This Decision issues regulations on the content, procedures, and processes for power development planning at different levels. It applies to the establishment, approval, and management of implementation of national, provincial, and district power plans. Detailed provisions regarding the content, procedures for construction, review, approval of plans, as well as their management and implementation are clearly stated.
적용 범위
Organizations and individuals participating in power activities.
핵심 사항
- National and provincial power development plans include various contents such as current status, demand forecast, economic-technical indicators, primary energy source assessment.
- For national power development planning, the Ministry of Industry is responsible for management and approval, while the Provincial People's Committee manages the implementation of the plan at the local level.
- Procedures for drafting outlines, registering capital, constructing, reviewing, and approving plans are detailed.
- Management and implementation of national and provincial power development plans are the responsibility of the Ministry of Industry and the Provincial People's Committee.
- Projects in Group A and B not included in approved plans may only be allowed to prepare for investment with the Prime Minister's approval.
🌐 이 문서의 사회적 영향
- Positive impact: Creates a scientific basis for power sector development, ensuring safe and continuous power supply.
- Negative impact: Investment costs for planned projects may put pressure on local budgets.
❓ 자주 묻는 질문
Who does this Decision apply to?
Applies to organizations and individuals participating in power activities.
What is the procedure for establishing a national power development plan?
The Ministry of Industry approves the outline budget and registration of state budget capital plan. The consulting organization selected conducts the planning according to the approved outline.
When does this Decision take effect?
Effective 15 days from the date of signature.
How can projects in Group A and B not included in the plan be implemented?
Must be approved by the Prime Minister after review by the Ministry of Industry.
How does this Decision replace previous regulations on power planning management work?
Replaces previous regulations on power planning management work.
전문
DECISION
Regarding the issuance of regulations on the content, procedures, and formalities
for power development planning
THE MINISTER OF INDUSTRY
Pursuant to Decree No. 74/CP dated November 1, 1995 of the Government on the functions, tasks, powers, and organizational structure of the Ministry of Industry;
Pursuant to Decree No. 45/2001/NĐ-CP dated August 2, 2001 of the Government on electricity activities and electricity usage;
Pursuant to the Investment Management and Construction Regulation issued together with Decree No. 52/1999/NĐ-CP dated July 8, 1999 and amended and supplemented by Decree No. 12/2000/NĐ-CP dated May 5, 2000 of the Government;
Delegating the Management Boards of High-Tech Zones in provinces and centrally governed cities the authority to approve plans for importing finished products to combine with export products and to approve the liquidation of machinery, equipment, transportation means, materials, and raw materials of joint ventures, wholly foreign-owned enterprises, export processing enterprises, and contractual joint ventures under the management of the delegated authority.
DECISION:
Article 1. Issued together with this Decision are the Regulations on the content, procedures, and formalities for power development planning, applicable to the preparation, approval, and management of implementation of national power development planning, provincial power development planning, district power development planning, county power development planning, town power development planning, and city power development planning directly under provinces.
Article 2. This Decision shall take effect 15 days from the date of signature and replace previous regulations on power planning management work.
Article 3. The Heads of the Ministry's Office, the Heads of the Ministry's Inspectorate, the Heads of Departments, Bureau Chiefs under the Ministry, People's Committees of provinces and centrally governed cities, General Directors of Vietnam Electricity Corporation, and organizations and individuals engaged in electricity activities are responsible for implementing this Decision./.
|
DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Hoang Trung Hai
|
REGULATIONS
Content, procedures, and formalities for power development planning
(ANNEXED TO DECISION
number: 21/2002/QĐ-BCN dated June 4, 2002 of the Minister of Industry )
PART I
General Provisions
Article 1.
1.Power development planning includes:
a)National power development planning;
b)Provincial power development planning (hereinafter referred to collectively as province);
c)District power development planning, county power development planning, town power development planning, and city power development planning directly under provinces (hereinafter referred to collectively as county).
2.Stages of planning:
a)National power development planning is prepared for each ten-year period, considering the prospects for the next ten years.
b)Other power development planning is prepared for each five-year period, considering the prospects for the next five years.
3.This regulation applies to organizations and individuals participating in electricity activities.
Article 2.
Power development planning is the goal, direction, solution, and policy mechanism for the development of the electricity industry, the development and improvement of power sources and grids, aimed at ensuring safe and continuous electricity supply for economic sectors, public services, people's livelihoods, and national defense and security, based on the efficient and economical use of the country's energy resources.
Article 3.
Only consulting organizations with permits to operate in the field of power development planning may participate in preparing national power development planning and provincial power development planning.
Chapter II
Content, procedures, and formalities for the construction, review, and approval of power development planning
Article 4.
1.National power development planning includes the following main contents:
a)Current state of national power and evaluation of the implementation of power development planning in the previous phase.
b)Overview of the economic and social situation and the energy system in Vietnam.
c)Forecast of electricity demand.
d)Economic and technical criteria for power source and grid projects.
