Decision No. 83/2002/QD-BNN approves the technical support project to prepare the World Bank loan disaster risk reduction project, managed by the Ministry of Agriculture and Rural Development. The project aims to prepare a pre-feasibility report, study the mechanism for using reserve funds, analyze social and environmental factors, assess policies related to disasters, and will be implemented within 12 months with a budget of 750,400 USD.
Đối tượng áp dụng
Ministry of Agriculture and Rural Development
Các điểm cốt lõi
- The Ministry of Agriculture and Rural Development will manage the technical support project to prepare the World Bank loan disaster risk reduction project.
- The project's tasks include preparing a pre-feasibility report, studying the mechanism for using reserve funds, analyzing social and environmental factors, and assessing policies related to disasters.
- The implementation budget is 750,400 USD from non-repayable aid from the Government of Japan through the World Bank.
- The project will be implemented over 12 months from the start date.
- The Steering Committee for the project preparation is chaired by a Deputy Minister of the Ministry of Agriculture and Rural Development, with members being representatives of relevant ministries and sectors.
🌐 Tác động xã hội từ văn bản này
- People in central provinces will be supported through the preparation of pre-feasibility reports for small disaster risk reduction projects.
- Enterprises can participate in the project preparation process by selecting consultants in accordance with regulations.
❓ Câu hỏi thường gặp
How long will this project be implemented?
The project will be implemented over 12 months from the start date.
What is the budget for the project?
The implementation budget for the project is 750,400 USD from non-repayable aid from the Government of Japan through the World Bank.
What purpose will this project serve?
The project aims to prepare the World Bank loan disaster risk reduction project, including preparing a pre-feasibility report, studying the mechanism for using reserve funds, analyzing social and environmental factors, and assessing policies related to disasters.
Who will chair the Steering Committee for the project preparation?
The Steering Committee for the project preparation is chaired by a Deputy Minister of the Ministry of Agriculture and Rural Development.
How will this project affect the people?
People in central provinces will be supported through the preparation of pre-feasibility reports for small disaster risk reduction projects, enhancing their ability to respond to disasters.
Toàn văn
Pursuant to …;
Approving the technical assistance project to prepare the disaster mitigation project for World Bank loan
borrowings from the World Bank
___________________________
THE MINISTER OF AGRICULTURE AND RURAL DEVELOPMENT
Pursuant to Decree No. 73-CP dated October 1, 1995 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Agriculture and Rural Development.
Pursuant to Decree No. 17/2001/NĐ-CP dated May 4, 2001 of the Government on the issuance of the Regulation on Management and Use of Official Development Assistance (ODA) Sources.
Pursuant to Document No. 2170/VPCP-QHQT dated April 25, 2002 and Document No. 5211/VPCP-QHQT dated September 19, 2002 of the Government Office notifying the Prime Minister's opinion assigning the Ministry of Agriculture and Rural Development to receive and implement the non-reimbursable technical assistance grant to prepare the Disaster Mitigation Project aimed at borrowing from the World Bank (WB).
DECISION:
Article 1. Approving the Technical Assistance Project to Prepare the Disaster Mitigation Project for World Bank Loan with the following contents:
1. Project Name: The Technical Assistance Project to Prepare the Disaster Mitigation Project for World Bank Loan.
2. Managing Authority: Ministry of Agriculture and Rural Development.
3. Type of Project: ODA Technical Assistance Project
4. Form of Investment: Non-reimbursable ODA.
5. Project Management Form: Steering Committee for Project Preparation and Project Preparation Board.
6. Project Implementation Area: The project will support the preparation of feasibility studies for sub-projects to be implemented in the first year in provinces most severely affected by disasters in Central Vietnam and may be expanded nationwide.
7. Project Office Location: Located at the Investment Preparation Board, Ministry of Agriculture and Rural Development.
8. Project Tasks: The project will assist the Ministry of Agriculture and Rural Development in preparing the Disaster Mitigation Project for World Bank Loan. The project includes the following activities:
- Preparing feasibility studies for sub-projects to be implemented in the first year.
- Studying and proposing mechanisms for using emergency recovery funds after disasters.
- Conducting social and environmental impact analyses, recommending small-scale disaster mitigation measures based on community involvement with local government support in disaster-affected communes.
- Evaluating relevant policies related to institutional and disaster response work of the Government to support policy development and institutional strengthening to enhance coordination efficiency in disaster prevention, control, and response among agencies and levels of the Government.
9. Implementation Budget:
The total budget for the project preparation phase is a non-reimbursable grant valued at 750,400 USD provided by the Japanese Government through the World Bank.
10. Implementation Period:
Completing the project preparation work within 12 months from the start date.
Article 2. Task Allocation and Organization of Implementation
1. A steering committee for project preparation shall be established, headed by a Deputy Minister of the Ministry of Agriculture and Rural Development, with members being representatives of relevant ministries and sectors involved in disaster prevention and mitigation. The steering committee is responsible for directing and supervising project preparation activities.
2. The secretariat for the steering committee for project preparation, located at the Investment Preparation Board, serves as the project preparation office.
3. The selection of consulting experts for project preparation shall be conducted in accordance with the World Bank's and the Government's procedures and regulations for consultant selection.
4. The implementation of agreements, commitments, and the selection of investment sub-projects in the project must comply with the construction procedures and regulations applicable to an ODA project.
Article 3. The Chairman of the Project Preparation Steering Committee, the Director of the International Cooperation Department, the Head of the Ministry's Office, and the Heads of relevant Departments and Bureaus under the Ministry are responsible for implementing this decision.
DEPUTY MINISTER
Bản đồ quan hệ