Circular No. 08/2006/TT-BLDTBXH guiding the wage system and allowances for workers, staff, and officials directly involved in constructing the Dong Nai 4 Hydropower Project.

Circular No. 08/2006/TT-BLDTBXH guides the wage system and allowances for workers, staff, and officials directly involved in constructing the Dong Nai 4 Hydropower Project in Lam Dong and Dak Nong provinces. The document applies the minimum wage from 2005, stipulates various types of allowances such as regional, attraction, mobility, and midday meal benefits, and determines the funding sources and responsibilities of the relevant parties.

Document No.08/2006/TT-BLĐTBXH
Document typeCircular
Issuing authorityMinistry of Home Affairs
Signed byLê Duy Đồng — Thứ trưởng
Updated29/06/2026
SectorLabour, War Invalids and Social Affairs
FieldUncategorized
Issued date27/07/2006
Effective date05/09/2006
Expiry date
StatusIn effect
✦ Smart summary

Circular No. 08/2006/TT-BLDTBXH guides the wage system and allowances for workers, staff, and officials directly involved in constructing the Dong Nai 4 Hydropower Project in Lam Dong and Dak Nong provinces. The document applies the minimum wage from 2005, stipulates various types of allowances such as regional, attraction, mobility, and midday meal benefits, and determines the funding sources and responsibilities of the relevant parties.

Scope of application

Workers, staff, and officials directly participating in the construction of the Dong Nai 4 Hydropower Project in Lam Dong and Dak Nong provinces; the project management board; consultants and designers working at the site; technical surveyors.

Key points

  • Workers, staff, and officials directly participating in the construction are subject to a minimum wage of VND 290,000 per month before October 1, 2005, increasing to VND 350,000 per month from October 1, 2005.
  • Regional, attraction, and mobility allowances are applied at specific rates: 30% of the job grade salary, and 0.4 times the general minimum wage.
  • The midday meal allowance is VND 5,000 per person per day, effective from July 12, 2006.
  • The costs for implementing these benefits are included in the project budget and are the responsibility of Vietnam Electricity Corporation (the project sponsor).
  • This circular takes effect 15 days after its publication in the Official Gazette and applies from the start of construction until the completion of the project.

🌐 Social impact of this document

  • Positive impact: Ensuring wage and allowance rights for workers, improving project quality.
  • Negative impact: Increased costs may affect the project budget.

❓ Frequently asked questions

When does the minimum wage apply?

The minimum wage before October 1, 2005 was VND 290,000 per month, and from October 1, 2005 onwards it is VND 350,000 per month.

How is the attraction allowance calculated?

The attraction allowance is calculated at 30% of the job grade salary.

What is the midday meal allowance per person per day?

VND 5,000 per person per day, effective from July 12, 2006.

Who is responsible for the funding of these benefits?

Vietnam Electricity Corporation (the project sponsor) is responsible.

When does this circular take effect?

This circular takes effect 15 days after its publication in the Official Gazette and applies from the start of construction until the completion of the project.

Full text

CIRCULAR

Guidelines for implementing wage and salary allowances for workers, employees, and officials constructing the Dong Nai 4 Hydropower Project

|||

____________________________

 

Pursuant to Decree No. 205/2004/NĐ-CP dated December 14, 2004 of the Government on the wage scale, salary table, and salary allowances in state-owned companies, and Circular No. 3656/VPCP-VX dated July 12, 2006 of the Government Office, the Ministry of Labor, Invalids, and Social Affairs guides the implementation of wage and allowance systems for workers, employees, and officials constructing the Dong Nai 4 Hydropower Project as follows:

I. SCOPE AND APPLICABLE SUBJECTS.

1\. The scope of application includes workers, employees, and officials directly involved in constructing the Dong Nai 4 Hydropower Project located in Lam Dong and Dak Nong provinces.

