Decision No. 1196/2000/QĐ-BGTVT stipulates that inland waterway vessels must reduce their load by 10% when the flood level reaches warning level 1 or higher. This decision shall take effect fifteen days from the date of issuance and replace Decision No. 1733/1999/QĐ-BGTVT.
Đối tượng áp dụng
Vessel captains and those controlling inland waterway vessels operating on routes with flood levels at warning level 1 or higher; Vietnam Inland Waterways Administration; Directors of Provincial Departments of Transport and Provincial Departments of Transport and Public Works.
Các điểm cốt lõi
- The captain or person controlling an inland waterway vessel must monitor hydrological conditions and reduce the vessel's load by 10% when the flood level reaches warning level 1 or higher throughout the entire route.
- In cases where a vessel is en route and encounters floods, it does not need to reduce its load but must implement measures to ensure the safety of the vessel until it reaches its destination.
🌐 Tác động xã hội từ văn bản này
- Positive impact: Reduces the risk of accidents due to overloading during the flood season, protecting human lives and property.
- Negative impact: May cause difficulties for cargo transportation activities, increasing transportation costs.
❓ Câu hỏi thường gặp
What should the captain do when encountering flood levels at warning level 1 or higher?
The captain or person controlling an inland waterway vessel must reduce the vessel's load by 10%.
Under what circumstances is load reduction not required?
When a vessel is en route and encounters floods, load reduction is not required, but the captain or person controlling the vessel must implement measures to ensure the safety of the vessel until it reaches its destination.
When is this Decision applicable?
This Decision shall take effect fifteen days from the date of issuance and replace Decision No. 1733/1999/QĐ-BGTVT.
What is the specific amount of load reduction?
The load reduction is 10% of the vessel's capacity when encountering flood levels at warning level 1 or higher.
Who is responsible for implementing this Decision?
Vietnam Inland Waterways Administration, Directors of Provincial Departments of Transport, Provincial Departments of Transport and Public Works, and relevant individuals are responsible for implementing this Decision.
Toàn văn
Pursuant to …;
Regulations on reducing load during flood season for inland waterway vessels
THE MINISTER OF TRANSPORTATION
Pursuant to Decree No. 22/CP dated March 22, 1994 of the Government stipulating tasks, powers, responsibilities for state management and organizational structure of the Ministry of Transport;
Pursuant to Decree No. 40/CP dated July 5, 1996 of the Government on Ensuring Order and Safety in Inland Waterway Traffic;
Pursuant to Decision No. 581-TTg dated July 25, 1997 of the Prime Minister promulgating the Storm and Flood Warning Regulation;
Pursuant to the proposal of the Heads of the Legal Affairs Department and the Transport Department, the Director of the Vietnam Inland Waterways Administration.
Pursuant to …;
Article 1. Now, it is hereby prescribed that the reduction of load for inland waterway transport vessels operating on inland waterway routes with flood levels at or above Level 1 warning (as announced by the General Department of Hydrology and Meteorology) shall be carried out as follows:
- Prior to loading, the master or person in charge of the vessel must monitor the hydrological conditions along the entire route. If any section of the river or canal on the route shows flood levels at or above Level 1 warning, then the vessel's load must be reduced by 10%.
- In cases where a vessel is en route and encounters floods, there is no need to reduce the load, but the master or person in charge of the vessel must base their actions on the technical condition of the vessel and actual circumstances to ensure safe arrival at the destination.
Article 2. This Decision takes effect fifteen days from the date of signature and replaces Decision No. 1733/1999/QĐ-BGTVT dated July 12, 1999 of the Ministry of Transport. The Vietnam Inland Waterways Administration is assigned to guide the implementation of this Decision.
Article 3. The Heads of the Ministry’s Office, the Heads of the Legal Affairs Department and the Transport Department, the Directors of the Departments of Transport Services, the Departments of Transport Infrastructure, the Heads of relevant agencies, units, and individuals are responsible for implementing this Decision./.
DEPUTY MINISTER