Decision No. 1224/2002/QD-TTg establishes and approves the investment project for construction of technical infrastructure in Quế Võ Industrial Zone, Bắc Ninh Province. The project aims to create a levelled ground for transportation systems, electricity supply, water supply, telecommunications, and waste treatment for the purpose of operating infrastructure within the industrial zone.
Scope of application
Kinh Bắc Urban Development Joint Stock Company (investor), Chairman of the People's Committee of Bắc Ninh Province, relevant Ministers, and Management Board of Bắc Ninh Industrial Zones.
Key points
- Kinh Bắc Urban Development Joint Stock Company is organized and operates under the Industrial Zone Regulations and is directly managed by the Management Board of Bắc Ninh Industrial Zones.
- The total investment capital of the project is 531 billion VND, including self-owned capital, advance investment capital from investors, and loans.
- Quế Võ Industrial Zone is constructed on an area of 311.6 hectares in Phương Liễu, Vân Dương, and Nam Sơn communes, Quế Võ district, Bắc Ninh Province.
- The project's operational period is 50 years from the date of the investment decision, with a construction period of 6 years from the date of land lease decision.
- Kinh Bắc Urban Development Joint Stock Company benefits from incentives under the Law on Encouragement of Domestic Investment.
🌐 Social impact of this document
- Enterprises will benefit from complete technical infrastructure, creating favorable conditions for production and business activities.
- Enhance regional economic development and promote industrialization and modernization in Bắc Ninh Province.
❓ Frequently asked questions
What incentives does Kinh Bắc Urban Development Joint Stock Company enjoy?
According to Article 3, Kinh Bắc Urban Development Joint Stock Company enjoys incentives under the Law on Encouragement of Domestic Investment.
What is the area of Quế Võ Industrial Zone?
According to Article 2, the area of Quế Võ Industrial Zone is 311.6 hectares, which will be confirmed when the land lease procedures are completed according to the Land Law.
What is the duration of the project's operation and construction?
According to Article 2, the project's operational period is 50 years from the date of the investment decision. The construction period is 6 years from the date of the land lease decision.
How is capital provided to Kinh Bắc Urban Development Joint Stock Company?
According to Article 2, the project's capital sources include self-owned capital, advance investment capital from investors, and loans.
What incentives does Kinh Bắc Urban Development Joint Stock Company enjoy?
According to Article 3, Kinh Bắc Urban Development Joint Stock Company enjoys incentives under the Law on Encouragement of Domestic Investment.
Full text
Pursuant to …;
REGARDING THE ESTABLISHMENT AND APPROVAL OF THE INVESTMENT PROJECT FOR CONSTRUCTION AND BUSINESS OF TECHNICAL INFRASTRUCTURE IN THE QUẾ VÕ INDUSTRIAL ZONE, BẮC NINH PROVINCE
TECHNICAL INFRASTRUCTURE OF QUẾ VÕ INDUSTRIAL ZONE, BẮC NINH PROVINCE
_______________________
PRIME MINISTER
Pursuant to the Law on Organization of the Government dated December 25, 2001;
Pursuant to the Regulations on Industrial Zones, Export Processing Zones, and High-Tech Zones issued together with Decree No. 36/CP dated April 24, 1997 of the Government;
Pursuant to the Investment Management and Construction Regulation issued together with Decree No. 52/1999/NĐ-CP dated July 8, 1999, and Decree No. 12/2000/NĐ-CP dated May 5, 2000 of the Government;
Considering the proposal of the Chairman of the People's Committee of Bac Ninh Province (documents No. 48/TT-UB dated July 9, 2002 and No. 1365/CN.XDCB-CT dated November 22, 2002) and the opinion of the Minister of Planning and Investment (document No. 7001 BKH/VPTĐ dated November 4, 2002),
DECISION:
Article 1. Establish the Quế Võ Industrial Zone, Bac Ninh Province.
The Quế Võ Industrial Zone shall be organized and operated according to the Regulations on Industrial Zones, Export Processing Zones, and High-Tech Zones issued together with Decree No. 36/CP dated April 24, 1997 of the Government and shall be directly managed by the Bac Ninh Industrial Zone Management Board.
Article 2. Approve the investment construction and business project for technical infrastructure in the Quế Võ Industrial Zone, Bac Ninh Province, with the following contents:
1. Project name: Investment construction and business project for technical infrastructure in the Quế Võ Industrial Zone, Bac Ninh Province.
2. Investor: Kinh Bắc Urban Development Joint Stock Company, headquartered at the Quế Võ Industrial Zone, Bac Ninh Province.
3. Project objectives: To create a construction site for transportation systems, power supply, water supply, telecommunications, waste treatment, etc., to operate the created infrastructure within the industrial zone.
4. Construction location: Phương Liễu, Vân Dương, Nam Sơn communes, Quế Võ district, Bac Ninh province.
5. Area of the industrial zone: 311.6 hectares, which will be confirmed when land leasing procedures are carried out in accordance with the Land Law.
6. Total investment capital: 531 billion Vietnamese dong.
7. Sources of capital: own capital, advance capital from investors, loans.
8. Operation period: 50 years from the date of the investment decision.
9. Construction period: 6 years from the date of land lease approval. During the investment and construction process, the investor must complete all necessary procedures in accordance with the Investment Management and Construction Regulation.
Article 3. Kinh Bắc Urban Development Joint Stock Company shall enjoy incentives under the Law on Encouragement of Domestic Investment.
Article 4. The Chairman of the People's Committee of Bac Ninh Province is responsible for directing the investor to implement the project in accordance with current regulations; to develop an overall plan for the synchronous development of external infrastructure outside the fence with internal infrastructure inside the fence, ensuring effective operation of the industrial zone.
Article 5. This Decision takes effect from the date of signature.
Article 6. The Chairman of the People's Committee of Bac Ninh Province, Ministers of Planning and Investment, Finance, Construction, Defense, Industry, Science and Technology, Natural Resources and Environment, Governor of the State Bank of Vietnam, Director of the Bac Ninh Industrial Zone Management Board, General Director of Kinh Bắc Urban Development Joint Stock Company, and heads of relevant agencies within their respective functions and authorities are responsible for implementing this Decision./.