Circular No. 13897/TC/DT regarding the provision of additional investment capital for basic construction projects in the supplementary plan for 2003.

This circular guides on providing additional investment capital for basic construction (BC) projects assigned in the 2002 plan, ensuring compliance with current regulations and specific payment deadlines.

Số hiệu13897/TC/ÐT
Loại văn bảnOfficial Dispatch
Cơ quan ban hànhMinistry of Finance
Người kýVũ Văn Ninh
Cập nhật16/06/2026
NgànhLabour, War Invalids and Social Affairs
Lĩnh vựcUncategorized
Ngày ban hành18/12/2002
Ngày áp dụng
Ngày hết hiệu lực
Tình trạngIn effect
✦ Tóm lược thông minh

This circular guides on providing additional investment capital for basic construction (BC) projects assigned in the 2002 plan, ensuring compliance with current regulations and specific payment deadlines.

Đối tượng áp dụng

[Ministries, ministerial-level agencies, government-affiliated agencies, central organizations of mass associations, State-owned Enterprise No. 91] and [People's Committees of provinces and centrally-administered cities]

Các điểm cốt lõi

  • Ministries and People's Committees of provinces must notify the supplementary plan for each project in accordance with the prescribed list and total capital amount (Point 1).
  • Additional funds will only be paid for completed work that has been inspected up to March 31, 2003, with payment deadlines by April 30, 2003 (Article 2).
  • The Ministry of Finance shall transfer funds to the State Treasury for projects under its management; People's Committees of provinces shall do likewise for projects under their management (Point 3).
  • Project sponsors must closely coordinate with the Ministry of Finance to resolve any arising issues, ensuring no delays in providing additional funding for the 2002 plan.
  • The Ministry of Finance will recover advance payments before supplementary quotas are provided for projects that have already received them (Point 3).

🌐 Tác động xã hội từ văn bản này

  • To assist ministries and localities in effectively implementing the basic construction investment plan for 2002.
  • Project sponsors may encounter difficulties resolving arising issues if they do not closely coordinate with the Ministry of Finance.

❓ Câu hỏi thường gặp

What is the payment deadline for additional funding under the supplementary plan for 2002?

The payment deadline is April 30, 2003 (Article 2).

What conditions must projects included in the supplementary plan meet?

They must comply with current investment and construction procedures and not use funds to pay off debts from previous years (Point 1).

How does the Ministry of Finance transfer funds to the State Treasury?

Transfer funds for projects under its management; People's Committees of provinces shall do likewise for projects under their management (Point 3).

What must sponsors do to ensure no delays in funding provision?

Closely coordinate with the Ministry of Finance to resolve arising issues (Final Article).

Toàn văn

LETTER

OF THE MINISTRY OF FINANCE NUMBER 13897 TC/ĐT DATED DECEMBER 19, 2002
REGARDING THE ISSUE OF CAPITAL FOR ADDITIONAL INVESTMENT AND CONSTRUCTION PLANS FOR 2002

 

To:

- Ministries, agencies equivalent to ministries, government agencies,
central-level social organizations, and General Company No. 91.

- People's Committees of provinces and centrally-administered cities.

 

Pursuant to Decision No. 1117/QĐ-TTg dated November 25, 2002 of the Prime Minister regarding additional state budget capital for development investment in 2002, the Ministry of Finance guides on issuing additional investment and construction capital plans for 2002 as follows:

1. Based on the additional investment and construction plan indicators assigned by Decision No. 1117/QĐ-TTg dated November 25, 2002 of the Prime Minister and document No. 7569 BKH/TH dated November 29, 2002 of the Ministry of Planning and Investment, ministries, agencies equivalent to ministries, government agencies, central-level social organizations, General Company No. 91 (hereinafter referred to as ministries) and People's Committees of provinces and centrally-administered cities (hereinafter referred to as provincial People's Committees) shall notify additional plans for each project in accordance with the principles stipulated in the aforementioned documents as follows:

- Ensuring compliance with the list of projects and total funding amounts per project as announced by the Ministry of Planning and Investment.

- Projects included in the additional plan must ensure completion of investment and construction procedures according to current regulations.

- This supplementary capital shall not be used to settle debts from previous years.

The implementation period for the plan and submission to the Ministry of Finance and the Ministry of Planning and Investment no later than December 31, 2002 for monitoring and as a basis for payment of funds.

2. Supplementary capital for the 2002 plan shall only be paid for completed work accepted up to March 31, 2003; the payment deadline is April 30, 2003.

3. For projects under ministry management, the Ministry of Finance will transfer funds to the State Treasury for payment; for projects under provincial management, the Ministry of Finance will provide supplementary targeted funding to provinces. Provinces shall transfer funds to the State Treasury for project payments. Supplementary capital provided in the 2002 plan will be settled within the 2002 fiscal year.

For projects that have already received provisional funding from the Ministry of Finance before receiving additional indicators, the Ministry of Finance shall recover such funds against the aforementioned indicators.

We request ministries and provincial People's Committees to instruct project sponsors to implement these guidelines and cooperate closely with the Ministry of Finance to promptly address any issues arising, ensuring smooth provision of supplementary investment capital for 2002.

 

Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 2
13897/TC/ÐT
Circular No. 13897/TC/DT regarding the provision of additional investment capital for basic construction projects in the supplementary plan for 2003.
In effect

Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.