đ)Evaluation of primary energy sources, exploitation capacity, import-export capacity of energy, and forecast of fuel prices for electricity production.
e)Program for developing power sources.
g)Program for developing grids.
h)Regional grid interconnection.
i)Program for rural electrification.
k)System dispatching and information for the Vietnamese power system.
l)Environment and environmental protection in power development.
m)Summary of construction volume and investment capital for the national power development program.
n)Economic and financial analysis of the national power development plan option.
o)Organizational structure for managing the electricity industry.
p)Conclusions and recommendations on policy mechanisms to ensure the implementation of the power development program during the planning phase.
(Detailed provisions in Appendix 1 attached).
2.Provincial power development planning includes the following main contents:
a)Evaluation of the current state of local power and the implementation of planning in the previous phase.
b)Current status and target for economic and social development in the planning phase.
c)Forecast of electricity demand.
d)Evaluation of potential for developing power sources locally.
đ)Evaluation of the ability to exchange electricity with adjacent areas.
e)Evaluation of electricity supply conditions in remote, difficult-to-reach areas, and special economic zones (if any).
g)Balancing capacity and electricity for important time periods during the planning phase.
h)Selection of some reasonable power source and grid development options.
i)Calculation and comparison of economic and technical criteria for selected options.
k)Selection of the optimal provincial power development option.
l)Summary of construction volume and investment capital for the planning phase.
m)Financial analysis of the selected option.
n)Conclusions and recommendations on policy mechanisms to ensure the implementation of the provincial power development program during the planning phase.
(Detailed provisions in Appendix 2 attached).
3.District power development planning includes the following main contents:
a)Evaluation of the current state of local power and the implementation of planning in the previous phase.
b)Current status and target for economic and social development of the locality in the planning phase.
c)Forecast of load demand.
d)Evaluation of potential for developing power sources locally.
đ)Evaluation of the ability to exchange electricity with adjacent areas.
e)Evaluation of electricity supply conditions in remote, difficult-to-reach areas, and special economic zones (if any).
g)Balancing capacity and electricity for important time periods during the planning phase.
h)Selection of some reasonable power source and grid development options.
i)Calculation and comparison of economic and technical criteria for selected options.
k)Selection of the optimal district power development option.
l)Summary of construction volume and investment capital for the planning phase.
m)Financial analysis of the selected option.
n)Conclusions and recommendations on policy mechanisms to ensure the implementation of the power development program during the planning phase.
(Detailed provisions in Appendix 3 attached).
Article 5.
Procedures and formalities for drafting outlines and registering capital for power development planning as follows:
1.For national power development planning:
According to the five-year cycle, the Ministry of Industry approves the draft budget estimate and registers the state budget capital plan according to current regulations.
2.For provincial power development planning:
According to the five-year cycle, the Department of Industry drafts the budget estimate and submits it to the Provincial People's Committee for approval and registers the state budget capital plan for provincial power development planning according to current regulations.
3.For district power development planning:
Every five years, the Industry Department shall prepare a framework and budget for the power development planning work according to the power development needs of each region, submit it to the Provincial People's Committee for approval and coordinate the local budget funds for this work in accordance with current regulations.
4.The unit price establishment and cost of reviewing the power development planning shall be carried out in accordance with current regulations.
Article 6.
The procedure for developing the power development plan is as follows:
1.For national power development planning:
a)Based on the state budget capital plan allocated for national power development planning, the Ministry of Industry shall select consulting organizations with sufficient capacity to develop the plan.
b)The selected consulting organization shall carry out the National Power Development Plan in accordance with the approved framework and the assigned deadline.
c)During the planning process, the consulting organization must implement intermediate reporting steps as prescribed to seek opinions from relevant agencies and complete the plan.
d)After completing the plan, the consulting unit shall submit it to the Ministry of Industry for review and report to the Prime Minister for approval. The documents for submission include:
5sets of draft plans.
15copies of the summary report of the draft plan.
2.Provincial power development planning:
a)Based on the state budget capital plan allocated for planning work, the Industry Department shall select consulting organizations with sufficient capacity to develop the plan.
b)The selected consulting organization shall carry out the provincial power development planning in accordance with the approved framework and the assigned deadline.
c)During the planning process, the consultant must implement intermediate reporting steps, seek opinions from the Provincial People's Committee and Vietnam Electricity Corporation to perfect the plan.
d)Upon completion, the planning proposal is reviewed by the Industry Department and reported to the Provincial People's Committee for approval and submitted to the Ministry of Industry for approval. The documents for submission include:
5sets of completed planning proposals.
15sets of summary reports of the planning proposals.
3.County power development planning:
a)Based on the local state budget capital plan allocated for planning work, the Provincial People's Committee shall instruct the Industry Department to select consulting organizations with sufficient capacity to develop the plan.
b)The selected consulting organization shall carry out the county power development planning in accordance with the approved framework and the assigned deadline.
c)During the planning process, the consultant must implement intermediate reporting steps, seek opinions from relevant provincial departments and provincial electricity companies to perfect the plan.
d)Upon completion, the plan is sent to the Industry Department for review. The documents for submission include:
5sets of completed planning proposals;
10copies of the summary report of the planning proposal;
e)Based on the review results of the Industry Department, with the participation of relevant departments, the Provincial People's Committee shall issue a decision to approve the plan and instruct the Industry Department to direct its implementation.
Article 7.
