Decision No. 39/2005/QD-BNN Issuing Regulations on Applying Unit Prices for Detailed Planning of Resettlement Areas for the Son La Hydropower Project

Decision No. 39/2005/QD-BNN of the Ministry of Agriculture and Rural Development issues regulations on applying unit prices for detailed planning of resettlement areas for the Son La Hydropower Project. These regulations apply to concentrated resettlement areas, interwoven resettlements, and urban areas, aiming to accelerate the work of preparing, reviewing, and approving plans.

文号39/2005/QĐ-BNN
文件类型Decision
发布机关Ministry of Agriculture and Environment
签署人Hứa Đức Nhị — Thứ trưởng
更新29/06/2026
行业Agriculture and Rural Development
领域Uncategorized
发布日期07/07/2005
生效日期09/08/2005
失效日期27/09/2018
状态Expired
✦ 智能摘要

Decision No. 39/2005/QD-BNN of the Ministry of Agriculture and Rural Development issues regulations on applying unit prices for detailed planning of resettlement areas for the Son La Hydropower Project. These regulations apply to concentrated resettlement areas, interwoven resettlements, and urban areas, aiming to accelerate the work of preparing, reviewing, and approving plans.

适用范围

Agencies managing the Son La Hydropower Project, units preparing detailed planning of resettlement areas, People's Committees of Son La, Lai Chau, and Dien Bien Provinces.

要点

  • Detailed planning of resettlement areas for the Son La Hydropower Project.
  • Norms and unit prices for preparing detailed planning of concentrated resettlement areas are specifically defined, including costs such as developing the outline, surveying and investigating, mapping, planning, topographic surveying and mapping at scales of 1:2,000 and 1:500, reviewing plans.
  • The unit price for preparing interwoven resettlement arrangement schemes is 1.5 million VND per resettled household accepted.
  • For resettlement areas in villages of Zone 1-3, the unit price has adjustment factors: Zone 1 - K = 1.0; Zone 2 - K = 1.1; Zone 3 - K = 1.2.
  • Regulations applicable to the preparation of detailed planning for urban resettlement (towns, market towns, central communes) are applied according to norms and unit prices issued together with Decision No. 06/2005/QD-BXD of the Ministry of Construction.

🌐 本文件的社会影响

  • Positive impact: Accelerating the progress of preparing and reviewing detailed planning of resettlement areas, helping the Son La Hydropower Project to be completed on schedule.
  • Negative impact: Increased costs for implementing planning preparation work due to regional adjustment factors.
  • Enterprises: Must comply with regulations on unit prices and norms for preparing detailed planning of resettlement areas.

❓ 常见问题

What does the unit price for preparing detailed planning of concentrated resettlement areas include?

The unit price includes: Costs for developing the outline (design tasks) and budget for planning; surveying, investigating, and mapping current socio-economic conditions and socio-economic planning maps of resettlement areas; detailed planning of resettlement areas; topographic surveying and mapping at scales of 1:2,000 and 1:500; setting plot markers; and other costs such as plan review, plan management, and publicizing the plan.

What is the unit price for preparing interwoven resettlement arrangement schemes?

The unit price for preparing interwoven resettlement arrangement schemes is 1.5 million VND per resettled household accepted.

What are the adjustment factors for the unit price of concentrated resettlement areas in different zones?

Adjustment factors for the unit price of concentrated resettlement areas in different zones are as follows: Zone 1 - K = 1.0; Zone 2 - K = 1.1; Zone 3 - K = 1.2.

How does this decision apply to urban resettlement areas?

Regulations applicable to the preparation of detailed planning for urban resettlement (towns, market towns, central communes) are applied according to norms and unit prices issued together with Decision No. 06/2005/QD-BXD of the Ministry of Construction.

When does this decision take effect?

This decision takes effect fifteen days after its publication in the Official Gazette.

全文

MINISTRY OF AGRICULTURE AND RURAL DEVELOPMENT
DEVELOPMENT OF RURAL AREAS

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 39/2005/QĐ-BNN
Hanoi, July 7, 2005

DECISION

ISSUING REGULATIONS ON UNIT PRICES FOR PREPARATION OF DETAIL PLANNING ZONES (POINTS) FOR RELOCATION PROJECT OF SON LA HYDROPOWER PLANT

RESIDENTIAL AREA OF THE SON LA HYDROPOWER PROJECT

THE MINISTER OF AGRICULTURE AND RURAL DEVELOPMENT

Pursuant to Decree No. 86/2003/NĐ-CP dated July 18, 2003 of the Government on the functions, tasks, powers, and organizational structure of the Ministry of Agriculture and Rural Development;

