Circular No. 05/2009/TT-BXD on guiding the adjustment of construction project budgets

Circular No. 05/2009/TT-BXD guides the adjustment of construction project budgets from January 1, 2009, based on the minimum regional wage levels stipulated in Decree No. 110/2008/NĐ-CP. This Circular applies to construction projects funded by state capital that are ongoing, and encourages its application to other sources of funding.

文号05/2009/TT-BXD
文件类型Circular
发布机关Ministry of Construction
签署人Cao Lại Quang — Thứ trưởng
更新27/06/2026
行业Construction
领域Uncategorized
发布日期15/04/2009
生效日期30/05/2009
失效日期15/08/2021
状态Expired
✦ 智能摘要

Circular No. 05/2009/TT-BXD guides the adjustment of construction project budgets from January 1, 2009, based on the minimum regional wage levels stipulated in Decree No. 110/2008/NĐ-CP. This Circular applies to construction projects funded by state capital that are ongoing, and encourages its application to other sources of funding.

适用范围

Construction projects funded by state capital that are ongoing; construction projects funded by other sources of capital (if applicable).

要点

  • For construction project budgets prepared according to local construction unit prices, labor costs and construction machinery costs shall be adjusted according to the KDCNC and KDCTMC factors.
  • Labor costs in construction survey budgets shall be adjusted according to the KDCNCKS factor.
  • The minimum regional wage levels stipulated in Decree No. 110/2008/NĐ-CP serve as the basis for determining the adjustment factors.
  • Adjustment factors for labor costs, construction machinery costs, and material testing costs are issued in the annex accompanying this Circular.
  • The project sponsor is responsible for approving the results of the adjustment of the construction project budget.

🌐 本文件的社会影响

  • Positive impact: Reducing labor and construction machinery costs for projects, helping to save state funds.
  • Negative impact: It may cause difficulties in adjusting project budgets for contracts signed prior to this regulation.

❓ 常见问题

How are the adjustment factors for labor costs and construction machinery costs determined?

The adjustment factor (KDCNC) for labor costs and KDCTMC for construction machinery costs are determined by dividing the new minimum regional wage level by the wage level already included in the unit price. Specific tables of these factors are issued along with this Circular.

Are construction projects funded by other sources of capital subject to this regulation?

It is encouraged that construction projects funded by other sources of capital apply the regulations for adjusting construction project budgets as guided by this Circular.

What should be done when implementing the adjustment of the construction project budget according to the new minimum regional wage level if the budget has been previously adjusted?

Labor and construction machinery costs in the construction cost budget, and labor costs in the construction survey cost budget, shall be further multiplied by the corresponding adjustment factor determined by dividing the new adjustment factor according to the new minimum regional wage level by the adjustment factor used for the previous adjustment under Circular No. 03/2008/TT-BXD.

How are other cost items in the construction project budget calculated?

Cost items for Project Management, Design, Construction Supervision, and Installation of Equipment are calculated as percentages according to current national regulations.

When does this Circular take effect?

This Circular takes effect 45 days from the date of issuance./.

全文

MINISTRY OF CONSTRUCTION

SOCIALIST REPUBLIC OF VIET NAM

Independence - Freedom - Happiness

Number: 05/2009/TT-BXD Hanoi, April 15, 2009

CIRCULAR

Guidelines for Adjusting Construction Project Budget Estimates

Pursuant to Decree No. 17/2008/NĐ-CP dated February 4, 2008 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;

Pursuant to Decree No. 12/2009/NĐ-CP dated February 12, 2009 of the Government on Management of Investment Construction Projects;

Pursuant to Decree No. 99/2007/NĐ-CP dated June 13, 2007 of the Government on Management of Investment Construction Costs; and Decree No. 03/2008/NĐ-CP dated January 7, 2008 of the Government amending and supplementing certain articles of Decree No. 99/2007/NĐ-CP dated June 13, 2007 on Management of Investment Construction Costs (hereinafter referred to as Decree No. 99/2007/NĐ-CP dated June 13, 2007 of the Government);