The procedures for reviewing and approving the power development plan are as follows:
1.For the national power development plan, the power development plan of Hanoi City and Ho Chi Minh City:
a)Within 45 days from receiving complete valid documents, the Ministry of Industry shall lead, cooperate with relevant ministries, sectors, localities, and Vietnam Electricity Corporation to conduct a review of the planning proposal. In necessary cases, the Ministry of Industry may hire consultants for review and counter-expertise to serve the review work;
b)After receiving formal written comments from relevant ministries, sectors, and localities on the planning proposal, the Ministry of Industry shall complete the review report and submit it to the Prime Minister for consideration and approval;
c)In case the planning proposal requires supplementation and modification, the Ministry of Industry shall request the consultant to make changes and supplements. Within 15 days from when the plan has been completed, the Ministry of Industry shall complete the review report and submit it to the Prime Minister for consideration and approval.
2.For the provincial power development plan:
a)Within 45 days from receiving complete valid documents, the Ministry of Industry shall lead, cooperate with relevant localities, and Vietnam Electricity Corporation to conduct a review of the plan. In necessary cases, the Ministry of Industry may hire consultants for review and counter-expertise to serve the review work;
b)After receiving formal written comments from relevant localities and Vietnam Electricity Corporation on the planning proposal, the Planning and Investment Department of the Ministry of Industry shall complete the review report and submit it to the Minister of Industry for consideration and approval;
c)In case the plan requires modification, the Ministry of Industry shall request the consultant to make changes and supplements. Within 15 days from when the plan has been completed, the Planning and Investment Department shall complete the review report and submit it to the Minister of Industry for consideration and approval.
3.For district power development planning:
a)Within 15 days from receiving the approval request for the power development plan and complete valid documents, the Industry Department shall lead, cooperate with relevant agencies and provincial electricity companies to conduct a review, prepare a review report, and submit it to the Chairman of the Provincial People's Committee for consideration and approval;
b)In case the plan requires modification, the Industry Department shall request the consultant to make changes and supplements. Within 15 days from when the plan has been completed, the Industry Department shall complete the review report and submit it to the Chairman of the Provincial People's Committee for consideration and approval.
Chapter III
Management and Implementation of Power Development Planning
Article 8.
Division of Responsibility for Managing and Implementing Power Development Planning as follows:
1.The Ministry of Industry is responsible for managing and implementing the national power development planning and provincial power development planning; directing the implementation of independent power projects according to the approved planning;
2.The Provincial People's Committee is responsible for directing and urging the implementation of power development planning within their jurisdiction;
3.Vietnam Electricity Corporation, organizations, and individuals involved in the power sector are responsible for implementing the national power development planning, provincial power development planning, and county power development planning related to them in accordance with the approved planning.
Article 9.
Amendments and Supplements to Power Development Planning Shall Be Conducted As Follows:
1.The Prime Minister shall approve amendments and supplements to the national power development planning, the power development planning of Hanoi City, and Ho Chi Minh City, based on the proposal of the Ministry of Industry;
2. The Minister of Industry shall approve the amendment and supplementation of the provincial power development plan upon the proposal of the Provincial People's Committee or Vietnam Power Corporation.
3. The Chairman of the Provincial People's Committee shall approve the amendment and supplementation of the district power development plan upon the proposal of the Department of Industry.
4. The investor shall not be permitted to implement projects that are inconsistent with the power development plan already approved by the competent authority.
5. Projects of Group A and B (as classified according to the current investment management regulations) which are not included in the approved plans may only proceed with investment preparation steps (feasibility study report, investment research report) upon permission from the Prime Minister based on the report of the Ministry of Industry. Within thirty days from receiving the request to supplement the project into the plan, the Ministry of Industry shall be responsible for reviewing and reporting to the Prime Minister, while also informing the requesting agency.
Article 10.
The reporting system regarding the implementation of the power development plan is as follows:
1. The Department of Industry of the province and Vietnam Power Corporation shall be responsible for compiling and reporting to the Ministry of Industry on the implementation status of the approved power development plans before December 20 each year.
2. The Department of Industry and the provincial power corporation shall be responsible for reporting to the Provincial People's Committee on the implementation status of the provincial power development plan before December 10 each year.
3. After being approved, the power development plan will be publicly announced. The Ministry of Industry shall be responsible for announcing the National Power Development Plan. The Provincial People's Committee and the municipal people's committees directly under the central government shall be responsible for announcing the provincial power development plan and the district power development plan.
ANNEX 1
Content of the power development plan proposal at the national level
(attached to Decision No. 21/2002/QĐ-BCN dated June 4, 2002 of the Minister of Industry)
Part I
Current state of the national power sector and implementation situation of the power development plan in previous stages
Chapter I. Current State of the National Power Sector
1.1. Organizational structure of the electricity industry in Vietnam
1.2. Current status of demand and supply of electric power
a) Demand for capacity and ability to meet
Statistics of maximum power values (Pmax) at load nodes of the 500kV, 220kV, and 110kV grid systems.
Analysis of typical daily, weekly, quarterly, and annual load curves nationwide and in regions.
Evaluation of the effectiveness of the demand-side management program in improving electricity usage patterns.
b) Demand for electricity and ability to meet it.
Aggregation and evaluation by types of electricity consumers.
