Circular No. 11/2008/TT-BCT guides the procedures and formalities for electricity trading with foreign countries, applicable to power units. The Circular details the dossier for requesting approval of the policy on electricity trading from 110kV voltage level and above to 35kV voltage level and below, as well as the review and approval procedures.
Scope of application
Power units
Key points
- Power unit → must submit the dossier for requesting approval of the policy on electricity trading with foreign countries to the Electricity Regulatory Authority, including contents such as the description of the current power grid status, electricity demand, connection schemes, and conclusions on organizational implementation solutions.
- The Electricity Regulatory Authority → within five working days notifies the validity of the dossier, within ten working days reviews and solicits opinions from relevant ministries and agencies (for 110kV voltage level and above), or within thirty working days completes the review report and submits it to the Minister for approval (for 35kV voltage level and below).
- In case of necessity, the power unit → must provide explanations or organize for the reviewing unit to examine on-site.
- This Circular takes effect fifteen days after its publication in the Official Gazette and relevant agencies are responsible for enforcement.
🌐 Social impact of this document
- Positive impact: Helps power units implement electricity trading with foreign countries in an organized, transparent manner, ensuring safety and efficiency.
- Negative impact: May cause time and resource costs for power units during the preparation of dossiers and reviews.
❓ Frequently asked questions
What should power units prepare when submitting the dossier?
Power units must prepare the dossier for requesting approval of the policy on electricity trading with foreign countries, including the application letter, the foreign party's request document, the electricity trading plan, and other contents such as the description of the current power grid status, electricity demand, connection schemes, and conclusions on organizational implementation solutions.
What is the review period for the dossier?
For 110kV voltage level and above, the review period is fifteen working days from the date of receipt of a complete and valid dossier. For 35kV voltage level and below, the review period is thirty working days.
Does the Electricity Regulatory Authority have the right to request explanations from power units?
Yes, in necessary cases, the Electricity Regulatory Authority has the right to request power units to provide explanations or organize for the reviewing unit to examine and evaluate on-site.
Is this Circular applicable to border areas?
No, customers using electricity in border areas purchasing electricity directly from foreign countries at 0.4kV voltage level for residential or business purposes with a capacity under 50kVA do not fall under the scope of this Circular.
When does this Circular take effect?
This Circular takes effect fifteen days after its publication in the Official Gazette.
Full text
CIRCULAR
Guidelines for the procedures and formalities of electricity purchase and sale with foreign countries
__________________________
Pursuant to Decree No. 189/2007/ND-CP dated December 27, 2007, issued by the Government, detailing the functions, tasks, powers, and organizational structure of the Ministry of Industry and Trade;
Pursuant to the Electricity Law dated December 3, 2004;
Pursuant to Decree No. 105/2005/NĐ-CP dated August 17, 2005 of the Government detailing and guiding the implementation of certain provisions of the Electricity Law;
The Ministry of Industry and Trade guides the preparation of documents and procedures for electricity purchase and sale with foreign countries as follows:
I. SCOPE OF REGULATION AND APPLICABLE OBJECTS
1. This Circular provides guidelines for the preparation of documents and procedures for electricity purchase and sale with foreign countries for each export-import electricity project and applies to electricity units.
2. Customers using electricity in border areas who directly purchase electricity from abroad at a voltage level of 0.4kV without going through the national power grid and use it for household or business and production purposes with a capacity under 50kVA are not subject to this Circular.
II. CONTENTS OF THE APPLICATION DOCUMENT FOR APPROVAL OF ELECTRICITY PURCHASE AND SALE WITH FOREIGN COUNTRIES
Electricity purchase and sale with foreign countries must be approved in terms of policy. The plan for electricity purchase and sale with foreign countries must be consistent with the approved power development planning.
Documents for electricity purchase and sale with foreign countries include:
1. Application documents for approval of the policy on electricity purchase and sale with foreign countries at voltage levels of 110kV and above
a) The application for approval of the policy on electricity purchase and sale with foreign countries from the electricity unit.
b) Written request for electricity purchase or consent for electricity sale from the foreign side.
