Circular No. 02/2025/TT-BXD amends and supplements certain Articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, issued by the Minister of Construction regarding classification of construction projects and guidance on application in investment construction management activities.

Circular No. 02/2025/TT-BXD stipulates the classification of construction projects and guidance on application in investment construction management activities, amending certain provisions of Circular No. 06/2021/TT-BXD. This document applies to organizations and individuals related to investment construction activities.

문서 번호02/2025/TT-BXD
문서 유형Circular
발행 기관Ministry of Construction
서명자Phạm Minh Hà — Thứ trưởng
업데이트22. 06. 2026
분야Uncategorized
발행일31. 03. 2025
발효일20. 05. 2025
효력 만료일
상태In effect
✦ 스마트 요약

Circular No. 02/2025/TT-BXD stipulates the classification of construction projects and guidance on application in investment construction management activities, amending certain provisions of Circular No. 06/2021/TT-BXD. This document applies to organizations and individuals related to investment construction activities.

적용 범위

Organizations and individuals related to investment construction activities such as investors, contractors, design units, project management units, state administrative agencies for construction.

핵심 사항

  • The scope of regulation of this Circular provides detailed provisions on the classification of construction projects and guidance on applying the classification of construction projects in managing investment construction activities according to the Construction Law.
  • The classification level of independent structure construction projects is determined based on specific criteria set out in Appendix III attached hereto.
  • In cases where construction projects belong to phased investment projects, the corresponding criteria for the completed stage shall be used to determine the classification level of the construction project.
  • The determination and application of the classification level of certain types of construction projects are guided in Appendix III attached hereto.
  • This Circular takes effect from May 20, 2025, but projects that have been decided on investment before this date will continue to apply existing laws.

🌐 이 문서의 사회적 영향

  • Positive impact: Helps improve the effectiveness of construction management through clear project classification, making it easier for investors and contractors to identify responsibilities.
  • Negative impact: It may cause difficulties for projects approved before the effective date of this Circular if they need to adjust according to new regulations.

❓ 자주 묻는 질문

When does this Circular take effect?

This Circular takes effect from May 20, 2025.

How is the classification level of construction projects belonging to phased investment projects determined?

In cases where construction projects belong to phased investment projects, the corresponding criteria for the completed stage shall be used to determine the classification level of the construction project.

Does the adjustment of construction design affect the classification level of the project?

If the adjustment of construction design changes the level of importance, capacity, or structural scale, the classification level of the project shall be determined according to the provisions of Circular No. 06/2021/TT-BXD, which has been amended and supplemented.

What will happen to projects that have been decided on investment before the effective date of this Circular?

The classification level of construction projects under investment projects decided on investment before the effective date of this Circular shall be determined according to the law at the time of investment decision.

How is the determination of the classification level of the project guided?

The determination and application of the classification level of certain types of construction projects are guided in Appendix III attached hereto.

전문

MINISTRY OF CONSTRUCTION

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 02/2025/TT-BXD
Hanoi, March 31, 2025

CIRCULAR

Amending and supplementing certain articles of Circular No. 06/2021/TT-BXDdated June 30, 2021 of the Minister of Construction on classification of construction projects and guidance for application in management of investment construction activitiesCircular No. 06/2021/TT-BXD dated June 30, 2021 of the Minister of Construction on classification of construction projects and guidance for application in management of investment construction activities

_________________ 

Pursuant to the Law on Construction dated June 18, 2014; the Law Amending and Supplementing Certain Provisions of the Law on Construction dated June 17, 2020;

Pursuant to the Law on Architecture dated June 13, 2019;

Pursuant to the Government Decree No. 06/2021/NĐ-CP dated January 26, 2021 detailing certain provisions on quality management, construction works, and maintenance of construction projects;

Decree No. 175/2024/NĐ-CP December 30, 2024, of the Government detailing certain provisions and measures for the implementation of the Construction Law concerning construction activity management;

Pursuant to Decree No. 33/2025/NĐ-CP dated February 25, 2025 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;

At the proposal of the Director of the National Construction Quality Supervision Agency;

The Minister of Construction issues this Circular amending and supplementing some articles of Circular No. 06/2021/TT-BXD dated June 30, 2021 of the Minister of Construction on classification of construction projects and guidance for application in management of investment construction activities.

Article 1. Amending and supplementing some articles of Circular No. 06/2021/TT-BXD dated June 30, 2021 of the Minister of Construction on classification of construction projects and guidance for application in management of investment construction activities

1. Amending and supplementing Clause 1 of Article 1 as follows:

"1. Scope of Regulation This Circular provides detailed provisions on the classification of construction projects and guidance for applying project classification in managing investment construction activities as prescribed by the Construction Law; specifically, at Clause 4, Article 5 of the Construction Law 2014 amended and supplemented by Clause 3, Article 1 of the Law Amending and Supplementing Certain Provisions of the Construction Law 2020 and Clause 2, Article 3 of Decree No. 06/2021/NĐ-CP."

2. Adding Clauses 5, 6, 7 following Clause 4, Article 2 as follows:

"5. The classification level of independent structure construction projects newly invested in and not part of phased investment projects of existing construction projects shall be determined according to the provisions of Clauses 1, 2, and 3 of this Article.

6. In cases where the project belongs to a phased investment project, the criteria specified in Clause 1 of this Article corresponding to the completion stage shall be used to determine the project classification level.

7. The determination of the classification level of certain types of projects is guided in Appendix III attached to this Circular."