CPursuant to Decree No. 110/2008/NĐ-CP dated October 10, 2008 of the Government stipulating the minimum wage levels for workers employed by companies, enterprises, cooperatives, production cooperatives, farms, households, individuals, and other organizations in Vietnam that hire labor (hereinafter referred to as Decree No. 110/2008/NĐ-CP dated October 10, 2008 of the Government);

Pursuant to Circular No. 03/2008/TT-BXD dated January 25, 2008 of the Ministry of Construction guiding the adjustment of construction project budget estimates (hereinafter referred to as Circular No. 03/2008/TT-BXD dated January 25, 2008 of the Ministry of Construction);

Pursuant to Circular No. 23/2008/TT-BLĐTBXH dated October 20, 2008 of the Ministry of Labor, Invalids and Social Affairs promulgating guidelines for implementing minimum wage levels for state-owned companies and limited liability companies wholly owned by the State.

The Ministry of Construction hereby guides the adjustment of construction project budget estimates as follows:

This technical regulation sets out technical requirements, testing methods, sampling procedures; management requirements; responsibilities of organizations and individuals producing, trading, and importing cigarettes.

1. This Circular guides the adjustment of budget estimates from January 1, 2009 according to the minimum wage level in the region (where the construction project is located) as prescribed in Decree No. 110/2008/NĐ-CP dated October 10, 2008 of the Government for the remaining quantities of the construction project, tender package (hereinafter collectively referred to as construction project budget estimate) belonging to investment construction projects using state capital that are still ongoing but have not yet been decided by the Investor to continue managing investment construction costs under Decree No. 99/2007/NĐ-CP dated June 13, 2007 of the Government.

It is encouraged for investment construction projects using other sources of funds to apply the regulations on adjusting construction project budget estimates as guided in this Circular.

2. Adjust the construction project budget estimate that has been prepared based on unit prices for building works, installation works, and construction survey works of provinces and centrally administered cities calculated according to the salary scale A.1.8 issued together with Decree No. 205/2004/NĐ-CP dated December 14, 2004 of the Government stipulating the salary scale system, salary table, and allowance system in state-owned companies (hereinafter referred to as Decree No. 205/2004/NĐ-CP dated December 14, 2004 of the Government) and the minimum monthly wage of VND 450,000 as specified in the annex attached to this Circular.

3. For construction projects that have established separate unit prices or machinery cost tables with the minimum wage level already approved by the competent authority, adjust according to the principles and methods provided in this Circular based on the new minimum wage level.

4. Adjust contract prices and settle actual work volumes from January 1, 2009 according to the contract and the agreed conditions signed in the contract. In cases where the parties have agreed in the contract not to adjust prices throughout the implementation period, the Investor and the construction contractor may negotiate supplementary contracts to ensure the rights of workers as prescribed.

II. SPECIFIC PROVISIONS

1. For construction project budget estimates prepared based on construction unit price lists of provinces and centrally administered cities calculated with the minimum wage of VND 450,000/month as stipulated in Decree No. 94/2006/NĐ-CP dated September 7, 2006 of the Government on adjusting the general minimum wage, with salary grades according to the salary table A.1.8 issued together with Decree No. 205/2004/NĐ-CP dated December 14, 2004 of the Government, shall be adjusted as follows:

1.1. Adjustment of construction cost estimates

1.1.1. Adjustment of labor costs

Labor costs in construction cost estimates prepared based on local construction unit prices shall be multiplied by the appropriate adjustment factor (KĐCNC) corresponding to the new minimum wage level.

The adjustment factor (KĐCNC) is determined by dividing the new minimum wage level by the minimum wage level included in the unit price.

1.1.2. Adjustment of construction machinery costs

Construction machinery costs in construction cost estimates prepared based on local construction unit prices shall be multiplied by the appropriate adjustment factor (KĐC MTC) corresponding to the new minimum wage level and fuel, energy prices at the time of January 2009.

The adjustment factor for construction machinery costs (KĐCMTC) is determined by the weighted average method of costs by machinery group.

According to the above principle, the adjustment factor for construction machinery costs in construction cost estimates (KĐCMTC) of provinces and centrally administered cities is guided in the annex attached to this Circular. Provinces and centrally administered cities with special construction structures will be decided by the People's Committee of the province or city.

