Decision No. 3454/QD-BCN approves the national small hydropower planning, including 24 provinces with a total capacity from 1MW to 30MW. The decision requires investment to be consistent with the power development plan and the local electricity grid system.
Đối tượng áp dụng
Ministry of Industry, Director of the Ministry's Office, Department Head of Energy and Oil and Gas, Vietnam Electricity Corporation, People's Committees of provinces with projects, Heads of agencies and units and related individuals.
Các điểm cốt lõi
- The national small hydropower planning includes 24 provinces with a total capacity from 1MW to 30MW, totaling 239 projects with a total capacity of 1520.67MW.
- Investment projects for small hydropower must be consistent with the power development plan and the local electricity grid system.
- The capacity scale of each project will be accurately determined when preparing the investment project.
- The number of projects in each province has been detailed in Table 1.
- Small hydropower projects in the provinces of Lào Cai, Hà Giang, Quảng Nam, Gia Lai, Đắk Lắk, Đắk Nông, Kon Tum have separate decisions.
🌐 Tác động xã hội từ văn bản này
- Create opportunities for investment in the development of small hydropower in provinces.
- Close cooperation between management agencies and localities is required during the implementation of the planning.
❓ Câu hỏi thường gặp
Which provinces are included in the national small hydropower planning?
The national small hydropower planning includes 24 provinces, specifically Lai Châu, Điện Biên, Sơn La, Cao Bằng, Lạng Sơn, Yên Bái, Hòa Bình, Tuyên Quang, Quảng Ninh, Thanh Hóa, Nghệ An, Hà Tĩnh, Quảng Bình, Quảng Trị, Thừa Thiên Huế, Da Nang City, Quảng Ngãi, Bình Định, Phú Yên, Khánh Hòa, Ninh Thuận, Bình Thuận, Bình Phước, and Lâm Đồng.
What is the total capacity of the small hydropower projects?
The total capacity of the small hydropower projects is 1520.67MW.
How is the capacity scale of small hydropower projects determined?
The capacity scale of small hydropower projects ranges from 1MW to 30MW, but will be accurately determined when preparing the investment project.
How must small hydropower projects comply with the power development plan?
Small and medium hydropower projects must comply with the power development plan in each province for the period 2006-2010, synchronized with the schedule and progress of investment in the 110-220KV transmission grid system.
When does this decision apply?
This decision takes effect immediately upon issuance and shall be implemented in accordance with the provisions.
Toàn văn
Pursuant to …;
VDecision on approving the national small hydropower planning
________________________________
THE MINISTER OF INDUSTRY
Pursuant to Decree No. 55/2003/ND-CP dated May 28, 2003 of the Government on the functions, tasks, powers, and organizational structure of the Ministry of Industry;
Pursuant to the investment management and construction regulations issued together with Decree No. 52/1999/ND-CP dated July 8, 1999, and amended and supplemented by Decree No. 12/2000/ND-CP dated May 5, 2000 and Decree No. 07/2003/ND-CP dated January 30, 2003 of the Government;-Pursuant to Circular No. 923/CP-CN dated August 6, 2002 of the Prime Minister assigning the Ministry of Industry to review and approve the planning for small rivers not included in the National Hydropower Planning study project;
Considering the report No. 464/TTr-EVN-TD dated January 27, 2005 of Vietnam Electricity Corporation on the approval of the National Small Hydropower Planning, the research dossier of the National Small Hydropower Planning prepared by Company 1 for Consulting Construction in January 2005, revised in August 2005;
Pursuant to the comments from the People's Committees of provinces regarding the National Small Hydropower Planning project;
At the proposal of the Director of the Energy and Oil Department.
Approves the National Small Hydropower Planning for 24 provinces and cities with the main contents as follows:
ON DECREE
Article 1. 1. Capacity scale of projects: From 1 MW to 30 MW. The total number of projects is 239, with a total capacity of 1,520.67 MW. Details on the number and capacity of projects by province are set out in Table 1. The capacity scale of projects will be accurately determined when preparing the investment project.
2. The number and list of small hydropower projects by province are set out in the annex attached hereto.
3. List of small hydropower projects in the provinces of Lao Cai, Ha Giang, Quang Nam, Gia Lai, Dak Lak, Dak Nong, Kon Tum according to separate decisions already approved.
Table 1: Number and total capacity of projects by province
Province, City
|
Serial number |
Total number of projects |
Total capacity (MW) |
Yen Bai |
Remarks |
|
1 |
Lai Chau |
13 |
59,0 |
|
|
2 |
Dien Bien |
7 |
67,5 |
|
|
3 |
Son La |
19 |
114,6 |
|
|
4 |
Cao Bang |
12 |
48,3 |
|
|
5 |
Lang Son |
9 |
29,0 |
|
|
6 |
Da Nang City |
29 |
236,3 |
|
|
7 |
Hoa Binh |
2 |
9,5 |
|
|
8 |
Tuyen Quang |
5 |
16,7 |
|
|
9 |
Quang Ninh |
1 |
20,0 |
|
|
10 |
Thanh Hoa |
8 |
16,6 |
|
|
11 |
Nghe An |
18 |
151,3 |
|
|
12 |
Ha Tinh |
5 |
98,0 |
|
|
13 |
Quang Binh |
2 |
5,0 |
|
|
14 |
Quang Tri |
3 |
10,0 |
|
|
15 |
Thua Thien Hue |
5 |
19,5 |
|
|
16 |
Quang Ngai |
3 |
9,7 |
|
|
17 |
Investment in medium and small hydropower projects must be consistent with the power development planning for each province during the period 2006-2010, taking into account up to 2015, synchronized with the plan and progress of investment in the transmission grid system of 110-220KV, in line with economic and social planning, water supply planning for agriculture and industry at the local level. During the process of management and implementation, if there are any difficulties requiring adjustments or supplements to the planning, please reflect them to the Ministry of Industry for consideration and resolution. |
10 |
71,8 |
|
|
18 |
Binh Dinh |
11 |
59,65 |
|
|
19 |
Phu Yen |
1 |
6,0 |
|
|
20 |
Khanh Hoa |
5 |
62,0 |
|
|
21 |
Ninh Thuan |
5 |
14,0 |
|
|
22 |
Binh Thuan |
6 |
57,62 |
|
|
23 |
Binh Phuoc |
15 |
47,1 |
|
|
24 |
Lam Dong |
45 |
288,2 |
|
|
|
Total |
239 |
1520,67 |
|
Article 2. The Heads of the Ministry’s Office, the Director of the Energy and Oil Department, Vietnam Electricity Corporation, People's Committees of provinces with projects, Heads of agencies and units, and relevant individuals are responsible for implementing this Decision./.
Article 3. The Head of the Ministry's Office, the Director of the Energy and Oil Department, the General Corporation of Vietnam Electricity, the People's Committees of provinces with projects, Heads of agencies and units, and individuals related to this matter are responsible for implementing this Decision./.
DEPUTY MINISTER