Decision No. 1570/QD-TTg approves the task to adjust the Master Plan for Urban Construction in Ho Chi Minh City until 2025, sets out objectives and key indicators for sustainable development, and outlines detailed research requirements. The Decision applies to the People's Committee of Ho Chi Minh City, the Ministry of Construction, and related agencies.
Scope of application
People's Committee of Ho Chi Minh City; Ministry of Construction; relevant agencies, organizations, and individuals.
Key points
- is the People's Committee of Ho Chi Minh City → shall prepare the adjusted Master Plan for Urban Construction in Ho Chi Minh City until 2025
- is the Ministry of Construction → shall review the adjusted Master Plan for Urban Construction in Ho Chi Minh City until 2025
- is the People's Committee of Ho Chi Minh City → must cooperate with the Ministry of Construction and related agencies to prepare the adjusted Master Plan for Urban Construction in Ho Chi Minh City until 2025 within 18 months
- is the Prime Minister → shall approve the task to adjust the Master Plan for Urban Construction in Ho Chi Minh City until 2025
- is the Institute of Urban Planning of Ho Chi Minh City → shall prepare the adjusted Master Plan for Urban Construction in Ho Chi Minh City until 2025
🌐 Social impact of this document
- Positive impact: Sets out sustainable development goals and indicators, and proposes solutions for technical infrastructure, environment, and urban architecture.
- Negative impact: The time frame for preparing the plan (18 months) may put pressure on related agencies.
❓ Frequently asked questions
What is the timeframe for preparing the adjusted Master Plan for Urban Construction in Ho Chi Minh City until 2025?
The timeframe for preparing the plan is 18 months, starting from when the design task is approved.
Which agency is responsible for reviewing the adjusted Master Plan for Urban Construction in Ho Chi Minh City?
The reviewing agency is the Ministry of Construction.
Who will approve the task to adjust the Master Plan for Urban Construction in Ho Chi Minh City?
The Prime Minister will approve the task to adjust the Master Plan for Urban Construction in Ho Chi Minh City.
Which agency prepares the adjusted Master Plan for Urban Construction in Ho Chi Minh City?
The Institute of Urban Planning of Ho Chi Minh City prepares the adjusted Master Plan for Urban Construction in Ho Chi Minh City.
Which agency cooperates to prepare the adjusted Master Plan?
The People's Committee of Ho Chi Minh City cooperates with the Ministry of Construction and related agencies to prepare the adjusted Master Plan for Urban Construction in Ho Chi Minh City.
Full text
Pursuant to …;
Regarding the approval of the task of compiling the general urban planning
for Ho Chi Minh City until 2025
______________
PRIME MINISTER
Pursuant to the Law on Organization of the Government dated December 25, 2001 and Decree No. 86/2002/NĐ-CP dated November 5, 2002 of the Government stipulating the functions, tasks, powers, and organizational structure of Ministries and ministerial-level agencies;
Pursuant to the Construction Law dated November 26, 2003 and Decree No. 08/2005/NĐ-CP dated January 24, 2005 of the Government on urban planning;
Considering the proposal of the Minister of Construction at document No. 69/TTr-BXD dated October 13, 2006 regarding the approval of the task of adjusting the General Urban Planning for Ho Chi Minh City until 2025,
Pursuant to …;
Clause 4 of Article 6Approve the task of adjusting the General Urban Planning for Ho Chi Minh City until 2025 with the following main contents:
1. Nature:
A special city, a major center for economy, culture, science and technology, with an important political position nationwide; an international exchange hub; a multi-sector industrial and service center, and a scientific and technological center in Southeast Asia.
2. Scope, boundaries, and scale of adjustment of the general urban planning:
a) The research scope includes the entire administrative boundary of Ho Chi Minh City and surrounding provinces, including: Binh Duong, Binh Phuoc, Tay Ninh, Long An, Dong Nai, Ba Ria - Vung Tau, and Tien Giang; with an area of approximately 30,404 km².
