Decision No. 2241/QD-BNN-TCLN approves the forest land use purpose change file for the construction of the national 500kV Son La - Hiep Hoa power transmission line passing through the land of the Northeast Scientific Production Forestry Center under the Vietnam Academy of Forestry Sciences, with specific area details.
要点
- The Vietnam Academy of Forestry Sciences shall have its forest land use purpose changed at two tower locations and safety clearance areas, with a total area of 1.16151 hectares.
- The Northeast Scientific Production Forestry Center under the Vietnam Academy of Forestry Sciences shall cooperate with the State Grid Corporation to prepare the design file for harvesting planted forests and to develop the replanting plan file.
- The State Grid Corporation shall be responsible for cooperating with the Northeast Scientific Production Forestry Center to develop the replanting plan file.
🌐 本文件的社会影响
- Enterprises will need to undertake complex procedures related to changing the purpose of forest land use, which may impose burdens on time and cost.
- The construction of the national power transmission project may impact the natural environment and livelihoods of people living in the area.
❓ 常见问题
Where does the Vietnam Academy of Forestry Sciences have its forest land use purpose changed?
The Vietnam Academy of Forestry Sciences has its forest land use purpose changed at two tower locations within plot 3, plot 5 section 1 area Lung Va, Ngoc Than commune, Vinh Phuc province.
What must the Vietnam Academy of Forestry Sciences do after having its forest land use purpose changed?
The Vietnam Academy of Forestry Sciences must cooperate with the State Grid Corporation to prepare the design file for harvesting planted forests and to develop the replanting plan file.
What is the area of land whose purpose of use is being changed from forest?
The area of land whose purpose of use is being changed for constructing power towers is 0.19151 hectares and for safety clearance areas is 0.97 hectares, totaling 1.16151 hectares.
What responsibilities does the State Grid Corporation have?
The State Grid Corporation is responsible for cooperating with the Northeast Scientific Production Forestry Center to develop the replanting plan file.
全文
Pursuant to …;
Regarding the approval of the file for changing the purpose of forest land use to construct the 500kV Son La - Hiep Hoa national power transmission project passing through the land area of the Northeast Forest Science and Production Center under the Vietnam Forest Science Institute
________________________________
THE MINISTER OF AGRICULTURE AND RURAL DEVELOPMENT
Pursuant to the Law on Protection and Development of Forests, Government Decree No. 23/2006/ND-CP dated March 3, 2006, guiding the implementation of the Law on Protection and Development of Forests;
Pursuant to Government Decree No. 117/2010/ND-CP dated December 24, 2010, on the organization and management of special-use forests;
Pursuant to Government Decree No. 01/2008/ND-CP dated January 3, 2008, stipulating the functions, tasks, powers, and organizational structure of the Ministry of Agriculture and Rural Development; Government Decree No. 75/2009/ND-CP dated September 10, 2009, amending Article 3 of Government Decree No. 01/2008/ND-CP dated January 3, 2008;
Pursuant to Decision No. 1243/QD-BTNMT dated June 13, 2008, of the Ministry of Natural Resources and Environment approving the environmental impact assessment report for the 500kV Son La - Hiep Hoa power transmission line project;
Considering the proposal of the Director of the Vietnam Forest Science Institute at Report No. 540/TT/KHLN-KH dated September 21, 2011, of the Vietnam Forest Science Institute regarding the change of forest land use purpose for constructing the power transmission project and recovering the value of forest products on the converted land area and within the power line safety zone;
At the proposal of the Director General of the Forest Management Department,
DECISION:
Article 1. Approve the file for changing the purpose of forest land use to construct the 500kV Son La - Hiep Hoa national power transmission project passing through the land area of the Northeast Forest Science and Production Center under the Vietnam Forest Science Institute with the following contents:
1. The location for changing the purpose of forest land use to construct the power transmission project is at two tower positions in lot 3, lot 5, compartment 1, Lung Va area, Ngoc Than commune, Vinh Phuc province;
2. The area for changing the purpose of forest land use to construct the power transmission towers is 0.19151 hectares and the power line safety zone is 0.97 hectares;
Article 2. Direct the Vietnam Forest Science Institute to instruct the Northeast Forest Science and Production Center to cooperate with the National Power Transmission Corporation to prepare the design exploitation harvesting plan for planted forests strictly according to the locations and areas specified in Clause 1.
The National Power Transmission Corporation shall be responsible for cooperating with the Northeast Forest Science and Production Center to develop the replanting plan in accordance with current laws.
Article 3. The Head of the Ministry's Office, Heads of relevant Departments, General Directors of the Forestry General Department, Director of the Vietnam Forest Science Institute, Heads of related agencies shall be responsible for implementing this Decision.
DEPUTY MINISTER