Pursuant to Decree No. 16/2005/NĐ-CP dated February 7, 2005 of the Government on project management for investment construction works;

Pursuant to Decree No. 08/2005/NĐ-CP dated January 24, 2005 of the Government on planning for construction;

Pursuant to Decision No. 207/2004/QĐ-TTg dated December 11, 2004 of the Government on the management mechanism and implementation of the Son La Hydropower Project;

Based on the proposal of the Director of the Planning Department, the Director of the Construction Management Department, the Director of the Legal Affairs Department, and the Head of the Specialized Sub-Committee on Relocation Work of the Son La Hydropower Project, 

DECISION:

Article 1. These regulations on unit prices for preparation of detail planning zones (points) for relocation of the Son La Hydropower Project are hereby issued together with this decision.

Article 2. This Decision shall take effect fifteen days from the date of publication in the Official Gazette.

Article 3. The Ministries, ministerial-level agencies, agencies under the Government, People's Committees of Son La, Dien Bien, and Lai Chau provinces shall be responsible for implementing this Decision.

 

DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Huu Duc Nhi

REGULATIONS

On the application of norms and unit prices for preparation of detail planning zones (points)

for relocation of the Son La Hydropower Project.

(Attached to Decision No.: 39/2005/QĐ-BNN dated July 7, 2005

of the Ministry of Agriculture and Rural Development)

 

PART I

GENERAL PROVISIONS

Article 1. Purpose and requirements.

Issuing norms and unit prices for preparation of detail planning zones (points) for relocation to expedite the work of preparing, reviewing, and approving detail planning zones (points) for relocation of the Son La Hydropower Project.

Article 2. Scope and objects of application:

1. Scope: Applied to detail planning zones (points) for relocation of the Son La Hydropower Project.

2. Objects: Various costs serving the work of preparing and reviewing detail planning zones (points) for relocation of the Son La Hydropower Project.

 

Chapter II

STANDARDS AND UNIT PRICES FOR PREPARATION OF DETAIL PLANNING

ZONES, POINTS FOR RELOCATION

Article 3. Provisions on standards and unit prices.

1. The standards prescribed in this decision serve as the basis for preparing budgets for the work of preparing and reviewing detail planning zones (points) for relocation of the Son La Hydropower Project, including:

- Detail planning for concentrated relocation zones (points).

- Relocation resettlement arrangement plans.

- Detail planning for urban relocation zones.

2. The unit prices prescribed in this decision serve as the basis for preparing budgets, reviewing, and finalizing settlement accounts for the costs of preparing and reviewing detail planning zones (points) for relocation within the Son La Hydropower Project.

3. Basis for establishing standards and unit prices for detail planning zones (points) for relocation of the Son La Hydropower Project.

Using unit prices issued by central ministries, sectors, and localities based on appropriate adaptation to the actual conditions of the Son La Hydropower Resettlement Project, specifically as follows:

- Decision No.: 02/2000/QĐ-BNN-KH dated January 4, 2000 of the Minister of Agriculture and Rural Development on issuing agricultural and rural planning prices.

- Decision No.: 06/2005/QĐ-BXD dated February 3, 2005 of the Minister of Construction on issuing construction planning cost standards.

- Circular No. 03/2005/TT-BXD dated March 4, 2005 of the Ministry of Construction guiding adjustments to basic construction project budgets.

- Decision No.: 519/2002/QĐ-BKH dated August 26, 2002 of the Minister of Planning and Investment on temporarily issuing a framework price and construction planning cost standards for overall economic and social development plans, industries, and territories.

- Decision No.: 62/2001/QĐ-UB dated January 9, 2001 of the People's Committee of Son La Province on issuing construction survey unit prices.

- Decision No.: 32/2001/QĐ-UB dated June 26, 2001 of the People's Committee of Lai Chau Province (former) on issuing construction survey unit prices.

- Decision No.: 7751/QĐ-UB dated December 14, 2001 of the People's Committee of Hanoi City on temporarily issuing unit prices for boundary marking, coordinate attachment, area calculation, lot division marking, and map digitization services for construction surveys in the Hanoi area.

Article 4. Unit prices for preparation of detail planning for concentrated relocation zones (points).