For construction projects implemented along routes through multiple provinces and centrally administered cities that have established separate machinery cost tables, the Investor shall calculate the adjustment factor and report it to the Investor for decision. In cases where the construction project belongs to an investment construction project decided by the Prime Minister, the Minister, Head of a ministry equivalent to a ministry, Head of a government agency, Chairman of the provincial People's Committee, Chairman of the economic group, or Chairman of the State-owned enterprise management council shall decide.

1.1.3. Cost items calculated as percentages in construction cost estimates.

Cost items calculated as percentages in construction cost estimates include: Other direct costs, common costs, pre-tax income, value-added tax, temporary housing at the construction site for living and construction management, which shall be implemented according to the regulations.

1.2. Adjustment of construction survey cost estimates.

The labor costs in the construction survey estimate (KDC NCKS) shall be adjusted according to the coefficients set out in the annex accompanying this Circular.

2. In cases where the construction project estimate prepared in accordance with point 1 of this section has been adjusted in accordance with the guidance of Circular No. 03/2008/TT-BXD dated January 25, 2008 of the Ministry of Construction, when implementing adjustments to the estimate based on the new minimum wage level, the labor costs and construction machinery costs in the construction cost estimate, and the labor costs in the construction survey estimate shall be further multiplied by the corresponding adjustment factor determined by dividing the adjustment factor according to the new minimum wage level specified in the annex accompanying this Circular by the adjustment factor already applied pursuant to Circular No. 03/2008/TT-BXD dated January 25, 2008 of the Ministry of Construction.

3. Other items of cost in the construction project estimate

The items of cost for project management investment in construction projects, design of construction projects, supervision of construction works and installation of equipment as stipulated in point 1 of Section I above shall be calculated as percentages in accordance with the prescribed regulations.

III. IMPLEMENTATION

1. The investor shall organize the implementation and approval of the results of adjusting the construction project estimate for remaining quantities carried out from January 1, 2009 of construction projects under construction investment projects as provided for in point 1 of Section I of this Circular. If the approved construction project estimate exceeds the total investment ceiling, the Investor shall report to the Investment Decision Maker for examination and decision. In cases where construction projects under construction investment projects are decided upon by the Prime Minister, the Minister, the Head of a ministry equivalent to a ministry, the Head of a government agency, the Chairman of the Provincial People's Committee, the Chairman of the Economic Group, and the Chairman of the State Capital Corporation shall make the decision.

2. For construction projects that have separate unit prices (unit price of construction projects), the Investor shall base on the system and policies permitted by the State to apply at the project and the principles for adjusting the construction project cost estimate as guided by this Circular, to determine the adjustment levels for labor costs, construction machinery costs, and other costs (if any) in the construction project estimate.

3. The adjustment of the construction project estimate for construction projects under construction investment projects shall be implemented in accordance with Decree No. 99/2007/NĐ-CP dated June 13, 2007 of the Government on Management of Construction Project Investment Costs, as decided by the Investor.

This Circular takes effect 45 days from the date of signature./.

Place of Receipt:
- Central Party Committee Secretariat;
- Standing Committee of the National Assembly;
- Prime Minister, Deputy Prime Ministers;
- Central Office and various Party Committees;
- Government Office ;
- National Assembly's Office;
- National Assembly's Ethnic Council and Committees;
- President's Office;
- Ministries, agencies equivalent to ministries, and government agencies;
- Provincial People's Councils, Provincial People's Committees;
- Supreme People's Procuracy;
- Supreme People's Court;
- Central agencies of mass organizations;
- Construction Departments of provinces, centrally governed cities;
- State Economic Groups, State Corporations;
- Official Gazette;
- Government Portal, Ministry of Construction Portal;
- Departments and Bureaus under the Ministry of Construction;
- To be filed: Office, Planning and Finance Bureau, Construction Supervision Bureau, Construction Research Institute (VI350).

DEPUTY MINISTER
DEPUTY MINISTER




Cao Lại Quang

 

ANNEX

(Issued together with Circular No. 05/2009/TT-BXD dated April 15, 2009 of the Ministry of Construction)

Adjusting the estimates of remaining quantities carried out from January 1, 2009 of construction projects under construction investment projects as stipulated in point 1 of Section I of this Circular.

