This Decision issues the Regulation on the Operation of the Water Regulation Working Group of the Se San River, applicable to all members of the group. The group is tasked with coordinating with Cambodia to establish mechanisms to avoid damage caused by water discharge from the Ialy Reservoir and other hydropower projects on the Se San River.
Scope of application
The Water Regulation Working Group of the Se San River includes the Head, Deputy Head, and members concurrently serving from the Ministry of Industry, Vietnam Mekong River Commission, Vietnam Electricity Corporation, People's Committee of Gia Lai Province, and Kon Tum Province.
Key points
- The Head of the Water Regulation Working Group of the Se San River is responsible for establishing mechanisms to avoid damage caused by water discharge from the Ialy Reservoir and other hydropower projects, contributing opinions to improve power generation efficiency, flood control, and ensure safety of hydropower facilities.
- In case the Head is unavailable, the Deputy will perform the responsibilities of the Head.
- Members report and seek opinions from leaders of Ministries, Departments, and Localities on issues assigned for research and contribution of opinions.
- There are two meetings annually: one exclusive for Vietnam and one joint with Cambodia. The content, location, and time of the meeting will be notified two months in advance.
- The operating budget of the Working Group is covered by the Ministry of Industry when attending meetings, and from the budget allocated to the Ministry of Industry and funds raised from other sources.
🌐 Social impact of this document
- Positive impact: The Working Group will help reduce damage caused by water discharge from the Ialy Reservoir, enhance power generation efficiency, and agricultural productivity downstream.
- Negative impact: Concurrently appointed members may face difficulties balancing their primary duties and those of the Working Group.
❓ Frequently asked questions
Who comprises the Water Regulation Working Group of the Se San River?
The Working Group includes the Head, Deputy Head, and concurrently appointed members from the Ministry of Industry, Vietnam Mekong River Commission, Vietnam Electricity Corporation, People's Committee of Gia Lai Province, and Kon Tum Province.
What are the responsibilities of the Head?
The Head is responsible for establishing mechanisms to avoid damage caused by water discharge from the Ialy Reservoir, contributing opinions to improve power generation efficiency, flood control, ensuring safety of hydropower facilities, and convening regular or extraordinary meetings of the Working Group.
How many meetings are held annually?
Annually, there are two meetings: one exclusive for the Vietnam Working Group and one joint with the Cambodian Working Group. The content, location, and time of the meeting will be notified two months in advance.
Where does the operating budget of the Working Group come from?
The operating budget is covered by the Ministry of Industry when attending meetings, and from the budget allocated to the Ministry of Industry and funds raised from other sources.
Are members reimbursed for travel expenses when participating in meetings?
Members are reimbursed for travel, accommodation, meals, and related expenses when attending meetings.
Full text
Pursuant to …;
Regarding the issuance of the Regulation on the Operation
of the Working Group for Water Regulation of the Sesan River
_______________
THE MINISTER OF INDUSTRY
Pursuant to the Government Decree No. 74/CP dated November 1, 1995 on the functions, tasks, powers, and organizational structure of the Ministry of Industry;
At the proposal of the Director of the International Cooperation Department, Head of the Working Group for Water Regulation of the Sesan River,
DECISION:
Article 1. To issue the attached Regulation on the Operation of the Working Group for Water Regulation of the Sesan River.
Article 2. This Decision shall take effect fifteen days from the date of signature. The Director of the Ministry's Office, the Director of the International Cooperation Department, the Director of the Organization and Cadres Department, and the members of the Working Group for Water Regulation of the Sesan River are responsible for implementing this Decision.
| THE MINISTER (Signed) Đặng Vũ Chư |
REGULATIONS
Operation of the Working Group for Water Regulation of the Sesan River
_______________________
(Issued together with Decision No. 24/2001/QĐ-BCN
dated May 10, 2001 of the Minister of Industry)
PART I
GENERAL PROVISIONS
Article 1. This Regulation applies to the Working Group for Water Regulation of the Sesan River (hereinafter referred to as "the Working Group"), established pursuant to Decision No. 0254/QĐ-HTQT dated February 8, 2001 of the Minister of Industry based on the opinion of the Prime Minister (Letter No. 104/CP-QHQT dated November 13, 2000 of the Government Office) and the nomination of participants by the Ministry of Agriculture and Rural Development, the Vietnam Mekong River Commission, the People's Committee of Gia Lai Province, the People's Committee of Kon Tum Province, and the Vietnam Electricity Corporation.