Aggregation and evaluation by power companies.
Aggregation and evaluation by regions.
1.3. Situation of electricity production
a) Evaluation of the cost structure of electricity generation of existing power plants.
b) Status of equipment of power plants (including those of Vietnam Power Corporation, BOT, independent sources...).
c) Capacity and electricity generated (monthly statistics throughout the year to assess seasonal operation conditions), self-use ratio of power plants.
d) Fuel consumption rate in thermal power plants.
đ) Situation of boiler incidents at power plants.
e) Evaluation of technological level and environmental impact of existing power plants.
1.4. Current status of transmission and distribution networks
a) Analysis and evaluation in terms of structure, equipment status, and operational capacity of the transmission and distribution network systems.
b) Voltage and power factor (cos j) status at nodes of the transmission and distribution networks.
c) Evaluation of reliability, safety of power supply, and quality of electricity.
d) Analysis and evaluation of electricity transmission situations in regions and their exchanges, transmission network incident status.
đ) Evaluation of technical and commercial losses through transmission and distribution stages.
1.5. Current status of communication and control systems for the power system
a) Current status of the telecommunications system in the electricity industry.
b) Current status and control capability of the National Dispatch Center for the power system.
Chapter II. Situation of Implementation of the Electricity Development Plan for the Previous Planning Period
2.1. Comparison between Actual Electricity Demand and Forecasted Electricity Demand
2.2. Evaluation of the Implementation of the Power Source Development Program
2.3. Evaluation of the Implementation of the Power Grid Development Program
2.4. Economic and Financial Evaluation
2.5. General Assessment of the Implementation of the Previous Planning Period, Main Strengths and Weaknesses, Causes, and Lessons Learned
Part II
National Electricity Development Scheme for the Planning Period
Chapter III. Overview of Economic-Social Conditions and Energy System in Vietnam
3.1. General Characteristics of Vietnam
a) Geographic, Climate, and Hydrological Features
b) Overview of Economic-Social Conditions
- Current State of Vietnam's Economic Development During the Previous Planning Period
+ National Budget, Exchange Rate, and Inflation Rate During the Previous Planning Period.
+ Gross Domestic Product (GDP) by Economic Sectors, by Provinces, and Growth Rates.
+ Per Capita GDP.
+ GDP Structure.
- Scenarios for Economic-Social Development During the Planning Period
+ Economic-Social Development Scenarios by Sectors and Regions During the Planning Period.
+ Overview of Economic-Social Development and Energy in Neighboring Countries and Prospects for Economic and Energy Cooperation Between Our Country and These Countries.
3.2. Comprehensive Analysis of Vietnam's Energy System
a) Energy-Economic Correlation During the Previous Planning Period.
b) Overview of Energy Supply and Demand During the Planning Period.
- Analysis of Primary Energy Production Capacity.
- Current Status and Potential for Importing and Exporting Various Forms of Energy.
c) Energy Balance During the Planning Period and Orientation for Energy and Fuel Development for the Next Ten Years.
- Evaluation of Primary Energy Sources' Potential: Coal, Oil, Gas, Nuclear, Hydropower, Geothermal...
- Long-Term Forecast of Primary Energy Sources' Exploitation and Utilization Capacity.
- Long-Term Forecast of Energy Consumption Needs.
- Energy Balance for the Planning Period, Considering Energy Exchange with Neighboring Countries.
Chapter IV. Forecast of Electricity Demand
4.1. Introduction to Models and Methods for Forecasting Electricity Demand
4.2. Selection of Suitable Models and Methods for Forecasting Electricity Demand in Vietnam
4.3. Forecast of Electricity Consumption During the Planning Period
a) Forecast of Installed Capacity and Electricity Consumption for Power Companies, Regions (North, Central, South).
b) Forecast of National Installed Capacity and Electricity Consumption for Key Years During the Planning Period.
c) Forecast of Electricity Consumption Patterns for Regions and Nationally During the Planning Period (Typical Daily Load Curves by Season, Annual Load Curves, Average Monthly Capacity, and Maximum Monthly Capacity).
4.4. Demand Side Management (DSM) Program
a) Implementation of DSM in Vietnam.
b) Potential for DSM in Vietnam.
c) Policy Mechanism for the DSM Program.
d) Implementation Plan for the DSM Program.
đ) Forecast of the DSM Program's Effectiveness.
4.5. Load Aggregation
a) Load Aggregation at Transmission Network Nodes of 110kV and Above for Planning Period Milestones.
b) System-Wide Load Aggregation for Planning Period Milestones.
4.6. Statistics on Electricity Consumption in Some Countries Worldwide and in the Region
4.7. Conclusions and Recommendations on Load Scenarios.
Chapter V. Economic and Technical Standards for Power Generation Projects and Grids
5.1. Investment Capital Standards
5.2. Fuel Standards
5.3. Technical Standards
Chapter VI. Evaluation of Primary Energy Sources, Development Potential, Export and Import Capacity, and Fuel Price Forecasting
6.1. Coal Evaluation
a) Coal reserves categorized by type, exploration level, region...
b) Coal extraction capacity over each phase.
c) Domestic coal quantity available for power generation.
d) Evaluation of coal import potential.