3. Adding Clauses 4, 5 following Clause 3, Article 3 as follows:

"4. In cases of phased investment projects, the project classification level specified in Clause 6, Article 2 of this Circular shall be applied in managing investment construction activities as prescribed in Clauses 1, 2, and 3 of this Article.

5. The application of the classification level of certain types of projects is guided in Appendix III attached to this Circular."

4. Amending and supplementing some contents of Appendices I, II, III in the Appendices attached to this Circular.

Article 2. Implementation clause

1. This Circular takes effect from May 20, 2025.

2. The classification level of projects under investment construction projects decided on before the date this Circular takes effect shall be determined according to the legal provisions at the time of decision on investment.

3. In cases where projects or construction projects have been submitted to specialized construction management agencies for review or adjustment of feasibility study reports for investment construction, design documents implemented after basic design before the date this Circular takes effect and meet the conditions for review, the determination of the classification level and application of the classification level in managing investment construction activities shall be determined according to the legal provisions at the time of submission for review.

4. In cases where there is a change in the construction design from the date this Circular takes effect:

a) If the change in the construction design does not alter the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the legal provisions at the time of investment decision;

b) If the change in the construction design alters the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the provisions of Circular No. 06/2021/TT-BXD amended and supplemented by this Circular./.

DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Pham Minh Ha

원본 문서(PDF)

새 탭에서 PDF 열기 ↗

관계도

↑ 근거 및 이 문서에 영향을 주는 문서
근거 16
62/2020/QH14 Luật sửa đổi, bổ sung một số điều của Luật Xây dựng số 62/2020/QH14 발효 중 33/2025/NĐ-CP Nghị định số 33/2025/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Xây dựng 발효 중 40/2019/QH14 Luật Kiến trúc số 40/2019/QH14 발효 중 06/2021/NĐ-CP Nghị định số 06/2021/NĐ-CP Quy định chi tiết một số nội dung về quản lý chất lượng, thi công xây dựng và bảo trì công trình xây dựng 발효 중 175/2024/NĐ-CP Nghị định số 175/2024/NĐ-CP Quy định chi tiết một số điều và biện pháp thi hành Luật Xây dựng về quản lý hoạt động xây dựng 발효 중 50/2014/QH13 Luật Xây dựng số 50/2014/QH13 발효 중 312/2025/QĐ-UBND Quyết định số 312/2025/QĐ-UBND Ban hành Quy định phân cấp trách nhiệm quản lý nhà nước về chất lượng, thi công xây dựng và bảo trì công trình xây dựng trên địa bàn tỉnh Vĩnh Long 발효 중 050/2025/QĐ-UBND Quyết định số 050/2025/QĐ-UBND Ban hành Quy định về thẩm quyền trong quản lý dự án đầu tư xây dựng trên địa bàn tỉnh Đắk Lắk 발효 중 29/2025/QĐ-UBND Quyết định số 29/2025/QĐ-UBND Về phân cấp thẩm quyền cấp giấy phép xây dựng; Quy định về quy mô, thời hạn tồn tại của công trình được cấp giấy phép xây dựng có thời hạn trên địa bàn Thành phố Hồ Chí Minh 발효 중 09/2026/QĐ-UBND Quyết định số 09/2026/QĐ-UBND Phân cấp thẩm quyền cấp phép xây dựng trên địa bàn thành phố Đà Nẵng 발효 중 '39/2025/QĐ-UBND Quyết định số '39/2025/QĐ-UBND Phân cấp một số nội dung về quản lý hoạt động xây dựng trên địa bàn tỉnh Lâm Đồng 발효 중 91/2025/QĐ-UBND Quyết định số 91/2025/QĐ-UBND Ban hành Quy định về phân cấp cấp giấy phép xây dựng và quản lý trật tự xây dựng trên địa bàn tỉnh Lai Châu 발효 중 45/2026/QĐ-UBND Quyết định số 45/2026/QĐ-UBND Ban hành Quy chế quản lý hoạt động quảng cáo ngoài trời trên địa bàn tỉnh Hà Tĩnh 발효 중 100/2026/QĐ-UBND Quyết định số 100/2026/QĐ-UBND Quy định một số nội dung liên quan đến việc cấp giấy phép xây dựng có thời hạn trên địa bàn thành phố Đà Nẵng 발효 중 87/2026/QĐ-UBND Quyết định số 87/2026/QĐ-UBND Ban hành quy định quản lý nghĩa trang và cơ sở hỏa táng trên địa bàn tỉnh Tây Ninh 발효 중 52/2026/QĐ-UBND Quyết định số 52/2026/QĐ-UBND Ban hành Quy chế Đặt tên, đổi tên đường, phố và công trình công cộng trên địa bàn thành phố Huế 발효 중
02/2025/TT-BXD
Circular No. 02/2025/TT-BXD amends and supplements certain Articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, issued by the Minister of Construction regarding classification of construction projects and guidance on application in investment construction management activities.
In effect
↓ 이 문서의 영향을 받는 문서
관련 5
91/2025/QĐ-UBND Quyết định số 91/2025/QĐ-UBND Ban hành Bảng giá tính thuế tài nguyên năm 2026 đối với nhóm, loại tài nguyên có tính chất lý, hóa giống nhau trên địa bàn tỉnh Lạng Sơn 발효 중 39/2025/QĐ-UBND Quyết định số 39/2025/QĐ-UBND Ban hành Bảng giá tính thuế tài nguyên năm 2026 trên địa bàn tỉnh Lào Cai 발효 중

문서를 클릭하면 열립니다. 빨간 테두리=효력을 변경하는 관계.