Article 2. The Head of the Working Group is responsible for organizing and supervising the implementation of this Regulation; periodically compiling the situation and proposing the Ministry to issue a decision on amending and improving the Regulation.
Chapter II
GENERAL TASKS
Article 3. The Working Group is tasked with coordinating with the Cambodian side to establish mechanisms and solutions to avoid damage to the downstream area due to water discharge from the Ialy Reservoir and other hydropower projects on the Sesan River in the future.
Chapter III
ASSIGNMENT OF RESPONSIBILITIES
Article 4. Responsibilities of the Head
Based on the guidance of the Prime Minister (Letter No. 53/CP-QHQT dated August 4, 2000 regarding the impact of the Ialy Reservoir on Cambodia) and the guidance of the Minister of Industry, the Head is responsible for directing the Working Group:
1. Establishing mechanisms and solutions to avoid damage to the downstream area due to water discharge from the Ialy Reservoir and other hydropower projects on the Sesan River,
2. Contributing opinions on research contents related to increasing power generation efficiency, flood control, enhancing agricultural productivity in the downstream area, and ensuring safety for hydropower plant facilities on the Sesan River,
3. Urging the Vietnam Electricity Corporation to implement five measures directed by the Prime Minister in Letter No. 104/CP-QHQT dated November 13, 2000,
4. Jointly with the Cambodian side to agree on the content and plan for implementing the project to assess environmental impacts on the downstream area due to water discharge from the Ialy Reservoir,
5. Compiling these contents to report to the Minister before discussing with relevant Vietnamese agencies, the Cambodian side, or Consultants,
6. The Head is responsible for convening and chairing regular or extraordinary meetings of the Working Group, concluding issues discussed at meetings; leading the Vietnamese Working Group in working with relevant Vietnamese agencies, the Cambodian side, or Consultants.
Article 5. Responsibilities of the Deputy Head of the Working Group
In case the Head is busy with other work, the Deputy Head of the Working Group shall perform the responsibilities of the Head as stipulated in Article 4 upon request of the Head.
Article 6. Responsibilities of Members
1. Report and seek opinions from the Ministry's, Sector's, and Local Authority's leaders on issues assigned for research and contribution of opinions.
2. Prepare proposals from the Ministry, Sector, and Local Authorities.
3. Seek opinions from the Ministry's, Sector's, and Local Authority's leaders on issues requiring common agreement.
4. Implement the assignments of the Team Leader.
5. Members concurrently serve at various Ministries, Sectors, and Local Authorities.
6. Attend all meetings of the Working Group when invited with a notice.
7. Members must strictly adhere to the reporting system for the tasks they are assigned to monitor.
Chapter IV
WORKING REGIME
Article 7. Working Regime
Members of the Working Group shall be convened for meetings as required by work and upon receipt of notices from the Ministry of Industry.
Annually, there are two (2) meetings: One meeting exclusively for the Working Group of Vietnam, and one joint meeting with the Working Group of Cambodia. The content, location, and time of the meetings will be notified two (2) months in advance.
In case of emergencies, the Ministry of Industry will issue notices to convene members.
Chapter V
OTHER PROVISIONS
Article 8. Operating Expenses
When attending meetings, members are covered by their respective Ministries, Sectors, and Local Authorities for travel, accommodation, meals, and related expenses.
Regular operating expenses and organizing regular and emergency meetings of the Working Group are funded from the budget allocated to the Ministry of Industry for incoming and outgoing delegations and other sources of funding, including the Electricity Corporation and the Mekong River Commission.
Article 9. Documents and Information
Documents and information relevant to the Working Group's tasks shall be provided by the Team Leader to all members for reference, study, proposal, and safekeeping./.