6.2. Natural Gas Evaluation
a) Gas reserves categorized by level, exploration block, extraction efficiency...
b) Natural gas extraction capacity over each phase.
c) Quantity of natural gas available for power production.
d) Evaluation of pipeline system formation potential within the region and prospects for gas export and import in Vietnam.
6.3. Oil Evaluation
a) Oil reserves and crude oil extraction capacity.
b) Prospects for developing the oil refining and petrochemical industry in Vietnam, quantity of oil available for power production.
6.4. Uranium Reserves Evaluation in Vietnam
6.5. Geothermal Potential Evaluation and Prospects for Developing Geothermal Power Plants
6.6. Hydropower Evaluation
a) Hydropower reserves in Vietnam and development potential.
b) Hydropower reserves in neighboring countries and their potential to supply electricity to Vietnam.
6.7. Fuel Price Forecast for the Planning Period
a) Methods and bases for forecasting fuel prices.
b) Crude oil price.
c) Uranium price.
d) Prices of FO and DO products.
đ) Domestic and imported coal prices.
e) Natural gas price.
Chapter VII. Power Generation Development Program
7.1. Methodology for Power Generation Development
a) Introduction to commonly used software worldwide for determining the power generation development program.
b) Comparison of software features, selection of software for calculating the power generation development program.
7.2. Calculation Conditions for the Power Generation Development Program
a) Ranking hydropower projects based on investment costs, considering the transmission grid to load centers.
b) Evaluating the ability of natural gas sources to supply power, considering the possibility of exchange with neighboring countries.
c) Domestic coal extraction capacity and imports.
d) Evaluating the potential to import electricity from neighboring countries.
đ) Environmental factors and resettlement planning for hydropower projects.
7.3. Power Generation Development Scenarios
a) Based on calculation conditions, using selected software, determine several power generation development scenarios.
b) Analyze and evaluate the economic and technical results of the aforementioned power generation development scenarios.
c) Recommend some optimal development scenarios (equivalent economic and technical standards).
7.4. Balancing Capacity and Electricity Production Among Scenarios
Basedon recommended scenarios, establish a balance between capacity and electricityproduction, determining:
a) Electricity production of power plants and various types of power plants.
b) Electricity exchange among regions.
c) Electricity exchange between Vietnam and neighboring countries.
d) Evaluate the energy mix structure at five-year and ten-year milestones during the planning period (hydroelectricity, gas-fired thermal power, coal-fired thermal power, oil-fired thermal power, nuclear power...).
7.5. Demand for Fuels for Power Production
Basedon the power generation development scenarios in the planning period, determine:
a) Demand for coal (domestic and imported).
b) Demand for natural gas.
c) Demand for various types of oil.
d) Nuclear fuel demand.
7.6. Recommendations for Priority Power Generation Projects to Develop Through Various Phases
Chapter VIII. Power Grid Development Program
8.1.Standards and databases used when developing the power grid development program
8.2.Methodology for developing the power transmission grid development program
8.3.Introduction to software for system analysis
8.4.Determining power grid development options corresponding to proposed power generation scenarios
8.5.Calculating power distribution during dry season and flood season operation modes for each grid structure option
8.6.Dynamic and static stability analysis of the system for various grid structure options
8.7.Calculating short-circuit currents at key nodes in the system
8.8.Analysis and selection of power transmission grid development options through different stages
8.9.Analysis and determination of reactive power compensation required for the power transmission grid in years five, ten, fifteen, and twenty within the planning period
8.10.Determining the volume of power transmission grids to be constructed through different stages (five years, ten years, and projected ten years thereafter)
8.11.List of construction projects during the planning period
8.12.Some conclusions and recommendations regarding the power grid development program
Chapter IX. Regional Power Grid Interconnection
9.1.General overview of the power development programs of countries in the region (mainly countries in the Mekong region)
9.2.Primary energy potential for electricity production in countries in the region
9.3.Assessment of electricity import and export capacity of countries in the region
9.4.Capability of interconnecting Vietnam's power system with those of other countries in the region
9.5.Analysis of Vietnam's power system in relation to the interconnected systems of other countries in the region
9.6.Forecasting imported electricity prices from countries in the region over different periods
Chapter X. Rural, Mountainous, and Island Power Development Program (Rural Electrification Program)
10.1.Characteristics of rural areas in Vietnam
10.2.Current status of electricity supply to rural areas in Vietnam
10.3.Evaluation of the implementation of the Rural Electrification Program in previous planning phases
10.4.Rural Electrification Program of Vietnam in the current planning phase
10.5.Solutions for supplying electricity to remote and far-flung areas where national power grids cannot reach economically or feasibly
10.6.Investment capital and policy mechanisms when implementing the Rural Electrification Program
Chapter XI. System Operation and Information for Vietnam's Power System
11.1.Operation of Vietnam's Power System
11.2.Power Telecommunication Information System of Vietnam
Chapter XII. Environment and Environmental Protection in Power Development
12.1.Environmental Impact of the Power Generation Development Program
a)Environmental impact assessment of sources:
-Hydropower
-Thermal power (oil-fired, coal-fired, gas-fired, diesel, nuclear ...)