2\. Applicable subjects:

a\. Workers, employees, and officials directly involved in construction;

b\. Workers, employees, and officials under the Project Management Board directly involved in construction;

c\. Consulting, designing workers, employees, and officials working at the project site;

d\. Workers, employees, and officials directly involved in surveying to serve the technical design of the project.

Subjects mentioned in points c and d above shall not apply to those receiving attraction allowances and hazardous work allowances already agreed upon in Document No. 2807/LĐTBXH dated August 29, 2005 of the Ministry of Labor, Invalids, and Social Affairs regarding allowances for surveying staff in power projects.

II. APPLIED REGIME.

1\. Wage and salary allowance system:

a\. Minimum wage:

- Before October 1, 2005, the general minimum wage of VND 290,000/month as stipulated in Decree No. 203/2004/NĐ-CP dated December 14, 2004 shall be applied.

- From October 1, 2005 onwards, the minimum wage of VND 350,000/month as stipulated in Decree No. 118/2005/NĐ-CP dated September 15, 2005 shall be applied.

b\. Job grade wages:

- Job grade: determined according to specific jobs based on the basic construction cost estimate issued by the Ministry of Construction;

- Job grade wages: calculated according to the corresponding wage coefficient of each specific job grade based on the aforementioned cost estimate.

c\. Salary allowance system:

- Regional allowance, construction project, or construction item located in which area shall be calculated according to the regional allowance rate for that area;

- Attraction allowance, applied at 30% of job grade, position, or specialized vocational wage;

- Mobility allowance, applied at 0.4 times the general minimum wage.

d\. Job grade wages and the allowances mentioned in points b and c above shall be calculated as follows:

- For construction work volume completed before October 1, 2004, including wages and allowances for surveyors, designers, and consultants, shall be applied according to Scale A6, Group IV issued with Decree No. 26/CP dated May 23, 1993, and allowance systems according to Circular No. 03/2001/TTLT-BLĐTBXH-BTC-UBDTMN dated January 18, 2001 guiding the implementation of regional allowance systems; Circular Nos. 16/LĐTBXH-TT and 19/LĐTBXH-TT dated June 2, 1993 guiding the implementation of attraction and mobility allowances.

- For construction work volume implemented from October 1, 2004 onwards, including wages and allowances for surveyors, designers, and consultants, shall be applied according to Scale A.1.8, Group III issued with Decree No. 205/2004/NĐ-CP dated December 14, 2004, and allowance systems according to Joint Circular Nos. 10/2005/TTLT-BNV-BLĐTBXH-BTC and 11/2005/TTLT-BNV-BLĐTBXH-BTC-UBDT dated January 5, 2005 guiding the implementation of attraction and regional allowances; Circular No. 05/2005/TT-BLĐTBXH dated January 5, 2005 guiding the implementation of mobility allowances in state-owned enterprises.

2\. Unstable production factor coefficient, applied at 15% of job grade, position, or specialized vocational wage.

3\. Midday meal allowance, applied at VND 5,000/person/day. The organization and implementation of midday meals shall follow Circular No. 15/1999/TT-BLĐTBXH dated June 22, 1999 guiding the implementation of midday meal allowances for workers and officials working in state-owned enterprises. The application of midday meal allowances shall commence from July 12, 2006.

III. IMPLEMENTATION:

1\. Source of funding.

a\. The provisions set out in Points 1, 2, and 3, Section II of this Circular, applicable to workers, employees, and officials directly engaged in construction, shall be included in labor costs in the construction budget. For workers, employees, and officials under the Project Management Board, these costs shall be included in the Project Management Board's budget.

b\. The provisions set out in Point 1, Section II of this Circular, applicable to surveyors, designers, and consultants directly working at the project site, shall be included in labor costs in the consulting and design budget.

c\. Midday meal costs shall be included in the project budget but not within labor costs.

d\. Additional funding sources to implement the provisions set out in Section II of this Circular shall be sourced from the contingency fund of the project.

