Joint Circular No. 74 KH/TL-TC on borrowing funds from the Kuwait Fund for the construction of the lower Yazun irrigation project in Gia Lai and Kon Tum provinces.

Joint Circular No. 74 KH/TL-TC stipulates the borrowing of funds from the Kuwait Fund to construct the lower Yazun irrigation project in Gia Lai and Kon Tum provinces. The project was approved in 1986 with a total investment of 84 billion VND (from secondary canals and above). This circular specifies the sources of borrowed funds, fund management, and the responsibilities of relevant agencies.

Số hiệu74 KH/TL-TC
Loại văn bảnJoint Circular
Cơ quan ban hànhMinistry of Finance
Người kýNguyễn Cảnh Dinh — Thứ trưởng
Cập nhật02/07/2026
NgànhFinance
Lĩnh vựcDebt Borrowing ManagementDomestic Debt RepaymentGovernment External DebtPublic Sector DebtNational Debt and International Aid
Ngày ban hành14/02/1990
Ngày áp dụng14/02/1990
Ngày hết hiệu lực—
Tình trạngIn effect
✦ Tóm lược thông minh

Joint Circular No. 74 KH/TL-TC stipulates the borrowing of funds from the Kuwait Fund to construct the lower Yazun irrigation project in Gia Lai and Kon Tum provinces. The project was approved in 1986 with a total investment of 84 billion VND (from secondary canals and above). This circular specifies the sources of borrowed funds, fund management, and the responsibilities of relevant agencies.

Các điểm cốt lõi

  • The Ministry of Water Resources negotiated with the Kuwait Fund to borrow between 28 to 30 million USD.
  • The Ministry of Finance and the State Planning Commission will balance annual investment capital for the project according to the agreed schedule.
  • Enterprises under the Ministry of Water Resources commit to borrowing and repaying directly to the State Budget immediately upon implementation, with interest rates calculated based on those of the Kuwait Fund, and repayment period of about 8-10 years.
  • The State Budget will invest in constructing main works, primary and secondary canals, while Gia Lai and Kon Tum provinces are responsible for mobilizing additional contributions from the people amounting to 10%.
  • The Ministry of Water Resources is the principal investor and implementing agency for the project, working closely with local authorities to ensure timely completion and early utilization of benefits.

🌐 Tác động xã hội từ văn bản này

  • Positive impact: Borrowed funds from Kuwait help shorten the construction time of the lower Yazun irrigation project, contributing to the promotion of local and Western Highlands economies.
  • Negative impact: Increased debt repayment costs for the State Budget over the next 8-10 years.

❓ Câu hỏi thường gặp

How much money does the Ministry of Water Resources borrow from the Kuwait Fund?

The Ministry of Water Resources negotiated to borrow between 28 to 30 million USD from the Kuwait Fund.

What is the repayment period?

The repayment period (principal and interest) is approximately 8-10 years.

What role will the State Budget play in this borrowing?

The State Budget will balance annual investment capital for the project according to the agreed schedule, while enterprises under the Ministry of Water Resources commit to borrowing and repaying directly to the State Budget immediately upon implementation.

What responsibility does Gia Lai and Kon Tum Province have in this matter?

Gia Lai and Kon Tum Province are responsible for mobilizing additional contributions from the people amounting to 10% for the construction of the project.

How will the Ministry of Water Resources manage the borrowed funds?

Enterprises under the Ministry of Water Resources commit to borrowing and repaying directly to the State Budget immediately upon implementation, while the portion allocated for constructing main works, primary and secondary canals will be managed through the State Budget repayment.

Toàn văn

MINISTRY OF FINANCE, MINISTRY OF WATER RESOURCES

SOCIALIST REPUBLIC OF VIETNAM

Independence - Freedom - Happiness

------------------------------

No.: 74 KH/TL-TC

Hanoi, February 14, 1990

 

JOINT CIRCULAR

Regarding borrowing funds from the Kuwait Fund for the construction of the Yazun Lower Water Conservancy Project in Gia Lai-Kon Tum Province

The Yazun Lower Water Conservancy Project in Gia Lai-Kon Tum Province was approved by the Prime Minister's Council for the preliminary design and technical estimate at the end of 1986. In the two years 1988-1989, the Ministry of Water Resources and the People's Committee of Gia Lai-Kon Tum Province have prepared for construction such as surveying, technical design, preparing the total budget estimate, and preparing the construction site to build some components of the main works and irrigation canal system.

As an infrastructure construction project with clear benefits and important position in the economic development of Gia Lai-Kon Tum and the Central Highlands, which has been identified as a national priority, only 2 billion dong were implemented in the two years 1988-1989; the plan for 1990 was balanced at 4 billion dong out of the total investment capital for the entire project (from secondary canals upwards) amounting to 84 billion dong (based on the price in quarter 2/1989). If not concentratedly invested by the State, the construction time will be prolonged, so it is necessary to borrow funds from Kuwait to provide investment capital and shorten the construction time of the project.

With the agreement of the Prime Minister in Document No. 1575 KTĐN dated August 24, 1989, allowing procedures for borrowing funds from the Kuwait Fund for the construction of the Yazun Lower Project, the Ministry of Water Resources directly worked with the National Planning Commission, the Ministry of Finance, the Office of the Government Council, the State Bank, and the People's Committee of Gia Lai-Kon Tum Province.

The Ministry of Water Resources and the Ministry of Finance submit to the Prime Minister regarding borrowing the Kuwait Fund for the Yazun Lower Project as follows:

1. On external matters: Entrust the Ministry of Finance and the State Bank to lead negotiations with the Kuwait Fund to borrow between 28 to 30 million US dollars together with the Ministry of Water Resources.

2. On internal matters:

a. The borrowed capital will be included in the State budget balance, the Ministry of Finance and the National Planning Commission will coordinate the annual investment capital for the project according to the committed schedule.

b. Principles of managing the borrowed capital:

1- The portion of capital for purchasing construction equipment: enterprises under the Ministry of Water Resources commit to borrowing and repaying to the State budget immediately after implementation. The interest rate will be calculated based on the interest rate of the Kuwait Fund, the repayment period (principal and interest) will be about 8-10 years.

The Ministry of Finance and the Ministry of Water Resources will issue specific regulations.

2- The portion of borrowed capital included in the State budget balance for investing in constructing the main works, primary and secondary canals will be repaid by the State budget, Gia Lai-Kon Tum Province is responsible for mobilizing people to contribute an additional 10% for the construction of this project.

c. The amount negotiated with the Kuwait Fund in cash will be deposited into the State's foreign currency reserve fund for use according to the general plan.

d- The Ministry of Water Resources is the leading management agency and the main investor of the project, along with local authorities, will be responsible for implementing the project well to quickly achieve its effectiveness.

3- To effectively implement the negotiation for borrowing funds from the Kuwait Fund, it is proposed that the Prime Minister promptly issue a decision to initiate negotiations.

MINISTER OF WATER RESOURCES

(Signed)

 

NGUYEN CANH DINH

THE MINISTER OF FINANCE

(Signed)

 

HOANG QUI

 

 

 

Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 1
74 KH/TL-TC
Joint Circular No. 74 KH/TL-TC on borrowing funds from the Kuwait Fund for the construction of the lower Yazun irrigation project in Gia Lai and Kon Tum provinces.
In effect

Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.