Circular No. 25/2012/TT-BKHCN stipulates the list and control requirements for materials and equipment in the nuclear fuel cycle, applicable to organizations and individuals using, storing, exporting, or importing such materials and equipment. Notably, it requires declarations and compliance with specific requirements when storing, using, exporting, or importing.
Scope of application
Organizations and individuals using, storing, exporting, or importing materials and equipment in the nuclear fuel cycle; State management agencies on radiation safety and nuclear safety and other relevant agencies and organizations.
Key points
- Organizations and individuals storing or using materials and equipment in the nuclear fuel cycle must comply with the requirements set forth in Clause 1, Article 8 of the Regulation on Nuclear Safety Control issued together with Decision No. 45/2010/QĐ-TTg.
- In cases where there is no storage or use of materials and equipment in the nuclear fuel cycle, a report must be submitted to the Radiation and Nuclear Safety Administration at least 30 days prior.
- Organizations and individuals exporting or importing materials and equipment in the nuclear fuel cycle must declare to the Radiation and Nuclear Safety Administration according to Form 03-II/AP or Form 04-II/AP at least 15 days before the expected date.
- For nuclear equipment, in addition to declaration, a permit for radiation work must be obtained in accordance with Circular No. 08/2010/TT-BKHCN.
- This Circular takes effect 45 days from the date of issuance.
🌐 Social impact of this document
- Positive impact: Helps ensure radiation and nuclear safety, preventing risks during the use of nuclear materials and equipment.
- Negative impact: May impose administrative burden on organizations and individuals required to comply with reporting requirements and implement regulations.
❓ Frequently asked questions
What is the legal basis for this Circular?
This Circular is based on the Atomic Energy Law 2008, Decree No. 28/2008/NĐ-CP, and Decision No. 45/2010/QĐ-TTg of the Government.
Which organizations and individuals are subject to this Circular?
This Circular applies to organizations and individuals using, storing, exporting, or importing materials and equipment in the nuclear fuel cycle.
What are the specific requirements for storing and using materials and equipment in the nuclear fuel cycle?
Organizations and individuals must comply with the requirements set forth in Clause 1, Article 8 of the Regulation on Nuclear Safety Control issued together with Decision No. 45/2010/QĐ-TTg.
What steps must organizations and individuals take when exporting or importing materials and equipment in the nuclear fuel cycle?
They must declare to the Radiation and Nuclear Safety Administration according to Form 03-II/AP or Form 04-II/AP at least 15 days before the expected export or import date, and report on the implementation of the planned activities within 15 days thereafter.
When does this Circular take effect?
This Circular takes effect 45 days from the date of issuance.
Full text
CIRCULAR
Article 24Prescribes the list and control requirements for materials and equipment in the nuclear fuel cycle
Pursuant to Decree No.For power plants invested under the Build-Operate-Transfer (BOT) model, n is determined according to the operational period of the power plant stipulated in the BOT contract.
___________________________
Pursuant to the Atomic Energy Law 2008;
WHEREAS,28/2008/NĐ-CP dated March 4, 12008 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Science and Technology;amendPursuant to Decision No. 45/2010/QĐ-TTg dated June 14, 2010 of the Prime Minister on the issuance of the Regulations on Nuclear Control Activities; The Minister of Science and Technology issues this Circular prescribing the list and control requirements for materials and equipment in the nuclear fuel cycle.
This Circular prescribes the list and control requirements for materials and equipment in the nuclear fuel cycle.
1. Organizations and individuals using, storing, exporting, or importing materials and equipment in the nuclear fuel cycle.
Article 1. Scope of Regulation
2. State management agencies for radiation safety and nuclear activities and other relevant agencies and organizations.
Article 2. Applicability
Article 3. List of materials and equipment in the nuclear fuel cycle
The list of materials and equipment in the nuclear fuel cycle is prescribed in Appendix 1 attached hereto.
Article 4. Requirements for storage and use of materials and equipment in the nuclear fuel cycle
Organizations and individuals storing and using materials and equipment in the nuclear fuel cycle must comply with the following requirements:
1. Within the time limit specified in Clause 1, Article 8 of the Regulations on Nuclear Control Activities issued together with Decision No. 45/2010/QĐ-TTg dated June 14, 2010 of
2. In case of not storing or using, they must report to the Radiation and Nuclear Safety Agency at least 30 days prior, specifying the reasons and handling methods for the materials and equipment.
Article 5. Requirements for export and import of materials and equipment in the nuclear fuel cycle
Organizations and individuals exporting or importing materials and equipment in the nuclear fuel cycle must comply with the following requirements:
1. Report to the Radiation and Nuclear Safety Agency according to Form 03-II/AP or Form 04-II/AP prescribed in Appendix 2 attached hereto at least 15 days before the planned date of export or import of the consignment.
2. Report the implementation status of the planned schedule, including quantities, types, or any changes, no later than 15 days after the planned date of export or import.
3. For equipment in the nuclear fuel cycle that is nuclear equipment, in addition to complying with the provisions of Clause 1 of this Article, they must declare and apply for a permit to conduct radiation work in accordance with Circular No. 08/2010/TT-BKHCN dated July 22, 2010 of the Ministry of Science and Technology guiding the declaration and issuance of permits to conduct radiation work and certificates for radiation workers.
2. The Radiation and Nuclear Safety Agency shall be responsible for guiding, urging, and inspecting the implementation of this Circular.
3. During the implementation process, if there are difficulties or new issues arise, the relevant organizations and individuals are requested to promptly reflect them to the Ministry of Science and Technology for review and amendment./.
Article 6. Effectiveness and Implementation
1. This Circular shall take effect 45 days from the date of signature.
2. The Radiation and Nuclear Safety Agency shall be responsible for guiding, urging, and inspecting the implementation of this Circular.
3. During the course of implementation, if there are any difficulties or new issues arise, organizations and individuals concerned are requested to promptly reflect them to the Ministry of Science and Technology for consideration of amendments and supplements./.