2\. Responsibilities of Vietnam Electricity Corporation (project sponsor)

a\. Based on the quantity determined according to the technical design or construction drawings or the work requirements of the project, the applicable systems stipulated in Section II of this Circular and the Circular guiding the preparation and management of project investment construction costs, calculate labor costs in the project budget.

b\. Based on the quantity of work completed and accepted, and the wage rates and midday meal costs included in the project budget, temporarily advance and settle payments to the construction units.

3\. Construction units, based on the completed work volume, wage rates, and midday meal costs included in the project budget temporarily advanced or settled by the project sponsor, organize timely and full payment to workers linked to productivity, work volume, quality, and project progress.

4\. The Ministry of Industry shall inspect whether the project sponsor has incorporated the applicable systems stipulated in Section II of this Circular into the unit price and project budget.

5/ The Ministry of Agriculture and Rural Development and the Ministry of Construction shall inspect construction units of projects to ensure compliance with the regulations stipulated in this Circular.

IV. EFFECTIVE DATE OF IMPLEMENTATION:

This Circular shall take effect fifteen days from the date of publication in the Official Gazette.

The provisions set forth in this Circular shall be implemented from the start of construction until the completion of the project, except for the mid-shift meal allowance which shall be implemented from July 12, 2006 until the completion of the project.

In the course of implementation, if there are any difficulties, the relevant ministries and enterprises are requested to report to the Ministry of Labor, Invalids and Social Affairs for study and resolution./.

 

The original file of this document is being updated. Please read the full text and check back later.

Relations map

08/2006/TT-BLĐTBXH
Circular No. 08/2006/TT-BLDTBXH guiding the wage system and allowances for workers, staff, and officials directly involved in constructing the Dong Nai 4 Hydropower Project.
In effect
↓ Documents affected by this document
References 10
05/2005/TT-BLĐTBXH Thông tư số 05/2005/TT-BLĐTBXH Hướng dẫn thực hiện chế độ phụ cấp lưu động trong các công ty nhà nước theo Nghị định số 205/2004/NĐ-CP ngày 14 tháng 12 năm 2004 của Chính phủ Expired 11/2005/TTLT/BNV-BLĐTBXH-BTC-UBDT Thông tư liên tịch số 11/2005/TTLT/BNV-BLĐTBXH-BTC-UBDT Hướng dẫn thực hiện chế độ phụ cấp khu vực In effect 203/2004/NĐ-CP Nghị định số 203/2004/NĐ-CP Quy định mức lương tối thiểu Expired 16/LĐTBXH-TT Thông tư số 16/LĐTBXH-TT Hướng dẫn về thời giờ làm việc hàng ngày được rút ngắn đối với những người làm những công việc đặc biệt nặng nhọc, độc hại, nguy hiểm In effect 10/2005/TTLT/BNV-BLĐTBXH-BTC Thông tư liên tịch số 10/2005/TTLT/BNV-BLĐTBXH-BTC Hướng dẫn thực hiện chế độ phụ cấp thu hút In effect 118/2005/NĐ-CP Nghị định số 118/2005/NĐ-CP Điều chỉnh mức lương tối thiểu chung Expired 03/2001/TTLT/BLĐTBXH-BTC-UBDTMN Thông tư liên tịch số 03/2001/TTLT/BLĐTBXH-BTC-UBDTMN Hướng dẫn thực hiện chế độ phụ cấp khu vực Expired 15/1999/TT-BLĐTBXH Thông tư số 15/1999/TT-BLĐTBXH Hướng dẫn thực hiện chế độ ăn giữa ca đối với công nhân, viên chức làm việc trong các doanh nghiệp nhà nước Expired 19/LĐTBXH-TT Thông tư số 19/LĐTBXH-TT Hướng dẫn việc dạy nghề, đào tạo lại nghề, bổ túc, bồi dưỡng nghề cho người lao động và dạy thêm nghề dự phòng cho lao động nữ làm việc trong doanh nghiệp In effect 26-CP Nghị định số 26-CP Quy định tạm thời chế độ tiền lương mới trong các doanh nghiệp Expired

Click a document to open. A red border = a relation that changes validity.