This Circular sets forth the expenditure regime for state-level scientific and technological research and development activities, applicable to programs, topics, and projects in science and technology. Maximum expenditure levels are specified according to specific fields of science and stages of the research process.
Đối tượng áp dụng
State-level science and technology programs, topics, and projects
Các điểm cốt lõi
- State-level science and technology programs, topics, and projects apply maximum expenditure levels of 25-35% for remuneration and contractual hiring, and 45-55% for raw materials and equipment.
- For basic investigation activities, the maximum expenditure level is 50-60% for remuneration and contractual hiring, and 20-30% for raw materials and equipment.
- Specific expenditure levels are defined for each stage such as drafting outlines, theoretical research, experiments, writing specialized reports, compiling data, surveys, scientific conferences, summarization, evaluation, and acceptance.
- Expenditure levels may change when market prices fluctuate by 20% or more.
- Program, topic, and project leaders base their payment of remuneration to scientific and technical staff on product quality and actual financial capacity.
🌐 Tác động xã hội từ văn bản này
- Positive impact: Provides a legal basis for budget preparation and approval, aiding research and development units in effectively managing finances.
- Negative impact: May cause difficulties in application due to market price fluctuations requiring frequent adjustments.
❓ Câu hỏi thường gặp
How are the maximum expenditure levels specified?
The maximum expenditure levels are set at 25-35% for remuneration and contractual hiring, and 45-55% for raw materials and equipment.
Do expenditure levels change with market price fluctuations?
Yes, when market prices fluctuate by 20% or more, the relevant ministries will study and adjust expenditure levels accordingly.
Who is subject to these expenditure levels?
They apply to state-level science and technology programs, topics, and projects.
What can topic leaders do to adjust expenditure levels?
Leaders base their payment of remuneration to scientific and technical staff on product quality and actual financial capacity, with payment levels potentially being up to 10-15% lower than the maximum.
For which stages are specific expenditure levels defined?
Specific expenditure levels are defined for stages such as drafting outlines, theoretical research, experiments, writing specialized reports, compiling data, surveys, scientific conferences, summarization, evaluation, and acceptance.
Toàn văn
CIRCULAR
JOINT MINISTRY OF FINANCE AND SCIENCE, TECHNOLOGY AND ENVIRONMENT
REGULATIONS ON EXPENSES
FOR RESEARCH AND DEVELOPMENT ACTIVITIES
Pursuant to Decree No. 35/HĐBT dated January 28, 1992 of the Council of Ministers (now the Government), the Joint Ministry of Finance and Science, Technology and Environment has issued several joint Circulars guiding financial management for national science and technology programs. These Circulars mainly guide financial management tasks but have not specified specific expense levels, causing difficulties for implementing units with inconsistent expenses among different programs, topics, and projects. To establish a basis for budgeting and approving expenditures for research and development tasks, the Joint Ministry of Finance and Science, Technology and Environment temporarily stipulates certain expense levels for scientific and technological activities as follows:
PART I
GENERAL PRINCIPLES
1. The expense levels prescribed in this Circular apply to national science and technology programs, topics, and projects. Research and development tasks at other levels shall be applied according to a certain ratio depending on product quality and allocated funding.
2. Certain expenditure items of programs, topics, and projects that are already covered by the current state regulations will not be prescribed here (such as purchasing raw materials, equipment, energy, transportation means, purchasing service documents... at market prices).
3. The levels prescribed in this Circular are maximum levels. Program leaders, topic leaders, and project leaders shall base their payment of remuneration to scientific and technical staff on product quality and actual available funds, which may be equal to or lower than 10 - 15% compared to the maximum level.
In the process of managing budget preparation and approval, strictness and thriftiness must be maintained, achieving efficiency, focusing on financing scientific research activities, purchasing raw materials and equipment, and paying remuneration for scientific staff.
PART II
SPECIFIC PROVISIONS
Research and development activities in different fields of science have different expenditure contents and structures. Therefore, the Joint Ministry temporarily guides programs, topics, and projects according to scientific fields and sets expenditure structure orientations as a basis for annual budget preparation.
I. STRUCTURE AND RATIO OF EXPENSES BY SCIENTIFIC FIELD:
1. SCIENCE AND TECHNOLOGY
Clause 1: Payment of labor and contractual hiring 25% - 35%
Clause 2 and 3: Raw materials and equipment 45% - 55%
Clause 4: Minor repairs and construction: if there is a need to prepare a separate description to allocate funds.
Clause 5: Administrative management and other expenses 20%
2. SOCIAL SCIENCES
Clause 1: Payment of labor and contractual hiring 50% - 60%
Clause 2, 3, and 4: Raw materials, equipment, minor repairs and construction: if there is a need to prepare a separate description to allocate funds.
Clause 5: Administrative management and other expenses 40% - 50%
Travel expenses 10%
Purchase of documents, data, document translation, printing 15%
Scientific conferences and seminars 15%
Final acceptance and evaluation 5%
- Administrative management 5%
Topics researching scientific bases for policy formulation, sectoral development strategies, planning... shall use the structure and ratio of social science type.
3. NATURAL SCIENCES
Depending on the characteristics and content of each topic, the structure and ratio of one of the above types can be applied.
For topics requiring experimental equipment, materials, and chemicals to produce products and technologies, the structure and ratio of science and technology type should be used.
For theoretical research topics where the product is published works in domestic and international journals, the structure and ratio of social science type should be used.
