Decision No. 24/2005/QĐ-BXD of the Ministry of Construction issues the Construction Cost Estimation Standards - Construction Works Section, replacing old standards and taking effect from the date of publication in the Official Gazette. These standards are uniformly applied nationwide to serve as the basis for cost estimation and investment construction expense management.
Scope of application
Ministries, ministerial-level agencies, government agencies, People's Committees of provinces and centrally governed cities; construction works units.
Key points
- The Construction Cost Estimation Standards - Construction Works Section replace the old standards previously issued by the Ministry of Construction.
- These standards are uniformly applied nationwide and take effect fifteen days after their publication in the Official Gazette.
- These standards serve as the basis for provinces and centrally governed cities to establish unit prices for construction, serving as the foundation for cost estimation, total construction cost estimation, and investment construction expense management.
🌐 Social impact of this document
- Reduce administrative burdens for construction works units.
- Enhance uniformity in cost estimation and investment construction expense management across the country.
❓ Frequently asked questions
When does this construction cost estimation standard take effect?
This construction cost estimation standard takes effect fifteen days after its publication in the Official Gazette.
Does this standard replace the old standards of the Ministry of Construction?
Yes, the Construction Cost Estimation Standards - Construction Works Section replace the basic construction cost estimation standards issued under Decision No. 1242/1998/QĐ-BXD; Decision No. 31/2002/QĐ-BXD and other agreed-upon standards.
What should construction works units do when applying these standards?
Construction works units must use these standards to prepare cost estimates, total construction cost estimates, and manage investment construction expenses.
Are these standards effective nationwide?
Yes, the Construction Cost Estimation Standards - Construction Works Section are uniformly applied nationwide.
Does this decision take effect immediately upon issuance or must it wait for publication in the Official Gazette?
This decision takes effect fifteen days after its publication in the Official Gazette.
Full text
DECISION OF THE MINISTER OF CONSTRUCTION
ADOPTING THE "BUDGET ESTIMATE UNIT RATES FOR CONSTRUCTION PROJECTS - CONSTRUCTION PART"
THE MINISTER OF CONSTRUCTION
Pursuant to the Construction Law No. 16/2003/QH11 dated November 26, 2003 of the National Assembly, 11th term, fourth session of the Socialist Republic of Vietnam;
Pursuant to the Government Decree No. 16/2005/NĐ-CP dated February 7, 2005 on Management of Investment Construction Projects;
Pursuant to Decree No. 36/2003/NĐ-CP dated April 4, 2003 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;
At the proposal of the Director of the Economic and Finance Department, the Director of the Institute of Construction Economics, and the Director of the Legal Affairs Department,
DECISION:
Article 1.
The "BUDGET ESTIMATE UNIT RATES FOR CONSTRUCTION PROJECTS - CONSTRUCTION PART" is promulgated together with this Decision.
Article 2.
This "BUDGET ESTIMATE UNIT RATES FOR CONSTRUCTION PROJECTS - CONSTRUCTION PART" replaces the sets of "BUDGET ESTIMATE UNIT RATES FOR BASIC CONSTRUCTION" issued pursuant to Decision No. 1242/1998/QD-BXD dated November 25, 1998; Decision No. 31/2002/QD-BXD dated November 12, 2002; the Drilling Work for Pile Foundation in Decision No. 17/2004/QD-BXD dated July 5, 2004; Decision No. 05/2005/QD-BXD dated January 24, 2005 of the Minister of Construction, and certain unit rates agreed upon by the Ministry of Construction for issuance by relevant ministries, sectors, and localities listed in this set of unit rates.
Article 3.
This "BUDGET ESTIMATE UNIT RATES FOR CONSTRUCTION PROJECTS - CONSTRUCTION PART" shall be uniformly applied throughout the country and shall take effect fifteen days from the date of publication in the Official Gazette. It serves as the basis for provinces and centrally administered cities to establish construction unit prices for preparing project estimates and total construction project budgets and managing investment costs.
Article 4.
Ministries, ministerial-level agencies, government-attached agencies, People's Committees of provinces and centrally administered cities are responsible for implementing this Decision./.
DEPUTY MINISTER
Download
The original file of this document is being updated. Please read the full text and check back later.