The scope and boundaries of the project to adjust the general urban planning include the entire administrative boundary of Ho Chi Minh City, with an area of 2,095 km².
b) Population scale:
- By 2025, about 10 million people; transient visitors and temporary residents (less than six months) about 2.5 million people;
- Population distribution: old inner city area from 4.0 to 4.5 million people; newly developed inner city area (six new districts) from 2.8 to 2.9 million people; suburban area about 2.6 million people (of which rural population is about 0.5 million people).
c) Scale of land for urban construction: by 2025 about 90,000 to 100,000 hectares; of which: old inner city area about 14,000 hectares; newly developed inner city area about 35,000 hectares and suburban area about 40,000 to 50,000 hectares.
3. Objectives and viewpoints:
a) Objective: to build Ho Chi Minh City into a sustainable, harmonious development between economic growth and preservation of historical and cultural relics and environmental protection; ensuring national defense and security through regional linkage to become a civilized and modern city, contributing increasingly to the development of southern Vietnam and the whole country; gradually becoming a center for industry, services, and science and technology in Southeast Asia.
b) Viewpoints:
- To leverage the special role of the city in its relationship with the Ho Chi Minh City region, the Southern key economic zone, the whole country, and internationally;
- To develop harmoniously and synchronously between new construction and urban renovation and beautification; between urban spatial development and technical infrastructure, social infrastructure, and environmental protection;
- To develop a modern city with distinct characteristics; to leverage the unique waterway advantage while creating urban attractiveness; to improve the quality of life for citizens.
4. Main indicators of the project:
a) Urban construction land indicators:
Average urban construction land: 80 - 100 m²/person, of which average residential construction land 55 - 65 m²/person, average green space within residential areas 8 m²/person, average construction land for public welfare facilities 4 - 6 m²/person;
b) Technical infrastructure indicators for urban areas:
- Transportation: transportation land indicator (dynamic and static) 20 - 24 m²/person; land allocated for transportation accounts for 22 - 24% of urban construction land; density of main roads reaches 4.5 - 5 km/km².
- Water supply: domestic water supply indicator about 200 liters/person/day-night; supplied to industry about 50 m³/ha. Percentage of urban population supplied with water 100%.
- Power supply: domestic power supply indicator about 2,600 kWh/person; supplied to industry about 300 kW/ha; supplied to service and trade activities about 40 - 50% of the standard domestic power supply.
- Drainage and environmental sanitation:
Standards for calculating sewage collection and treatment take into account the corresponding water supply standards for each category. Sewage is collected and treated to meet standards before being discharged into the environment, achieving a rate of 80% or higher.
5. Research requirements:
The orientation for the development of Ho Chi Minh City is determined in relation to the economic and social aspects with the Ho Chi Minh City region, the Southern key economic zone, the whole country, the region, and internationally, including:
a) Propose a development model for the city based on the principle of linking with other cities in the Ho Chi Minh City region; not developing cities in areas of natural conservation and urban ecology;
b) Propose directions for urban spatial development, including the inner city and suburbs; identify satellite towns and new towns in the Ho Chi Minh City region to support the sustainable development of the city based on a unified urban spatial development framework;
c) Propose zoning function plans; determine urban development zones, industrial development zones, ecological zones, resort and holiday zones, agricultural zones, and natural conservation zones;
d) Propose appropriate economic and technical indicators for the city's development model, taking into account the specific geographical, geological, and hydrological conditions in each zone, each functional area, and according to each stage of the city's development;
đ) Propose zoning functions and spatial organization structures for the city, including:
- Residential areas (old inner city, newly developed inner city, suburban areas; rural residential areas; areas for renovation, beautification, and upgrading of technical and social infrastructure); with emphasis on the Eastern North Science City, Hiệp Phước Port Urban Area, Western North Urban Area, and Bình Quới - Thanh Đa Urban Area;
- Industrial clusters and zones: towards relocating polluting industries out of the old inner city area; limiting industrial development in the newly developed inner city area; arranging industries by specialty and attracting investment to develop clean, modern industries with high scientific content, high added value, low labor intensity, and no environmental pollution.