1. Adjustment of construction cost estimates

1.1. Adjustment of labor costs, construction machinery costs

Labor costs and construction machinery costs in the construction cost estimate shall be multiplied by the adjustment factors (KĐCNC) and (KĐC MTC) specified in Table 1 of the annex to this Circular.

1.2. Items of cost calculated as percentage rates in the construction cost estimate.

Direct fees, common costs, pre-tax income, value-added tax, and construction costs for temporary housing at the site for living and construction management shall be calculated as percentage rates in accordance with the prescribed regulations.

2. Adjustment of construction survey cost estimates

Labor costs in the construction survey estimate shall be multiplied by the adjustment factor (KĐC NCKS) specified in Table 2 of the annex to this Circular.

3. Adjustment of cost estimates for material and component testing

Labor costs in the material and component testing estimate shall be determined according to the testing standards and unit prices for materials and components issued together with Decision No. 32/2001/QĐ-BXD dated December 20, 2001 of the Minister of Construction and shall be multiplied by the adjustment factor (KĐCNCTN) specified in Table 3 of the annex to this Circular.

4. Some items of cost calculated as percentage rates in the construction project estimate shall be calculated in accordance with current national regulations.

Table 1: ADJUSTMENT FACTORS FOR CONSTRUCTION COST ESTIMATES

Minimum wage level

 

Adjustment factor

Region I

Region II

Region III

Region IV

800,000 VND/month

740,000 VND/month

690,000 VND/month

650,000 VND/month

Labor costs KĐCNC

1,78

1,64

1,53

1,44

Construction machinery costs KĐCMTC

1,20

1,18

1,16

1,14

Table 2: ADJUSTMENT FACTORS FOR CONSTRUCTION SURVEY COST ESTIMATES

Minimum wage level

 

Adjustment factor

Region I

Region II

Region III

Region IV

800,000 VND/month

740,000 VND/month

690,000 VND/month

650,000 VND/month

Labor costs KĐCNCKS

1,78

1,64

1,53

1,44

Table 3: ADJUSTMENT FACTORS FOR MATERIAL AND COMPONENT TESTING COST ESTIMATES

Minimum wage level

 

Adjustment factor

Region I

Region II

Region III

Region IV

800,000 VND/month

740,000 VND/month

690,000 VND/month

650,000 VND/month

Labor costs KĐCNCTN

4,20

3,88

3,62

3,41

 

REGULATIONS ON THE LIST OF AREAS APPLYING MINIMUM WAGE LEVELS BY REGION

Region

Area

I

- Districts within Hanoi City;

- Districts within Ho Chi Minh City;

II

- Counties of Gia Lam, Dong Anh, Soc Son, Thanh Tri, Tu Liem, Thanh Xuan, Hoai Duc, Dan Phuong, Thach That, Quoc Oai, and My Duc Town within Hanoi City;

- Counties within Ho Chi Minh City;

- Districts and counties of Thuy Nguyen, An Duong within Hai Phong City;

- The districts under the city of Da Nang;

- Districts of Ninh Kieu, Binh Thuy within Can Tho City;

- Ha Long city in Quang Ninh province;

- Bien Hoa City, Long Khanh Town, and counties of Nhon Trach, Long Thanh, Vinh Cuu, Trang Bom within Dong Nai Province;

- Thu Dau Mot Town, Thu An County, Di An County, Ben Cat County, Tan Uyen County within Binh Duong Province;

- Vung Tau City and Tan Thanh County within Ba Ria-Vung Tau Province.

III

- Cities directly under provinces (excluding cities under provinces listed in Region II);

- Remaining counties in Hanoi city;

- Bac Ninh City, Tu Son Town, and counties of Quet Vo, Tien Du, Yen Phong within Bac Ninh Province;

- Bac Giang City and counties of Viet Yen, Yen Dong within Bac Giang Province;

- City Hung Yen and districts My Hao, Van Lan, Van Giang, Yen My in Hung Yen Province;

- Hai Duong City and counties of Cam Giang, Nam Sach, Chi Linh, Kim Thanh, Kim Mon within Hai Duong Province;

- Vinh Yen City, Phuc Yen Town within Vinh Phuc Province;

- Remaining counties in Hai Phong city;