4. BASIC INVESTIGATION
Clause 1: Payment of labor and contractual hiring 50% - 60%
Clause 2 and 3: Raw materials and equipment 20% - 30%
Clause 4: Minor construction repairs: if there is a need to establish a separate explanation to allocate funds.
Clause 5: Administrative management and other expenses 20%
Research topics with content and products like science and technology or research topics that only study theory such as social sciences shall use the structure and ratio of science and technology or social sciences.
II. SOME SPECIFIC EXPENSE LEVELS
The research process of a scientific topic or project includes many stages depending on each field of science. Below are some main stages as follows:
Establishing and reviewing the research outline
Collecting and analyzing domestic and foreign data.
Field investigation.
Theoretical experimental research.
Pilot testing and field testing.
Scientific seminar.
Writing project reports.
Testing and certification before acceptance.
Evaluation and acceptance summary.
To be consistent with these research stages, the Inter-Ministry temporarily stipulates specific expense levels for national programs, topics, and projects as follows in the Table:
Table:
|
No. |
Content of work |
Unit of Measurement |
Expense Level (1,000 dong) |
Remarks |
|
1 |
2 |
3 |
4 |
5 |
|
I |
Establishing and reviewing the research outline |
|||
|
1 |
- Establishing the general research outline of the topic or project (according to model R, R-D, P) - Establishing the detailed research outline of the topic (for social sciences) |
Outline Outline |
200 600 |
Accepted by the Review Committee |
|
2 |
- Establishing the general program outline - Establishing the detailed program outline (for social sciences) |
Outline Outline |
500 1000 |
As above |
|
3 |
Reviewing the program, topic, and project outlines - Chairperson of the Council - Committee member secretary - Committee member reviewer - Member |
1 session 1 session 1 session 1 session |
70 70 70 50 |
|
|
II |
Theoretical research, experimentation, writing specialized reports, and compiling data |
|||
|
1 |
Writing specialized reports (or parts with defined themes) |
1 report |
300 |
15-20 typed pages accepted by the topic leader |
|
2 |
Compiling from existing data |
1 article |
200 |
15-20 typed pages accepted by the topic leader |
|
No. |
Content of work |
Unit of Measurement |
Expense Level (1,000 dong) |
Remarks |
|
1 |
2 |
3 |
4 |
5 |
|
3 |
Reviewing specialized articles |
1 article |
50 |
Maximum 2 reviews for 1 specialized article |
|
4 |
Revising and perfecting the report after each feedback or scientific seminar |
Each revision |
50 |
Maximum 2 times |
|
5 |
Collecting, exploiting, and creating data sheets |
1 sheet |
20 |
Accepted by the topic leader |
|
6 |
Conducting experiments according to the topic content |
Person/day |
10 |
Applies to science and technology |
|
III |
Survey and investigation |
|||
|
1 |
Creating a survey form containing approximately 30 parameters |
1 form |
50 |
Approved by the committee |
|
2 |
Entering information into the form |
1 form |
10 |
Contains 30-40 questions (given to the information provider) |
|
3 |
Processing forms and creating a report |
1 report |
150 |
10-15 typed pages, accepted by the topic leader |
|
4 |
Payment for staff going on-site or collecting information forms - Mountainous areas, coastal regions, remote and difficult areas - Other areas: |
Person/day |
60 |
In accordance with the current regulations |
|
5 |
Payment for guides - Mountainous areas or particularly difficult conditions |
Person/day |
20 |
|
|
6 |
Payment for excavation workers, archaeologists |
Person/day |
25 |
|
|
No. |
Content of work |
Unit of Measurement |
Expense Level (1,000 dong) |
Remarks |
|
1 |
2 |
3 |
4 |
5 |
|
IV |
Scientific conferences |
|
|
|
|
1 |
Internal scientific seminars within the topic (among collaborators) |
Person/day |
50 |
|
|
2 |
Scientific seminars involving multiple fields - Seminar host - Seminar secretary - Report presenter - Seminar participant contributing opinions |
Person/day 1 report Person/day |
70 70 150 50 |
Program or topic seminar about 10 pages |
|
V |
Summary, evaluation, and acceptance of the topic, project, or program |
|||
|
1 |
Writing comprehensive reports, summary reports |
Typed page |
25 |
Accepted by the Acceptance Committee |
|
2 |
Revising and perfecting the comprehensive report of the topic or project after initial acceptance |
(Handle according to regulations on handling students and trainees using drugs) |
500 |
Only counted once |
|
3 |
Testing and certification before acceptance (science and technology field) |
Expert/day |
80 |
|
|
4 |
Initial Acceptance Committee - Chairperson (with comments) - Secretary (with comments) - Reviewer (with comments) - Member (with comments) |
1 session 1 session 1 session 1 session
|
100 100 150 80 |
Committee members read the comprehensive report, write comments, and participate in the acceptance session |
|
5 |
National Acceptance Committee - Chairperson (with comments) - Secretary (with comments) - Reviewer (with comments) - Member (with comments) |
1 session 1 session 1 session 1 session |
150 150 200 100 |
Committee members read the comprehensive report, write comments, and participate in the acceptance session. |
PART III
IMPLEMENTING PROVISIONS
When market prices fluctuate by 20% or more, the Inter-Ministry will study and adjust the expense levels accordingly.
This Circular takes effect from July 1, 1995.
During implementation, if any issues arise, relevant ministries, sectors, units, agencies, and localities should report to the Inter-Ministry for further study and amendment./.