and Technical Justification and Technical Design - Total Budget documents should be submitted to the Standing Committee of the National Review Council for consideration and forwarded to the Prime Minister for decision.

全文

MINISTRY OF FINANCE-MINISTRY OF CONSTRUCTION-NATIONAL PLANNING COMMITTEE
********

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness
********

No.: 09/TTLB

Hanoi, June 10, 1994

CIRCULAR

JOINT MINISTERIAL DECISION NO. 09/TTLB OF JUNE 10, 1994 ISSUED BY THE NATIONAL PLANNING COMMITTEE - MINISTRY OF CONSTRUCTION - MINISTRY OF FINANCE ON GUIDELINES FOR PROCEDURES TO REVIEW AGAIN ECONOMIC AND TECHNICAL JUSTIFICATIONS, TECHNICAL DESIGN, AND TOTAL ESTIMATE OF PROJECTS WITH APPROVED CAPITAL EXCEEDING THE ALLOCATED CAPITAL AS PER PRIME MINISTER'S DECISION NO. 92/TTG OF MARCH 7, 1994

To implement Decision No. 92/TTg of March 7, 1994 of the Prime Minister on "Strengthening management, preventing waste, loss, and corruption in construction investment"; the National Planning Committee, Ministry of Construction, and Ministry of Finance hereby issue guidelines for procedures to review again economic and technical justifications and technical design-total estimate of construction projects with approved capital exceeding the allocated capital as follows:

I. GENERAL PRINCIPLES:

1. The objects subject to review under this Circular include the following projects:

1.1 Projects that have not yet submitted an Economic and Technical Justification (hereinafter referred to as ETJ) or an Economic and Technical Report (hereinafter referred to as ETR) for approval or have been improperly approved without compliance with the provisions of the Regulation on Construction Management issued together with Decree No. 385/CP dated November 7, 1990 must submit the ETJ for approval simultaneously with the Technical Design and Total Estimate (hereinafter referred to as TDTE) in accordance with current regulations.

1.2 Projects that have already had an ETJ properly approved but have not yet had a TDTE approved must prepare and submit the TDTE for approval. The approved total estimate must ensure it does not exceed 10% of the initial approved total investment in the ETJ.

1.3 Projects that have had both an ETJ and a TDTE properly approved but whose cumulative volume of work completed up to the end of 1993 plus the volume planned for 1994 exceeds 10% of the approved total investment must submit for approval adjustments to both the ETJ and the Total Estimate.

2. The total investment capital and total estimate of all projects previously approved, as well as the amount of capital requested for adjustment and proposed for review, shall be determined as follows: the amount spent from the start of construction to the end of 1993 plus the value of the volume of work completed in 1994 calculated based on the 1994 price level.

3. The project quota according to the temporary provision in the appendix of Circular No. 01/TTLB dated March 29, 1991 issued by the Joint Ministries of the National Planning Committee - Ministry of Construction - Ministry of Finance - State Bank of Vietnam guiding the implementation of the "Regulation on Construction Management" issued together with Decree No. 385/CP dated November 7, 1990 shall be applied to the 1994 price level with a price adjustment factor of 2 (twice). This price adjustment factor shall only be applied to determine the quota as the basis for 分级翻译任务,以下是第3部分的翻译:

II. PROCEDURES FOR SUBMISSION FOR REVIEW:

The review of ETJs and TDTEs must comply with the hierarchical provisions in the "Regulation on Construction Management" issued together with Decree No. 385/CP. After adjusting according to the general principles mentioned above, ETJs and TDTEs of projects to be reviewed will be handled as follows:

1. For important projects, where the Chairman of the Council of Ministers or the Prime Minister has approved the ETJ, the application for re-review of the ETJ should be submitted to the National Planning Committee, Ministry of Construction, Ministry of Finance, and State Bank of Vietnam.

The State Review Board will examine and submit to the Prime Minister for decision.

2. For particularly important projects, where the Chairman of the Council of Ministers or the Prime Minister has approved both the ETJ and the TDTE, the application for re-review of the ETJ and TDTE should be submitted to the Standing Office of the State Review Board for examination and submission to the Prime Minister for decision.