- Mong Cai City, Uong Bi Town, Cam Pha Town within Quang Ninh Province;

- City of Da Lat and Bac Loc Town in Lam Dong Province;

- City of Nha Trang and Cam Ranh Town in Khanh Hoa Province;

- Trang Bang District in Tay Ninh Province;

- The remaining districts in Binh Duong Province;

- The remaining districts in the province of Dong Nai;

- Tan An Town and Duc Hoa, Ben Luc, Can Duoc Districts in Long An Province;

- The remaining districts and towns in Can Tho City;

- Ba Ria Town and Chu Doc, Long Dien, Dat Do, Xuan Moi Districts in Ba Ria-Vung Tau Province;

IV

- Comprising the remaining areas

 

本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

下载

本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

关系图

↑ 依据及影响本文件的文件
依据 23
99/2007/NĐ-CP Nghị định số 99/2007/NĐ-CP Về quản lý chi phí đầu tư xây dựng công trình 已失效 03/2008/TT-BXD Thông tư số 03/2008/TT-BXD Hướng dẫn điều chỉnh dự toán xây dựng công trình 已失效 110/2008/NĐ-CP Nghị định số 110/2008/NĐ-CP Quy định mức lương tối thiểu vùng đối với người lao động làm việc ở công ty, doanh nghiệp, hợp tác xã, tổ hợp tác, trang trại, hộ gia đình, cá nhân và các tổ chức khác của Việt Nam có thuê mướn lao động 已失效 23/2008/TT-BLĐTBXH Thông tư số 23/2008/TT-BLĐTBXH Hướng dẫn thực hiện mức lương tối thiểu vùng đối với công ty nhà nước và công ty trách nhiệm hữu hạn một thành viên do Nhà nước sở hữu 100% vốn điều lệ 已失效 12/2009/NĐ-CP Nghị định số 12/2009/NĐ-CP Về quản lý dự án đầu tư xây dựng công trình 已失效 03/2008/NĐ-CP Nghị định số 03/2008/NĐ-CP Về sửa đổi, bổ sung một số điều của Nghị định số 99/2007/NĐ-CP ngày 13 tháng 06 năm 2007 của Chính phủ về quản lý chi phí đầu tư xây dựng công trình 已失效 17/2008/NĐ-CP Nghị định số 17/2008/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Xây dựng 已失效 272/2009/QĐ-UBND Quyết định số 272/2009/QĐ-UBND Về việc áp dụng hệ số điều chỉnh chi phí xây dựng công trình trên địa bàn tỉnh Ninh Thuận theo Thông tư số 05/2009/TT-BXD ngày 15 tháng 4 năm 2009 của Bộ Xây dựng 已失效 1261/2010/QĐ-UBND Quyết định số 1261/2010/QĐ-UBND Về việc điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Ninh Thuận 已失效 57/2009/QĐ-UBND Quyết định số 57/2009/QĐ-UBND Về việc hướng dẫn điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Bà Rịa - Vũng Tàu theo Thông tư số 05/2009/TT-BXD ngày 15 tháng 4 năm 2009 của Bộ Xây dựng 已失效 20/2009/QĐ-UBND Quyết định số 20/2009/QĐ-UBND Về việc ban hành hệ số điều chỉnh dự toán xây dựng công trình do tăng mức lương tối thiểu vùng trên địa bàn tỉnh Thái Nguyên 已失效 01/2013/QĐ-HĐND Quyết định số 01/2013/QĐ-HĐND Về việc điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Ninh Thuận 生效中 65/2011/QĐ-UBND Quyết định số 65/2011/QĐ-UBND Về việc điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Ninh Thuận 已失效 167/2009/QĐ-UBND Quyết định số 167/2009/QĐ-UBND Về việc áp dụng hệ số điều chỉnh chi phí xây dựng công trình trên địa bàn tỉnh Ninh Thuận theo