Decision No. 87/2000/QĐ-TTg on delegating the Ministry of Construction to approve adjustments to the overall and detailed planning of functional areas of the Vietnam Ethnic Village - Tourism Project

Decision No. 87/2000/QĐ-TTg delegates to the Minister of Construction the authority to approve adjustments to the overall and detailed planning of functional areas of the Vietnam Ethnic Village - Tourism Project, and at the same time requires coordination with relevant agencies to unify the adjustment plan for the entrance area ensuring a width of 400 meters.

Document No.87/2000/QĐ-TTg
Document typeDecision
Issuing authorityMinistry of Finance
Signed byPhan Văn Khải — Thủ tướng
Updated21/06/2026
FieldUncategorized
Issued date31/07/2000
Effective date31/07/2000
Expiry date
StatusIn effect
✦ Smart summary

Decision No. 87/2000/QĐ-TTg delegates to the Minister of Construction the authority to approve adjustments to the overall and detailed planning of functional areas of the Vietnam Ethnic Village - Tourism Project, and at the same time requires coordination with relevant agencies to unify the adjustment plan for the entrance area ensuring a width of 400 meters.

Scope of application

Ministry of Construction; Ministry of National Defense; Ministry of Culture and Information; Land Administration General Department; People's Committee of Ha Tay Province and other relevant agencies

Key points

  • The Minister of Construction is authorized to approve adjustments to the overall planning (Article 1)
  • The Ministry of Construction must coordinate with relevant agencies to unify the adjustment plan for the entrance area ensuring a width of 400 meters (Article 2)
  • This Decision takes effect from the date of signature (Article 3)
  • Ministries, ministerial-level agencies, and provincial People's Committees are responsible for implementing this Decision
  • The Ministry of Construction must consider approving the detailed planning of functional areas of the Vietnam Ethnic Village - Tourism Project (Article 1)

🌐 Social impact of this document

  • Development of infrastructure and planning for the Vietnam Ethnic Village - Tourism
  • Strengthen coordination among ministries and sectors in adjusting the planning
  • It may create a burden in terms of time and resources for the Ministry of Construction and relevant agencies

❓ Frequently asked questions

What authority does the Minister of Construction have?

Approving adjustments to the overall and detailed planning of functional areas of the Vietnam Ethnic Village - Tourism.

Which agencies must coordinate with the Ministry of Construction?

Ministry of National Defense, Ministry of Culture and Information, Land Administration General Department, People's Committee of Ha Tay Province and other relevant agencies.

What is the required width of the entrance to the Vietnam Ethnic Village - Tourism?

400 meters

Full text

PRIME MINISTER

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 87/2000/QĐ-TTg
Date: July 31, 2000

DECISION OF THE PRIME MINISTER

Regarding the delegation to the Ministry of Construction to approve the adjustment

 of the general planning and detailed planning for functional areas of the

 Vietnam Ethnic Cultural Village Tourism Project

 

PRIME MINISTER

Pursuant to the Government Organization Law dated September 30, 1992;

Pursuant to Decision No. 667/TTg dated August 21, 1997 of the Prime Minister on the construction of the Vietnam Ethnic Cultural Village Tourism;

Considering the proposal of the Minister of Culture and Information (in letter No. 2483/VHTT-LVH dated June 27, 2000) and the Minister of Planning and Investment (in letter No. 3343/BKH-VPTĐ dated June 2, 2000),

 

DECISION:

Article 1. The Prime Minister delegates the Minister of Construction to examine and approve the "adjustment of the general planning" and the "detailed planning for functional areas" of the Vietnam Ethnic Cultural Village Tourism Construction Project.

Article 2. The Ministry of Construction shall take the lead and coordinate with the Ministry of National Defense, the Ministry of Culture and Information, the General Department of Land Administration, the People's Committee of Ha Tay Province, and related agencies to unify the adjustment plan for the area of the entrance to the Vietnam Ethnic Cultural Village Tourism to ensure a width of 400 meters in accordance with the conclusion of the Prime Minister as stated in the Government Office's Notification No. 183/TB-VPCP dated September 21, 1999.

Article 3. This Decision shall take effect from the date of signing.

The Ministers of the Ministries, the Heads of ministerial-level agencies, the Heads of agencies under the Government, and the Chairpersons of the People's Committees of provinces and centrally governed cities directly under the central government which are concerned are responsible for implementing this Decision.

PRIME MINISTER
(Signed)
Phan Van Khai
The original file of this document is being updated. Please read the full text and check back later.

Download

The original file of this document is being updated. Please read the full text and check back later.

Relations map

↑ Basis & documents that affect this document
Based on 2
87/2000/QĐ-TTg
Decision No. 87/2000/QĐ-TTg on delegating the Ministry of Construction to approve adjustments to the overall and detailed planning of functional areas of the Vietnam Ethnic Village - Tourism Project
In effect
↓ Documents affected by this document
References 1

Click a document to open. A red border = a relation that changes validity.