- The system of integrated centers, specialized centers (cultural, training, scientific research, healthcare, sports, tourism and leisure...), urban district centers;
- The system of green parks, water surfaces, open spaces, especially the landscape along both banks of the Saigon River; green areas and zones within the old city center based on the principle of utilizing the city's axes, rivers, and canals to simultaneously perform waterway transportation, drainage, water regulation, and landscape functions;
- Conservation areas, particularly protecting the Can Gio Biosphere Reserve, protective forests, and special-use forests in Cu Chi and Binh Chanh districts; prohibiting and restricting construction in safety buffer zones around airports, security, and defense areas; limiting urban development in agricultural and forestry areas with the function of serving as ecological buffers for the city;
e) Determine the underground infrastructure system, multi-functional underground complexes, and propose planning for the underground infrastructure system in the city, as well as management and usage requirements;
g) Propose orientation for the development of urban architecture:
Based on the development perspective and objectives, urban spatial development orientation, study the orientation for developing the architecture and landscape of new urban areas, renovation areas in old urban districts, and important functional zones; particularly focusing on the modernization and renovation of existing central areas while preserving valuable cultural and architectural works; implement urban design studies in key urban areas to serve urban construction management;
h) Propose orientation for the development of technical infrastructure systems:
Urban technical infrastructure must be designed and constructed to meet the city's development goals and perspectives, satisfy usage needs, ensure aesthetics, safety, and environmental hygiene, specifically as follows:
- Transportation:
+ Determine the external transportation network based on regional relationship studies and internal transportation (air, rail, road, water), determine the inland port system;
+ Propose solutions for the underground transportation system (subway), public transportation, routes, and means (bus, elevated railway...);
+ Propose land allocation for static transportation development (bus stations, underground and surface parking lots);
- Construction site preparation technology:
Determine the control levels for construction in each area and the main traffic axes of the city; propose solutions for stormwater drainage (watershed and direction, sewerage system) combined with solutions for creating balancing lakes, dredging canals, open space creation, and greenery; solutions for flood prevention, riverbank erosion, and tidal influence;
- Water supply:
Determine the water source, demand, location, scale of primary facilities, pipeline networks, and major technical parameters; propose solutions for protecting surface and groundwater; research should be based on the Master Plan for Regional Construction of Ho Chi Minh City;
- Power supply:
Determine the power source, capacity, load demand, location, scale of power plants, substations, transmission corridors, and main distribution networks, as well as major technical parameters; research should be based on the Master Plan for Regional Construction of Ho Chi Minh City;
- Determine the sources and networks for supplying gas, fuel, and other combustion materials;
- Wastewater discharge and environmental sanitation:
+ Determine the location and scale of wastewater treatment plants, solid waste treatment facilities; solutions and main drainage networks, balancing lakes, and environmental protection measures;
+ Determine the location and scale of cemeteries and cremation technologies;
- Postal and telecommunications infrastructure system;
i) Evaluate environmental impacts and propose solutions to limit effects on the environment;
k) Determine priority investment programs and projects in line with resource forecasts; propose mechanisms and policies for urban planning and architectural management, and solutions for implementing the adjustment project of the General Urban Planning for Ho Chi Minh City until 2025;
l) Draft regulations for construction management according to the content of the adjustment project of the General Urban Planning for Ho Chi Minh City until 2025;
6. Components of the dossier: the dossier for the adjustment project of the General Urban Planning for Ho Chi Minh City until 2025 shall be implemented in accordance with Article 17 of Decree No. 08/2005/NĐ-CP dated January 24, 2005 of the Government and Circular No. 15/2005/TT-BXD dated August 19, 2005 of the Ministry of Construction on guiding the preparation, review, and approval of urban planning;
7. Implementation organization:
a) Project management agency: People's Committee of Ho Chi Minh City;
b) Project sponsor: People's Committee of Ho Chi Minh City;
c) Project planning agency: Institute of Urban Planning of Ho Chi Minh City;
d) Reviewing agency: Ministry of Construction;
đ) Approval level: Prime Minister;
e) Time for preparing the project: 18 months after the design task is approved;
12/2025/TT-BNNMT dated June 19, 2025 issued by the Minister of Agriculture and EnvironmentThe People's Committee of Ho Chi Minh City will coordinate with the Ministry of Construction and relevant ministries and sectors to organize the preparation of the adjustment project of the General Urban Planning for Ho Chi Minh City until 2025;
Article 3.This Decision takes effect from the date of signature.
The Chairman of the People's Committee of Ho Chi Minh City, the Minister of Construction; heads of agencies, organizations, and individuals related to this Decision are responsible for its implementation./.