Decision No. 33/2000/QD-BCN On Issuing the Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant

Decision No. 33/2000/QD-BCN of the Ministry of Industry on issuing the Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant, replacing the previous decision. This decision takes effect from the date of issuance.

文号33/2000/QĐ-BCN
文件类型Decision
发布机关Ministry of Industry and Trade
签署人Lê Quốc Khánh — Thứ trưởng
更新01/07/2026
行业Industry and Trade
领域Uncategorized
发布日期05/05/2000
生效日期05/05/2000
失效日期
状态In effect
✦ 智能摘要

Decision No. 33/2000/QD-BCN of the Ministry of Industry on issuing the Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant, replacing the previous decision. This decision takes effect from the date of issuance.

要点

  • Dau Niim Hydropower Plant → shall implement the Flood Release Procedure for Don Duong Reservoir according to the Flood Release Procedure DN99

🌐 本文件的社会影响

  • Positive impact: Enhance safety during flood release, reduce risk of loss due to natural disasters.
  • Negative impact: Requires time for training and implementing the new procedure for plant management staff.

❓ 常见问题

When was the Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant issued?

Decision No. 33/2000/QD-BCN of the Ministry of Industry issued this procedure on May 5, 2000.

Which procedure does the new Flood Release Procedure replace?

The Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant (QTxl-ĐN99) replaces Decision No. 607/NL-KHKT dated September 27, 1994 of the Ministry of Energy.

When does this decision take effect?

This decision takes effect from the date of issuance, which is May 5, 2000.

How should Dau Niim Hydropower Plant implement the Flood Release Procedure?

Dau Niim Hydropower Plant must implement the Flood Release Procedure for Don Duong Reservoir (QTxl-ĐN99) as issued with this decision.

全文

MINISTRY OF INDUSTRY

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 33/2000/QĐ-BCN
Hanoi, May 5, 2000

Pursuant to …;

Regarding the issuance of the Flood Release Procedure for the Don Duong Reservoir

Da Nhim Hydroelectric Power Plant

_________________

THE MINISTER OF INDUSTRY

 On the basis of Decree No. 74/CP of the Government dated November 1, 1995 on the functions, tasks, powers, and organizational structure of the Ministry of Industry;

In consideration of the proposal of Vietnam Electricity Corporation;

At the proposal of the Director of the Department of Technology Management and Product Quality;

Pursuant to …;

 Article 1. The Flood Release Procedure for the Don Duong Reservoir of the Da Nhim Hydroelectric Power Plant (QTxl-DN99) is hereby issued together with this Decision.

Article 2. This Decision takes effect from the date of signing and replaces Decision No. 607/NL-KHKT dated September 27, 1994 of the Ministry of Energy (previously) regarding the issuance of the Flood Release Procedure for the Don Duong Reservoir of the Da Nhim Hydroelectric Power Plant (QTxl-DN94).

Article 3. The Head of the Ministry's Office, Directors of the Departments of Technology Management and Product Quality, Planning and Investment, Legal Affairs, the Director of the Technical Safety Inspection Bureau, General Director of Vietnam Electricity Corporation, and the Director of the Da Nhim Hydroelectric Power Plant are responsible for implementing this Decision./.

 

DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Le Quoc Khanh
本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

关系图

33/2000/QĐ-BCN
Decision No. 33/2000/QD-BCN On Issuing the Flood Release Procedure for Don Duong Reservoir of Dau Niim Hydropower Plant
In effect
↓ 受本文件影响的文件
替代 1

点击文件即可打开。红色边框=改变效力的关系。