Decision No. 43/2005/QĐ-BXD on the issuance of TCXDVN 358: 2005 "Pile Driven by Drilling - Ultrasonic Pulse Method to Determine the Uniformity of Concrete"

Decision No. 43/2005/QĐ-BXD of the Minister of Construction on the issuance of the Vietnamese Construction Standard TCXDVN 358: 2005 on the method of using ultrasonic pulse to determine the uniformity of concrete in pile driven by drilling. The Decision shall take effect fifteen days from the date of publication in the Official Gazette.

Document No.43/2005/QĐ-BXD
Document typeDecision
Issuing authorityMinistry of Construction
Signed byNguyễn Văn Liên — Thứ trưởng
Updated29/06/2026
SectorConstruction
FieldUncategorized
Issued date30/11/2005
Effective date30/12/2005
Expiry date
StatusExpired
✦ Smart summary

Decision No. 43/2005/QĐ-BXD of the Minister of Construction on the issuance of the Vietnamese Construction Standard TCXDVN 358: 2005 on the method of using ultrasonic pulse to determine the uniformity of concrete in pile driven by drilling. The Decision shall take effect fifteen days from the date of publication in the Official Gazette.

Key points

  • The Vietnamese Construction Standard TCXDVN 358: 2005 is issued to specify the method of using ultrasonic pulse to determine the uniformity of concrete in pile driven by drilling.
  • The Decision shall take effect fifteen days from the date of publication in the Official Gazette.
  • The Director of the Ministry's Office, the Department Head of the Science and Technology Department, and the Heads of related units are responsible for implementing this Decision.

🌐 Social impact of this document

  • Positive impact: The new standard will help improve the quality of construction projects, ensuring the uniformity of concrete in pile driven by drilling.
  • Negative impact: Enterprises need to comply with the new regulations, which may encounter difficulties in terms of time and cost to implement.

❓ Frequently asked questions

To whom does the standard TCXDVN 358: 2005 apply?

This standard applies to construction projects using pile driven by drilling.

When does the Decision take effect?

The Decision shall take effect fifteen days from the date of publication in the Official Gazette.

What responsibilities do the related units have?

The Director of the Ministry's Office, the Department Head of the Science and Technology Department, and the Heads of related units are responsible for implementing this Decision.

What method does the standard TCXDVN 358: 2005 stipulate?

This standard stipulates the method of using ultrasonic pulse to determine the uniformity of concrete in pile driven by drilling.

When does the Decision take effect?

The Decision shall take effect fifteen days from the date of publication in the Official Gazette.

Full text

 

 

 

 

DECISION OF THE MINISTER OF CONSTRUCTION

Regarding the issuance of TCXDVN 358: 2005 "Pile Drilling - Ultrasonic Pulse Velocity Method for Determining Concrete Uniformity"

Issued along with this Decision is one Vietnamese Construction Standard:

THE MINISTER OF CONSTRUCTION

BASED ON THE GOVERNMENTAL DECREE NO. 36/2003/NĐ-CP OF APRIL 4, 2003, PROVIDING THE FUNCTIONS, TASKS, POWERS, AND ORGANIZATIONAL STRUCTURE OF THE MINISTRY OF CONSTRUCTION;

CONSIDERING THE PROPOSAL OF THE HEAD OF THE SCIENCE AND TECHNOLOGY DEPARTMENT;

DECISION:

Article 1. TCXDVN 358: 2005 "Pile Drilling - Ultrasonic Pulse Velocity Method for Determining Concrete Uniformity"

The Heads of the Ministry's Office, the Director of the Science and Technology Department, and the Heads of related units are responsible for implementing this Decision./.

Article 2. The Standard Measurement Quality Control Department shall be responsible for organizing and guiding the implementation of the Regulations adopted herein.

Article 3. The Heads of the Ministry's Office, the Director of the Science and Technology Department, and the Heads of relevant units shall be responsible for implementing this Decision./.

The original file of this document is being updated. Please read the full text and check back later.

Relations map

43/2005/QĐ-BXD
Decision No. 43/2005/QĐ-BXD on the issuance of TCXDVN 358: 2005 "Pile Driven by Drilling - Ultrasonic Pulse Method to Determine the Uniformity of Concrete"
Expired

Click a document to open. A red border = a relation that changes validity.