-Other power sources
b)Recommendations for solutions to mitigate negative environmental impacts
12.2.Environmental Impact Assessment of the Power Grid Development Program
Chapter XIII. National Investment Program for Power Development
13.1.Capital investment for power generation projects
13.2.Capital investment for power grid development
13.3.Capital investment for other project components serving power development
13.4.Comprehensive national power development investment capital
13.5.Capital structure for national power development investment
Chapter XIV. Economic-Financial Analysis of National Power Development Plans
14.1. Electricity Pricing System
a) Long-term marginal costs for power development
b) Collection and analysis of electricity pricing tables from countries in theregion
c) Basic principles for electricity pricing
d) Current electricity pricing table of the Vietnamese power industry
đ) Recommendations for directions in the construction of electricity pricingtables during the planning period
14.2. Financial Analysis of Power Development Plans During the Planning Period
a) The financial relationship among production, transmission, and distributionstages of the power industry
b) Financial analysis
c) For Vietnam Power Corporation
d) For the production and transmission process
đ) For power distribution companies
e) Analysis of pricing mechanisms for BOT and IPP projects within the Vietnamese electricity pricing system
14.3. Conclusions and Recommendations on Mechanisms and Policies to Ensure theImplementation of Power Development Programs During the Planning Period
Chapter XV. National Power Organizational Mechanism
15.1. Current Status of the National Power Management Organizational Mechanism
15.2. Recommendations for Reforming the Power Industry's Organizational Structure
Part III
Conclusion and Recommendations
Part IV
Appendices
I. Load Forecasting Documents
1. Survey and statistical data for load forecasting
2. Changes in the structure of national and regional electricity consumption duringthe planning period
a) Electricity consumption by season and components (industrial, agricultural,service...)
b) Electricity consumption by voltage level
c) Number of households and amount of electricity consumed in the residentiallighting component according to the current electricity pricing table
2. Capacity and consumption patterns of some 110, 220kV substations
3. Maximum and minimum capacity
4. Electricity consumption charts of some 110kV substations supplying typicalconsumers: industrial, urban residential, rural, mountainous...
5. Data on concentrated industrial zones, export processing zones
6. Industrial zones that have been granted licenses, characteristics of industrialzones
7. Industrial zones that have commenced operations
8. Capacity and energy usage in constructed industrial zones
9. Prospects for the development of industrial zones in the coming years
10. Load profiles of companies and regions in past years
11. Average statistics according to hourly ratios throughout the year
12. Analysis of consumption patterns
13. Collection and processing of statistical data on the development of variousnational economic sectors by region and sector
14. Forecast results based on different models
15. Comparison of forecast results
16. Detailed forecast results on consumption patterns
II. Basis Documents for Planned Power Generation Projects
2.1. Thermal Power Plants
a) Technical characteristics of thermal power plants
b) Main features of planned thermal power plant locations: climate, hydrology,transportation, water supply, fuel supply...
2.2. Hydroelectric Power Plants
a) Key parameters of planned hydroelectric power plants
b) Hydrological and hydropower data for projects
III. Data and Calculation Results of Power Generation Development Scenarios
a) Input data for thermal and hydroelectric power plants in planning models
b) Calculation results of power generation development scenarios
IV. Data and Calculation Results of Power Transmission Grid Development Scenarios
4.1. Data for calculating establishment conditions, system stability analysis...
4.2. Calculation results of power grid development scenarios
4.3. List of planned transmission lines and substations to be developed throughvarious stages
V. Data and Calculation Results of Economic and Financial Analysis
a) Input data for economic and financial analysis
b) Investment capital calculation table for power generation and grid development
c) Financial calculation results of power industry scenarios
VI. Data and Balance Energy Results
Vietnam's energy balance for the planning period
Appendix 2
Content of the Provincial and Central City Power Development Master Plan Proposal
(attached to Decision No. 21/2002/QĐ-BCN dated June 4, 2002 of the Minister ofIndustry)
A. Explanatory Section
PART I.Analysis of the current status of power sources, grid, and implementation ofplanning in the previous period
1.1. Current Status of Power Sources and Grids:
a) Evaluation based on statistical data
Power Supply Sources
+ Statistics of installed capacity of power stations connected to the nationalgrid
+ Determination of the ability to receive power from the national grid
+ Statistics of independent power sources currently in operation (smallhydroelectric power plants, renewable power sources, new energy sources...)
+ Analysis and synthesis of local independent power sources with potential fordevelopment
Power Grid
+ Statistics of installed capacity of distribution substations (low voltage) andcurrent utilization of transformer capacities according to seasons and loadconditions
+ Statistics of length and technical specifications (voltage, conductor crosssection, load capacity, insulator type, pole type...) of power lines
+ Statistics of actual loading of power lines according to operational conditions
+ Analysis of interconnection capabilities of lines within the planning area andwith other lines in the national power system
+ Statistics and analysis of recent electricity loss situations
b) Evaluation based on calculation results
Calculation of power distribution and technical losses for medium voltage grids(some technical parameters such as Tmax, t, cos j, simultaneity factor... takenaccording to previous regulations of the Ministry of Energy or guidelines of theMinistry of Industry) for typical conditions such as maximum power, minimumpower in winter and summer
Based on calculation results, evaluate the current state of the grid, actualloading capacity, and hidden potential exploitation capacity of lines andtransformers. Analyze management and operation situations, summarize thestrengths and weaknesses of the distribution grid system
1.2. Evaluation of the implementation of the power development planning phase prior to this period.
a) Electricity demand, its actual and forecasted growth rate.
b) Assessment of the implementation of the power source development program and the power grid.
