Decision No. 31/2005/QĐ-BXD of the Minister of Construction on issuing the Regulation on Architectural Management in the area surrounding the National Convention Center shall take effect fifteen days after its publication in the Official Gazette. This regulation applies to the People's Committees of relevant districts and communes, investors in construction projects in the area, as well as related agencies, organizations, and individuals.
Scope of application
The People's Committee of Hanoi City, the People's Committee of Tu Liem District, the People's Committee of Cau Giay District, the People's Committee of Thanh Xuan District, the People's Committee of Me Tri Commune, investors in construction projects in the area surrounding the National Convention Center, and related agencies, organizations, and individuals.
Key points
- The People's Committee of Hanoi City, Tu Liem District, Cau Giay District, Thanh Xuan District, and Me Tri Commune are responsible for implementing this Decision.
- Investors in construction projects in the area surrounding the National Convention Center must comply with the architectural management regulations issued.
🌐 Social impact of this document
- Positive impact: This provision will contribute to ensuring aesthetic and harmonious architectural development in the area surrounding the National Convention Center, enhancing the cultural and historical value of the site.
- Negative impact: It may cause difficulties for investors when implementing construction projects due to the need to comply with architectural regulations.
❓ Frequently asked questions
To which areas does this Decision apply?
This Decision applies to the area surrounding the National Convention Center, including Tu Liem District, Cau Giay District, Thanh Xuan District, and Me Tri Commune of Hanoi City.
What regulations must construction investors comply with?
Investors in construction projects in the area surrounding the National Convention Center must comply with the architectural management regulations issued together with this Decision.
When does this Decision come into effect?
This Decision shall take effect fifteen days after its publication in the Official Gazette.
What actions must related agencies, organizations, and individuals take to implement this Decision?
The People's Committee of Hanoi City, the People's Committee of Tu Liem District, Cau Giay District, Thanh Xuan District, and the People's Committee of Me Tri Commune, investors in construction projects in the area, and related agencies, organizations, and individuals must be responsible for implementing this Decision.
What contents does the architectural management regulation issued together with this Decision include?
Specific information about the contents of the architectural management regulation issued together with this Decision is not mentioned in this Decision. Citizens and businesses need to refer to the architectural management regulation issued together with this Decision for detailed information.
Full text
DECISION OF THE MINISTER OF CONSTRUCTION
Regarding the Issuance of the Architectural Construction Management Regulation
Surrounding the National Convention Center Area
THE MINISTER OF CONSTRUCTION
Pursuant to the Construction Law No. 16/2003/QH11 dated November 26, 2003;
Pursuant to Decree No. 36/2003/NĐ-CP dated April 4, 2003 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;
Based on the Notification No. 122/TB-VPCP dated June 24, 2004 of the Government Office regarding the assignment to the Ministry of Construction to study and issue the Architectural Construction Management Regulation for the area surrounding the National Convention Center;
At the proposal of the Director of the Architecture Planning Department and the Director of the Institute of Urban and Rural Planning,
DECISION:
Article 1. The attached Decision hereby promulgates the "Architectural Construction Management Regulation for the Area Surrounding the National Convention Center."
Article 2. This Decision takes effect fifteen days from the date of publication in the Official Gazette.
Article 3. The People's Committee of Hanoi City, the People's Committees of Tu Liem District, Cau Giay District, Thanh Xuan District, Me Tri Commune, construction investors in the area, relevant agencies, organizations, and individuals are responsible for implementing this Decision./.