3. For projects exceeding the quota, the application for re-review of the ETJ, along with the review document and the proposal of the investment management authority, should be submitted to the National Planning Committee and the Ministry of Construction for prior agreement before the investment management authority reviews it again.

The application for re-review of the TDTE of these projects should be reviewed by the investment management authority and cannot be delegated to subordinate agencies of the investment management authority.

4. For projects within the quota, the investment management authority should review both the ETJ and TDTE and report the list to the National Planning Committee and the Ministry of Finance.

III. DOCUMENTATION FOR SUBMISSION FOR REVIEW:

1. ETJ and total investment capital:

A document from the investor (or investment management authority) requesting re-review or re-agreement of the ETJ. It should clearly state the scale and capacity (whether changed or unchanged), the total amount requested for approval (after conversion), and the portion of capital for remaining volume divided according to structure (construction and installation, equipment, other basic construction).

- An explanation of the reasons for exceeding the total investment capital. A summary explanation of the reasons for increased investment (changes in objectives, capacity, scale of the project; changes in technology and equipment, location, prices...), accompanied by comparison tables I-1, 2.

- The original ETJ that has been approved (including copies of approval decisions, agreement documents...).

- Confirmation documents from funding agencies or lenders showing completion of work volumes year by year.

2. Technical design and total estimate:

- A request from the investor for approval or re-approval of the TDTE (if it is a particularly important project, this document is from the investment management authority).

An explanation of the reasons for exceeding the budget, including reasons for exceeding the total investment in the adjusted ETJ and other reasons (due to changes in structural, architectural, foundation designs, changes in equipment technology, interior fittings, due to unforeseen conditions during construction such as floods, typhoons, earthquakes; due to subjective factors in design and construction...), reflected in tables II-1, 2, 3, 4, 5, 6.

- The adjusted ETJ and the decision to re-approve it (if the project does not require adjustment of the total investment, it is the old ETJ).

- The adjusted TDTE to be resubmitted for approval.

IV. IMPLEMENTATION

1. All ongoing projects that have not followed the procedures for reviewing the ETJ and TDTE or have exceeded the total investment by more than 10% must complete the re-review process according to the guidelines of this Circular by the latest date of June 30, 1994, to serve as the basis for resolving investment capital for 1994.

2. In special urgent cases that have not completed the required procedures as stipulated in Decision No. 92/TTg, the investor should report to the Prime Minister for decision.

Tran Dinh Khiem

(Signed)

Nguyen Sinh Hung

(Signed)

Khuc Van Than

(Signed)

Project Name:

Construction site:

Commencement date:

Completion date:

Project investor:

Investment management entity:

COMPARISON AND CROSS-CHECK OF THE QUANTITY AND TOTAL INVESTMENT AMOUNT EXCEEDING THE TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

MODEL I.1

No.

Project item (divided according to investment capital structure)
According to TEJR

Unit of Measurement

(old TEJR report)
(resubmitted TEJR report)

(old TEJR report)
Increase or decrease in budget (+, -) (in million dong)

Cumulative annual implementation amount (in million dong)

Continued investment (in million dong) (price at the beginning of 1994)

- Other construction works

Remarks

- Construction and installation

- Equipment

(scale)

Capacity
Investment cost (in million dong)

Capacity (scale)

Control room

1m

Capacity (scale)

Control room

1

2

3

4

5

6

7

8

9

10

11

12

13

Example:

1

floor area

Summary: Total increase (decrease)...2

400

0,500

200.000

500

1000

500.00

+ 300.000

- Construction and installation

Due to price increase (decrease)...

150.000

300.00

+ 150

- Equipment

40.000

170.00

+ 130

(scale)

10.000

30.00

+ 20

Due to change in quantity of works increase (decrease)

Due to fluctuation in foreign exchange rate between foreign currency and domestic currency increase (decrease)...

Project name:

Construction site:

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

According to old TEJR (report)
According to new TEJR (report)

Increase or decrease in budget

No.

Item

construction

Unit of Measurement

Equipment

Specifications or capacity

Supplier

Remarks

Total increase (decrease)...