1.3. Some observations.
a) Based on points a and b of Section 1.1, provide comments on the current status of the local power grid, evaluate and classify power stations, distribution substations, and power lines regarding their capacity for mobilization, requirements for renovation and development.
b) Classify loads according to economic sectors, structure of electricity consumption by sector, paying particular attention to large industrial loads, loads serving irrigation, and loads for economically disadvantaged regions.
Evaluate the current status and management mechanism of low-voltage power grids, losses, and electricity prices in different economic zones of the locality.
d) Provide an overall assessment of the implementation of the previous planning phase, including main strengths and weaknesses, causes, and lessons learned.
Chapter II. Characteristics and directions for economic and social development.
2.1. Natural and socio-economic characteristics of the locality.
Summarize and assess the socio-economic development situation of the locality over the past five years in the following areas:
a) Agriculture.
Total cultivated area, natural characteristics.
Types of crops.
Total irrigated area suitable with natural conditions and crops.
b) Local industry and small-scale cottage industry.
Summarize the development situation of local industry, small-scale cottage industry, total value of products.
Situation of electricity consumption by local industrial enterprises and small-scale cottage units.
c) Central industries located in the locality.
Industrial enterprises and factories located in the locality.
Production situation and level of electricity consumption over the past five years.
d) Various service activities, cultural and social life of the people.
2.2. Directions for socio-economic development during the planning period.
Based on the approved comprehensive socio-economic development plan of the locality, summarize the main socio-economic development goals of the locality, emphasizing the following aspects:
a) Forecast of population development and rural urbanization.
b) Development of agricultural production, irrigation systems serving agriculture.
c) Development of local industry and small-scale cottage industry, central industries located in the locality. It is necessary to emphasize projects with feasibility, and economically disadvantaged areas to formulate appropriate and effective power grid systems.
d) The relationship between socio-economic development and power development.
Chapter III. Forecast of electricity demand.
3.1. Methodology and basis for forecasting electricity demand.
a) Introduce models and methods for forecasting electricity demand.
b) Select models and methods for forecasting electricity demand that are suitable for the locality's circumstances.
3.2. Load zoning for electricity.
Load zoning must be consistent with the approved overall development plan of the locality and the financial feasibility of major industrial projects. On this basis, clearly define:
a) High feasibility industrial zones.
b) Industrial projects without clear financial feasibility, unable to calculate clear economic benefits.
c) Urbanizing residential areas.
d) Pure agricultural residential areas with normal economic development.
đ) Economically difficult or extremely difficult areas.
3.3. Calculation of electricity demand.
Based on Sections 2.1 and 2.2, determine load zones according to socio-economic development targets. For each load zone, determine the following basic parameters:
a) Consumption capacity of typical years in the planning proposal.
b) Electricity demand by planning years.
c) Total demand for capacity and energy in typical years during the planning period. For agricultural loads, consider the special load profile where the maximum capacity utilization time is very short (a few hours a day) to appropriately calculate capacity.
3.4. Comments on the results of electricity demand calculation.
Comments on the ability of local power sources and national power system sources to meet load demands in planning years, and professional, economic-technical recommendations.
Chapter IV. Power Development Scheme.
4.1. Views and design standards for the power development scheme.
Based on the current regulations' requirements for power supply safety, propose views and design standards for the power development scheme. These views and design standards are clearly defined for each voltage level in the planning:
High-voltage transmission system (220, 110kV).
Medium-voltage distribution network.
Low-voltage power network.
4.21. Propose power development options.
Balance power sources and loads for each region and locality corresponding to each planning phase.
Based on analyses, conclusions, and recommendations from Chapters I and II, balance power sources and loads, and propose several power improvement and development options. Then, using expert methods, select three typical options:
a) Option I meets the maximum load for the locality's socio-economic development needs (no investment capital limit, locality has no financial difficulties).
b) Option II meets the maximum load for residential areas and high feasibility industrial zones, projects already approved and financially guaranteed by the State.
c) Option III has limited investment capital.
4.23. Power source and grid development scheme.
a) Develop a power grid improvement and development scheme for the selected options in Section 4.21.
b) Choose technical features of independent power sources, power generation substations, and power lines for each option.
4.4.3 Selection of options.
a) Calculate economic-technical indicators for the grid and power sources for the above options.
- Power loss, voltage, energy in the power grid system, power distribution on the line, etc.
- Economic-technical indicators of power sources.
- Economic, financial, and social indicators.
b) Select the option.
Based on economic-technical indicators and social policies, choose the optimal option for the planning proposal.
Chapter V.Small hydropower and renewable energy planning.
5.1. Current status and potential of small hydropower.
5.2. Evaluation of potential and applicability of renewable energy sources.
Chapter VI. Investment Volume for Construction
6.1. Based on the selected scheme for grid renovation and development in Chapter IV, calculate the volume of new construction and grid renovation, and compute the total investment capital for the project.