Thông tư số 05/2009/TT-BXD ngày 15 tháng 4 năm 2009 của Bộ Xây dựng 已失效 157/QĐ-UBND QUYẾT ĐỊNH SỐ 157/QĐ-UBND VỀ VIỆC ĐIỀU CHỈNH DỰ TOÁN XÂY DỰNG CÔNG TRÌNH TRÊN ĐỊA BÀN TỈNH NINH THUẬN 已失效 1261/2010/QĐ-UBND Quyết định số 1261/2010/QĐ-UBND Về việc điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Ninh Thuận 已失效 01/2013/QĐ-UBND Quyết định số 01/2013/QĐ-UBND Về việc điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Ninh Thuận 生效中 37/2010/QĐ-UBND Quyết định số 37/2010/QĐ-UBND Về việc hướng dẫn điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Bà Rịa - Vũng Tàu theo mức lương tối thiểu từ 01/01/2010 已失效 48/2011/QĐ-UBND Quyết định số 48/2011/QĐ-UBND Về việc Ban hành hệ số điều chỉnh dự toán xây dựng công trình do tăng mức lương tối thiểu vùng trên địa bàn tỉnh Thái Nguyên 已失效 14/2011/QĐ-UBND Quyết định số 14/2011/QĐ-UBND Về việc ban hành Hệ số điều chỉnh dự toán xây dựng công trình do tăng mức lương tối thiểu vùng trên địa bàn tỉnh Thái Nguyên 已失效 67/2009/QĐ-UBND Quyết định số 67/2009/QĐ-UBND Ban hành quy định về điều chỉnh dự toán xây dựng công trình áp dụng theo Thông tư số 05/2009/TT-BXD, ngày 15 tháng 4 năm 2009 của Bộ Xây dựng trên địa bàn thành phố Hồ Chí Minh. 生效中 31/2009/QĐ-UBND Quyết định số 31/2009/QĐ-UBND Ban hành Quy định về giá nhà xây dựng mới trên địa bàn tỉnh Đắk Lắk 已失效 18/2009/QĐ-UBND Quyết định số 18/2009/QĐ-UBND Ban hành quy định điều chỉnh dự toán xây dựng công trình trên địa bàn tỉnh Bình Phước 已失效
05/2009/TT-BXD
Circular No. 05/2009/TT-BXD on guiding the adjustment of construction project budgets
Expired
↓ 受本文件影响的文件
相关 8
157/QĐ-UBND Quyết định số 157/QĐ-UBND Về việc quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Chi cục Chăn nuôi và Thú y trực thuộc Sở Nông nghiệp và Môi trường thành phố Huế 生效中 37/2010/QĐ-UBND Quyết định số 37/2010/QĐ-UBND về việc ban hành bảng giá cho thuê nhà ở thuộc sở hữu nhà nước chưa được cải tạo, xây dựng lại: nhà A2, A3, A5, A6, B1, B2, B3, B4, B5, B6, C2, C3, C4, C5, C6, C7 khu chung cư Quang Trung, TP Vinh 已失效 01/2013/QĐ-UBND Quyết định số 01/2013/QĐ-UBND Về bãi bỏ văn bản. 生效中 17/2010/QĐ-UBND Quyết định số 17/2010/ QĐ-UBND Ban hành Quy định quản lý trật tự đô thị trên địa bàn thành phố Bắc Giang 已失效 31/2009/QĐ-UBND Quyết định số 31/2009/QĐ-UBND Về việc ban hành Quy định về quản lý nhà nước trong lĩnh vực thuốc bảo vệ thực vật trên địa bàn tỉnh An Giang 已失效 48/2011/QĐ-UBND Quyết định số 48/2011/QĐ-UBND Phê duyệt Đề án điều chỉnh mức thu học phí công lập từ mầm non đến trung học phổ thông trên địa bàn tỉnh Bình Định 已失效 14/2011/QĐ-UBND Quyết định số 14/2011/QĐ-UBND Về việc phê duyệt đề án kiện toàn tổ chức, biên chế cơ quan tư pháp cấp huyện và cấp xã trên địa bàn tỉnh Bà Rịa - Vũng Tàu 已失效 67/2009/QĐ-UBND Quyết định số 67/2009/QĐ-UBND Về việc ban hành chính sách hỗ trợ đào tạo bác sĩ, dược sĩ đại học cho ngành Y tế tỉnh Bà Rịa - Vũng Tàu từ nay đến năm 2020 已失效

点击文件即可打开。红色边框=改变效力的关系。