Decision No. 15/2005/QĐ-BCN On the transfer of Uong Bi Thermal Power Plant to become an independent accounting affiliate company under Vietnam Electricity Corporation

Decision No. 15/2005/QĐ-BCN of the Ministry of Industry transfers Uong Bi Thermal Power Plant to become Uong Bi Thermal Power Company, an independent accounting affiliate unit under Vietnam Electricity Corporation. The company has legal personality and operates in various business fields.

Số hiệu15/2005/QĐ-BCN
Loại văn bảnDecision
Cơ quan ban hànhMinistry of Industry and Trade
Người kýHoàng Trung Hải — Bộ trưởng
Cập nhật29/06/2026
NgànhLabour, War Invalids and Social Affairs
Lĩnh vựcUncategorized
Ngày ban hành30/03/2005
Ngày áp dụng27/04/2005
Ngày hết hiệu lực
Tình trạngIn effect
✦ Tóm lược thông minh

Decision No. 15/2005/QĐ-BCN of the Ministry of Industry transfers Uong Bi Thermal Power Plant to become Uong Bi Thermal Power Company, an independent accounting affiliate unit under Vietnam Electricity Corporation. The company has legal personality and operates in various business fields.

Đối tượng áp dụng

Uong Bi Thermal Power Company

Các điểm cốt lõi

  • Business name: Uong Bi Thermal Power Company; Head office located in Uong Bi City, Quang Ninh Province. It has legal personality and implements an independent economic accounting system.
  • The Charter Capital of the Company is 72,727,000,000 VND (Seventy-two billion, seven hundred twenty-seven million VND).
  • Business scope includes electricity production, electrical equipment management and operation, human resource training, material purchase and sale, construction, and other industries.
  • The company's organizational structure includes General Director, Deputy General Directors, Chief Accountant, technical and operational departments, and operation and repair workshops.
  • The company must complete all registration procedures for business operations according to the Company Charter approved by the Management Board of Vietnam Electricity Corporation.

🌐 Tác động xã hội từ văn bản này

  • Positive impact: Uong Bi Thermal Power Company will operate independently, enhancing production and business efficiency.
  • Negative impact: There may be difficulties during the transition and adjustment of the management structure.

❓ Câu hỏi thường gặp

What is the international trading name of Uong Bi Thermal Power Company?

The international trading name of Uong Bi Thermal Power Company is Uong Bi Thermal Power Company.

What is the Charter Capital of Uong Bi Thermal Power Company?

The Charter Capital of Uong Bi Thermal Power Company as of December 31, 2004, is 72,727,000,000 VND (Seventy-two billion, seven hundred twenty-seven million VND).

In which areas does Uong Bi Thermal Power Company operate?

Uong Bi Thermal Power Company operates in various fields such as electricity production and trade; management, operation, maintenance, and repair of electrical equipment; human resource training for operation management; material and equipment purchase and export-import; construction of electrical projects, and other appropriate industries as stipulated by law.

How many members are there in the management structure of Uong Bi Thermal Power Company?

The organizational structure of Uong Bi Thermal Power Company includes the General Director, Deputy General Directors, Chief Accountant, technical and operational departments, and operation and repair workshops.

When does this decision take effect?

This decision takes effect fifteen days after its publication in the Official Gazette.

Toàn văn

MINISTRY OF INDUSTRY

SOCIALIST REPUBLIC OF VIETNAM
Independence - Freedom - Happiness

Number: 15/2005/QĐ-BCN

Hanoi, March 30, 2005

 

Pursuant to …;

Regarding the conversion of the Ung Bai Thermal Power Plant into a subsidiary independent accounting entity under Vietnam Electricity Corporation

the independent accounting unit under the Vietnam Electricity Corporation

THE MINISTER OF INDUSTRY

Pursuant to Decree No. 55/2003/NĐ-CP dated May 28, 2003 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Industry;

Pursuant to Decree No. 180/2004/NĐ-CP dated October 28, 2004 of the Government on the establishment, restructuring, and dissolution of state-owned enterprises;