6.2. Establish a schedule table for each project component (source substations, independent power sources, distribution substations, medium and low voltage lines) and corresponding financial requirements.
Chapter VII. Economic and Financial Analysis
7.1. Conditions for analysis:
a) Views and methodological approaches to calculation.
b) Conditions and assumptions about data included in the calculations.
7.2. Analysis of calculation results: economic and financial
a) Analysis of the economic and financial efficiency of the chosen investment option
b) Sensitivity analysis
c) Financial flow analysis for the chosen option
7.3. Conclusion of the economic and financial analysis section
Chapter VIII. Conclusions and Recommendations
8.1. Summary of the project content
a) Summary of the main contents of the local power grid planning project.
b) Summary of the strengths and weaknesses of the distribution system, existing issues in management and operation in previous years, and the advantages that the project will bring.
8.2. Recommendations:
a) Compilation of difficulties and obstacles encountered when implementing the planning project.
b) Proposals for mechanisms and policies, organizational solutions to implement the planning project.
Appendix B
Appendix 1: List of industrial and construction loads
Specifications for rescue and emergency response command bands List of agricultural, forestry, and fisheries loads
Technical requirements and testing methods for 1-Butanol List of service and trade loads
Appendix 4: Electricity demand for management consumption and residents
Appendix 5: Electricity demand for other activities
Appendix 6: List of provincial (city) substations up to year...
Appendix 7: Calculation results of high-voltage grid operation modes at different stages (including worst-case fault scenarios) and short-circuit calculations.
Appendix 8: Calculation results of medium-voltage grids after 110kV substations at different stages.
Appendix 9: Construction volume of 220kV and 110kV high-voltage grids at different stages (create tables).
Appendix 10: Construction and renovation volume of substations by districts and towns up to year...
Appendix 11: Construction and renovation volume of medium-voltage lines by districts and towns up to year... (create tables).
Appendix 12: Construction volume of small hydropower plants and new energy projects (including upgrades and new constructions).
Appendix 13: Economic and financial analysis calculation table
Appendix 14: Financial flow analysis calculation table
C. Drawings Section
1.Map of 220-110kV grid throughout the province (city) up to year...
2.Principle diagram of 220-110kV grid throughout the province (city) up to year...
3.Map of district (town) distribution grid
4.Principle diagram of district (town) distribution grid
5.Various calculation diagrams for normal and fault conditions...
Tel:
Content of the district, county, town, and city-level power development planning project
(attached Decision No.: 21/2002/QĐ-BCN dated June 4, 2002 of the Minister of Industry))
A. Explanatory Section
Preface (general introduction)
Chapter I. Current Status of Power Sources, Grids, and Implementation of Planning in Previous Stages
1.1.Power Sources and Distribution Centers
1.2.Grids
1.3.Situation of Power Supply and Consumption
1.4.Evaluation of Implementation in Previous Stages
1.5.General Comments and Evaluation
Chapter II. General Characteristics and Directions for Economic-Social Development
2.1.Natural Characteristics
2.2.Current Economic-Social Situation
2.3.Directions for Economic-Social Development
Chapter III. Forecasting Electricity Demand and Load Zoning
3.1.Forecasting Directions for Economic-Social Development
3.2.Legal Foundations for Determining Electricity Demand
3.3.Forecasting Electricity Demand
a)Electricity Demand for Industry and Construction
b)Electricity Demand for Agriculture, Forestry, and Aquaculture
c)Electricity Demand for Services and Commerce
d)Electricity Demand for Management and Residential Use
đ)Electricity Demand for Other Activities
3.4.Load Zoning
Chapter IV. Design of Grid Improvement and Expansion Schemes for Counties, Cities Directly Under Provinces, and Towns
4.1.Balance of Power Supply and Demand
4.2.Design of Power Supply Schemes
Chapter V. Construction Volume and Investment Capital
5.1.Construction Volume and Progress
5.2.Determination of Total Investment Capital and Sources of Capital
Chapter VI. Economic-Financial Analysis
6.1.Economic-Financial Analysis
6.2.Sensitivity Analysis
Chapter VII. Conclusions and Recommendations on Mechanisms and Policies for Implementing the Plan
Appendix B
Appendix 1: List of Industrial and Construction Loads
Appendix 2: List of Agricultural, Forestry, and Aquaculture Loads
Appendix 3: List of Service and Commercial Loads
Appendix 4: Electricity Demand for Management and Residential Use
Appendix 5: Electricity Demand for Other Activities
Appendix 6: List of Medium Voltage Substations to Year...
Appendix 7: Results of Calculations for Medium Voltage Grid Operation Modes in Various Stages (Including Worst Case Scenarios)
Appendix 8: Construction Volume of Medium Voltage Line Renovation to Year... (Prepare Table)
Appendix 9: Construction Volume of Small Hydropower Plants and New Energy Projects (Including Upgrades and New Construction if Any)
Appendix 10: Financial-Economic Analysis Calculation Table
C. Drawings Section
1.Map of County, District (City), and City Directly Under Province Distribution Networks.
2.Schemes for Normal and Fault Conditions Calculations...
DEPUTY MINISTER