c) Plan for electricity purchase and sale with foreign countries (five copies), including the following contents:
- A brief description of the current state of the power grid in the area;
- Electricity demand (capacity, energy, annual load curve, typical day load curve) expected to be purchased or sold to foreign countries for each year during the period consistent with the national or local power development planning phase that has been approved;
- Scheme for connecting the Vietnamese power grid with the foreign power grid to be purchased or sold electricity:
+ Development plan for the power grid in the area already approved by the competent authority;
+ Connection scheme including: capacity, energy, time of expected electricity purchase and sale, connection point, metering equipment installation point, voltage level for electricity purchase and sale, showing the electricity purchase and sale scheme on maps and diagrams of the power grid in the area;
- Preliminary analysis and selection regarding technology, technical aspects, land clearance, resettlement if applicable, impacts of the project on the environment, ecology, fire prevention, security, defense;
Investment form, preliminary determination of construction volume, total investment cost, project implementation time, capital mobilization plan according to progress and economic-social efficiency of the project and phased investment if applicable from the Vietnamese side;
- Conclusions and recommendations for organizational implementation measures.
d) In case the electricity unit uses the power grid managed by another unit, there must be a written opinion from that unit.
2. Application documents for approval of the policy on electricity purchase and sale with foreign countries at voltage levels up to 35kV
a) The application for approval of the policy on electricity purchase and sale with foreign countries from the electricity unit.
b) Written request for electricity purchase or consent for electricity sale from the foreign side.
c) Plan for electricity purchase and sale with foreign countries (five copies), including the following contents:
- A brief description of the current state of the power grid in the area;
- Electricity demand (capacity, energy) expected to be purchased or sold to foreign countries for each year during the period consistent with the local power development planning phase that has been approved;
- Scheme for connecting the Vietnamese power grid with the foreign power grid to be purchased or sold electricity:
+ Development plan for the power grid in the area already approved by the competent authority;
+ Connection scheme including: capacity, energy, time of expected electricity purchase and sale, connection point, metering equipment installation point, voltage level for electricity purchase and sale, showing the electricity purchase and sale scheme on maps and diagrams of the power grid in the area.
- Preliminary determination of construction volume and investment cost from the Vietnamese side;
- Conclusions and recommendations for organizational implementation measures.
d) In case the electricity unit uses the power grid managed by another unit, there must be a written opinion from that unit.
III. PROCEDURES FOR REVIEW AND APPROVAL OF POLICIES ON ELECTRICITY PURCHASE AND SALE WITH FOREIGN COUNTRIES
1. For electricity purchase and sale with foreign countries at voltage levels of 110kV and above
a) The electricity unit submits the application documents for review of the policy on electricity purchase and sale with foreign countries to the Electricity Regulatory Authority for review.
b) Within five working days from the date of receipt of the documents, the Electricity Regulatory Authority must notify the electricity unit in writing about the validity of the application documents for electricity purchase and sale with foreign countries.
c) Within ten working days from the date of receipt of valid documents, the Electricity Regulatory Authority must organize the review and seek opinions from relevant ministries and sectors on the plan for electricity purchase and sale with foreign countries.
d) If necessary, the electricity unit must provide explanations or organize for the reviewing unit to examine and evaluate on-site.
đ) Within fifteen working days from the date of receipt of official written opinions from relevant ministries and sectors on the plan for electricity purchase and sale with foreign countries, the Electricity Regulatory Authority must complete the review report for submission to the Minister of Industry and Trade for consideration and submission to the Prime Minister for approval.
2. For electricity purchase and sale with foreign countries at voltage levels up to 35kV
a) The electricity unit submits the application documents for review of the policy on electricity purchase and sale with foreign countries to the Electricity Regulatory Authority for review.
b) Within five working days from the date of receipt of the documents, the Electricity Regulatory Authority must notify the electricity unit in writing about the validity of the application documents for electricity purchase and sale with foreign countries.
c) Within thirty working days from the date of receipt of valid documents, the Electricity Regulatory Authority must complete the review report and submit it to the Minister of Industry and Trade for consideration and approval.
IV. IMPLEMENTATION PROVISIONS
1. This Circular takes effect fifteen days after its publication in the Official Gazette.
2. The Director of the Ministry's Office, the Inspector General of the Ministry, the Heads of Departments and Bureaus under the Ministry, the Directors of Provincial Departments of Industry and Trade under central cities, the Heads of related agencies, and organizations and individuals participating in activities in the field of electricity import and export shall be responsible for implementing this Circular.
3. During the implementation process, if any difficulties arise, the relevant units shall reflect them to the Ministry of Industry and Trade for supplementation and amendment to ensure appropriateness./.
Download
The original file of this document is being updated. Please read the full text and check back later.
Relations map
Click a document to open. A red border = a relation that changes validity.
Translations
This document is available in the following languages: