This Decision stipulates the implementation of construction projects that have been completed and those under construction, including conditions for recording capital, approving budgets, and procedures for new projects. It applies to Ministries, localities, and related organizations.
Scope of application
Ministries, central agencies, localities, and organizations related to construction projects.
Key points
- Construction projects completed in 1993-1994 do not need to reapprove the total budget but only record capital to pay for work already done, and be allocated capital according to approved item budgets.
- Ongoing projects expected to be completed in 1994-1995, if they have been under construction for many years, must reapprove the construction volume budget from 1994 until completion and must be reviewed for economic and technical justification (if exceeding budget).
- Large-scale special projects with a total investment of 100 billion VND or more must prepare economic and technical reports, design documents, and total budgets.
- Small projects (total investment under one billion VND) still need to approve construction installation budgets due to differences in foundations and material prices between locations.
- New projects initiated in 1994 must have complete economic and technical justification documents, design documents, and approved total budgets. If procedures are incomplete but urgent investment is necessary, a certain amount of capital can be registered for surveying, designing, and preparing total budgets for construction preparation.
- Important ongoing projects assigned plans according to Decision No. 62-TTg must ensure compliance with regulations. In cases where procedures cannot be supplemented in time but construction needs to continue in 1994, permission must be sought.
- Projects recorded in the 1994 plan of Ministries and localities up to July 30, 1994, if they have supplemented all procedures or submitted review documents to the State Appraisal Agency and the State Planning Commission, will be notified of final agreement on the plan in August 1994. Projects without completed procedures will not be included in the 1994 construction plan.
🌐 Social impact of this document
- Positive impact: Helps manage construction projects effectively, ensuring project progress and quality.
- Negative impact: May cause difficulties for organizations in complying with complex regulations regarding documentation and procedures.
❓ Frequently asked questions
What can be done with projects completed in 1993-1994?
These projects do not need to reapprove the total budget but only record capital to pay for work already done, and be allocated capital according to approved item budgets.
What must be done for large-scale special projects?
These projects must prepare economic and technical reports, design documents, and total budgets to serve construction purposes.
What requirements are there for small projects (total investment under one billion VND)?
These projects still need to approve construction installation budgets due to differences in foundations and material prices between locations.
What must be done for new projects initiated in 1994?
These projects must have complete economic and technical justification documents, design documents, and approved total budgets. If procedures are incomplete but urgent investment is necessary, a certain amount of capital can be registered for surveying, designing, and preparing total budgets for construction preparation.
What can be done with projects recorded in the 1994 plan of Ministries and localities up to July 30, 1994?
If all procedures or review documents have been supplemented and submitted to the State Appraisal Agency, the State Planning Commission will notify final agreement on the plan in August 1994. Projects without completed procedures will not be included in the 1994 construction plan.
Full text
|
PRIME MINISTER |
SOCIALIST REPUBLIC OF VIETNAM |
|
Number: 467-TTg |
Hanoi, August 29, 1994 |
Pursuant to …;
On certain specific provisions for implementation of Article 1 of Decision No. 92-TTg dated March 7, 1994
PRIME MINISTER
Pursuant to the Government Organization Law dated September 30, 1992;
At the proposal of the Minister, Chairman of the State Planning Committee, the Minister of Construction, and the Minister of Finance,
DECISION:
Article 1. Projects completed in 1993 and 1994 shall not be reviewed again for the total budget estimate but only recorded for payment of the volume of work already carried out, and shall be funded according to the approved unit project budget estimates, in accordance with the quantity consistent with the design, confirmed by the price certificate of the basic bank.
For ongoing projects that will be completed in 1994 and 1995, if construction has been extended over many years and started before 1992 but did not meet the conditions to prepare a total budget estimate, they shall only be reviewed for the construction cost estimate from 1994 until completion for management purposes and must be reviewed for economic and technical justification (if exceeding the budget as prescribed).
Article 2. For special large-scale projects (with a total investment of 100 billion VND, equivalent to 10 million USD or more) in certain sectors such as water resources, transportation, etc., which are under construction and have been underway for many years, the economic and technical justification already approved in stages according to investment targets (as stipulated in the economic and technical justification) shall serve as the basis for approving the design and budget estimate for construction, recording plans, and funding payments.
Small projects (with a total investment of less than one billion VND), although only requiring a brief economic and technical report, a concise explanation about the scale and requirements for approval of the policy, and the application of standard designs, still must be reviewed for the construction and installation budget estimate due to differences in foundation and construction material prices between locations.
Article 3. New projects initiated in 1994 must necessarily have complete economic and technical justification files, design files, and approved total budget estimates. If these projects have been allocated funds in the 1994 plan but have not yet met the above conditions, but there is an urgent need for investment, relevant ministries and localities may register some funds to conduct survey and design work and prepare the total budget estimate for construction to start in 1995.
Important ongoing projects of ministries and localities assigned plans according to Decision No. 62-TTg dated February 8, 1994, must still comply with the procedures as prescribed. In cases where necessary procedures have not been supplemented in time but urgent needs require continued construction in 1994, permission must be sought.
Article 4. For other projects registered in the 1994 plan of ministries and localities, by July 30, 1994, if they have supplemented all necessary procedures or submitted documentation to the state appraisal agency, the State Planning Committee will announce the final agreement on the plan in August 1994. Projects that have not completed their procedures are considered not included in the 1994 construction plan, and ministries and localities must continue to complete all procedures as the basis for recording the 1995 plan. These projects, if required, may be recorded for some funds for survey, design, and preparation of the total budget estimate for construction.
VICE-PRESIDENT OF THE GOVERNMENT