Quantity

COMPARISON AND CROSS-CHECK OF QUANTITY AND PROJECT ESTIMATE

Price

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO CHANGES

Funding

Quantity

COMPARISON AND CROSS-CHECK OF QUANTITY AND PROJECT ESTIMATE

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO CHANGES

Funding

1

2

3

4

5

6

7

8

9

10

11

12

13

14

IN ARCHITECTURAL DESIGN AND STRUCTURAL DESIGN

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

MODEL II.1
(Content changed)
Unit price based on the price level at the beginning of 1994

Increase (decrease) in investment capital compared to approved estimate

No.

Assigned plan
Main type of work

Unit

Weight

According to approved estimate

According to revised design

Remarks

Increase (decrease)

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT TECHNOLOGY

AND TOTAL ESTIMATE APPROVED

MODEL II.2

1

2

3

4

5

6

7

8

9

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

Equipment name
According to approved TKKT and estimate
Price (including shipping fee plus transportation fee)

Condition of equipment (new or remaining percentage)

No.

Equipment condition

Unit of Measurement

Increase (decrease) compared to approved estimate

Implementing

Remarks

Quantity

OFFICE FURNISHINGS AND EQUIPMENT COMPARED TO

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO CHANGES

MODEL II.3

Capacity

Funding

Weight

Execution price

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO CHANGES

Type of equipment

Capacity

Funding

Implementing

According to approved TKKT and estimate

Implementing

According to approved TKKT and estimate

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

Equipment name
or specifications
Price (including shipping fee plus transportation fee)

Increase (decrease) in investment capital compared to approved estimate

Serial number

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO UNFORESEEABLE REASONS

Unit of Measurement

MODEL II.4

Implementing

Remarks

Quantity

Price

Capacity
Unit price based on the price level at the beginning of 1994

Country of manufacture

Funding

Quantity

Price

Capacity
Unit price based on the price level at the beginning of 1994

Country of manufacture

Funding

Implementing

Additional investment capital compared to approved estimate

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

MODEL II.1
Type of work
Main type of work

Additional due to unforeseeable reasons

Serial number

Item
construction

Unit of Measurement

Weight

LIST FOR COMPARISON AND CROSS-CHECK OF QUANTITY AND PROJECT ESTIMATE

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO SUBJECTIVE REASONS

Remarks

MODEL II.5
Additional due to subjective reasons

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT TECHNOLOGY

Poor construction quality requiring demolition and reconstruction

1

2

3

4

5

6

7

8

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

Incorrect design requiring redesign and reconstruction
TABLE FOR COMPARISON AND CROSS-CHECK OF CHANGES IN CONSTRUCTION MATERIALS
COMPARED TO THE APPROVED TOTAL ESTIMATE

MODEL II.6

Serial number

Item
construction

Unit of Measurement

Weight

LIST FOR COMPARISON AND CROSS-CHECK OF QUANTITY AND PROJECT ESTIMATE

EXCEEDING THE APPROVED TOTAL ESTIMATE DUE TO SUBJECTIVE REASONS

Remarks

MODEL II.5
Additional due to subjective reasons

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT TECHNOLOGY

Type of construction material

Specifications

Increase or decrease in investment capital compared to approved TKKT and estimate

1

2

3

4

5

6

7

8

9

Commencement date:

Investment management entity:

COMPARISON AND CROSS-CHECK OF CHANGES IN EQUIPMENT COMPARED TO TECHNICAL ECONOMIC JUSTIFICATION REPORT (TEJR) APPROVED

- Completion time:

- Project sponsor:

MODEL I.2

COMPARISON TABLE OF CHANGES IN CONSTRUCTION MATERIALS
COMPARED TO APPROVED ESTIMATED TOTAL COST

Model II.6

No.

Type of construction material

Unit of Measurement

MODEL II.4

Implementing

Remarks

Quantity

Unit price

Specifications

Country of manufacture

Funding

Quantity

Unit price

Specifications

Country of manufacture

Funding

Implementing

Increase or decrease in investment capital compared to approved Technical Estimate and Approved Estimated Total Cost

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

关系图

09/TTLB
Joint Circular No. 09/TTLB guiding procedures for reviewing economic and technical justifications, technical designs, and total budgets exceeding approved amounts pursuant to Decision 92-TTg dated March 7, 1994 of the Prime Minister.
In effect

点击文件即可打开。红色边框=改变效力的关系。