1. Costs for the work of preparing detail planning for concentrated relocation zones (points) include:

1.1. Costs for building the outline (design task) and budget for planning:

The construction cost for the outline (design task) and budget for detailed planning of relocation zones is calculated at 10% of the cost of preparing the detailed planning design document (according to Decision No.: 06/2005/QĐ-BXD dated February 3, 2005 of the Minister of Construction), specified in Sections I, II, III - Appendix 01 attached to these regulations.

1.2. Costs for investigation, survey, creation of current socio-economic status maps, and socio-economic planning maps of the relocation zone (commune):

Applying the unit prices in Table 1 of Decision No.: 02/2000/QĐ-BNN-KH dated January 4, 2000 of the Minister of Agriculture and Rural Development, specified in Section I - Appendix 01 attached to these regulations.

1.3. Costs for preparing detail planning for relocation zones (points):

Applying the unit prices in Table 5 - Part IV of Decision No. 06/2005/QĐ-BXD dated February 3, 2005 of the Minister of Construction on construction planning cost standards, specifically as follows:

- Costs for detail planning of production land for relocation points: Specified in Section II - Appendix 01 attached to these regulations.

- Costs for preparing detail planning for residential areas within relocation points: Specified in Section III - Appendix 01 attached to these regulations.

1.4. Costs for topographic survey work to create 1:2,000 scale topographic maps:

Including control point establishment, elevation control, and 1:2,000 scale topographic map drawing costs: Specified in Appendix 02 attached to these regulations.

1.5. Costs for topographic survey work to create 1:500 scale topographic maps: Specified in Appendix 02 attached to these regulations.

1.6. Costs for lot division marker installation: Specified in Appendix 02 attached to these regulations.

1.7. Other costs:

- Costs for reviewing detail planning for relocation zones (points): Calculated at 9% of the cost of preparing the detailed planning document for relocation zones (points);

- Costs for reviewing the outline (design task) and budget: Calculated at 10% of the cost of reviewing detail planning for relocation zones (points).

- Planning management costs: Calculated at 6% of the cost of preparing the detailed planning project for the resettlement area (point);

- Publication costs: Calculated at 3% of the cost of preparing the detailed planning project for the resettlement area (point) (when settling accounts, there must be a detailed budget approved), this funding is assigned to the project investor responsible for organizing its implementation.

2. The price of the detailed planning project for the concentrated resettlement area includes the following items: Costs for collecting related materials, labor costs, material costs, depreciation costs of machinery and equipment, management costs, conference costs to approve the results of the planning project, training and professional development costs, health insurance, social insurance, trade union fees, and pre-tax income (excluding value-added tax).

3. The unit price stipulated in Section 1, Article 4 of this regulation shall be increased by the following factor:

Detailed planning for resettlement areas in villages in Zone 1: factor K = 1.0.

Detailed planning for resettlement areas in villages in Zone 2: factor K = 1.1.

Detailed planning for resettlement areas in villages in Zone 3: factor K = 1.2.

Article 5. Unit price for preparing the resettlement arrangement plan with interwoven resettlement.

Includes the following items: Costs for collecting related materials, labor costs, material costs, management costs, conference costs, and construction costs for the plan. When settling accounts, there must be a detailed budget approved by the People's Committee of the district or town.

The price for preparing the resettlement arrangement plan with interwoven resettlement is calculated at VND 1.5 million per resettled household accepted.

Article 6. Unit price for preparing the urban resettlement arrangement plan (towns, market towns, central communes).

The work of preparing urban resettlement planning shall apply the norms and unit prices issued together with Decision No. 06/2005/QĐ-BXD dated February 3, 2005, of the Minister of Construction.

 

Chapter III

IMPLEMENTATION

1. The People's Committees of Son La, Lai Chau, and Dien Bien provinces shall implement the application of unit prices and norms for preparing and reviewing detailed plans as stipulated herein, accelerate the review and approval process for detailed plans for the resettlement areas of the Son La Hydropower Project, to meet the set schedule.

2. During the implementation process, if there are any difficulties requiring adjustments and supplements, the People's Committees of Son La, Lai Chau, and Dien Bien provinces are requested to promptly report in writing to the Ministry of Agriculture and Rural Development for consideration, adjustment, and supplementation to ensure appropriateness./.

DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Huu Duc Nhi
本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

下载

本文件的原始文件正在更新中,请先查看全文,稍后再来查看。

关系图

↑ 依据及影响本文件的文件
39/2005/QĐ-BNN
Decision No. 39/2005/QD-BNN Issuing Regulations on Applying Unit Prices for Detailed Planning of Resettlement Areas for the Son La Hydropower Project
Expired

点击文件即可打开。红色边框=改变效力的关系。