Pursuant to Decision No. 12/2005/QĐ-TTg dated January 13, 2005 of the Prime Minister approving the supplementary restructuring and reform plan for state-owned enterprises under Vietnam Electricity Corporation until 2005;

Considering the proposal of the Board of Directors of Vietnam Electricity Corporation at Report No. 116/TTr-EVN-HĐQT dated March 24, 2005 regarding the conversion of the Ung Bai Thermal Power Plant into an independent accounting subsidiary;

At the suggestion of the Director of the Department of Organization and Cadres,

DECISION:

Article 1. The Ung Bai Thermal Power Plant, a dependent accounting unit, shall be converted into the Ung Bai Thermal Power Company, an independent accounting subsidiary of Vietnam Electricity Corporation.

1. Enterprise name: Ung Bai Thermal Power Company;

International trade name: Uông Bi Thermal Power Company;

Abbreviation: UBTPC;

2. The company's headquarters is located in Uong Bi city, Quang Ninh province;

3. The Ung Bai Thermal Power Company shall have legal person status, operate with independent economic accounting, use its seal, open bank accounts, and establish credit relationships with domestic and foreign banks in accordance with the law.

Article 2.

1. Business activities of the company:

- Production and trading of electric power;

- Management, operation, maintenance, repair, and renovation of electrical equipment, thermal power plants, and architectural works of power plants;

- Training and development of human resources for management, operation, maintenance, and repair of power plant equipment;

- Purchase and sale, import and export of materials and equipment;

- Project investment construction planning, project investment construction management, and construction supervision consultancy;

- Construction and installation of electrical works;

- Coal production and business;

- Production of electric poles, steel balls, machine grinding plate linings, centrifugal concrete products, thermal insulation and electrical insulation materials;

- Engaging in other businesses in accordance with the provisions of the law.

2. The Charter Capital of the Company as of December 31, 2004 is: 72,727,000,000 VND (Seventy-two billion seven hundred twenty-seven million VND).

Article 3. The organizational structure of the company includes:

1. General Director,

2. Deputy General Directors,

3. Chief Accountant,

4. Technical and operational departments,

5. Operation and repair workshops.

Article 4. The Ung Bai Thermal Power Company is responsible for completing all business registration procedures and operating according to the Company Charter approved by the Board of Directors of Vietnam Electricity Corporation, in accordance with the Law on State-Owned Enterprises and other relevant laws.

Article 5. This Decision takes effect fifteen days from the date of publication in the Official Gazette.

The Director of the Ministry's Office, the Inspector General of the Ministry, Heads of Departments and Bureaus under the Ministry, Chairman of the Board of Directors and General Director of Vietnam Electricity Corporation, and the Director of the Ung Bai Thermal Power Company are responsible for implementing this Decision.

 

Place of Receipt:
- As per Article 5,
- Prime Minister (for comments),
- VPCP,
- Steering Committee for Restructuring and Modernization,
- Ministry of Home Affairs,
- Ministry of Planning and Investment,
- Ministry of Labor, Invalids and Social Affairs,
- Ministry of Finance,
- Ministry of Public Security,
- Ministry of Science and Technology,
- Ministry of Trade,
- Ministry of Natural Resources and Environment,
- People's Committee of Quang Ninh Province,
- State Bank,
- Official Gazette,
- To be filed with the Office and Personnel Department (3 copies).

THE MINISTER

MINISTRY OF INDUSTRY 

(Signed)


 
Hoang Trung Hai




Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 3
180/2004/NĐ-CP Nghị định số 180/2004/NĐ-CP Về thành lập mới, tổ chức lại và giải thể công ty nhà nước Hết hiệu lực 55/2003/NĐ-CP Nghị định số 55/2003/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Công nghiệp Hết hiệu lực
15/2005/QĐ-BCN
Decision No. 15/2005/QĐ-BCN On the transfer of Uong Bi Thermal Power Plant to become an independent accounting affiliate company under Vietnam Electricity Corporation
In effect