High School A has a project level of Level II because the project includes a combination of main works used for educational purposes with a scale of 1,500 students and some auxiliary works.
적용 범위
Investment Construction Project of High School A
핵심 사항
- The combination of main works of the project has a project level of Level II according to the capacity scale.
- Individual works within the project have levels from III to IV depending on their scale and type.
- Applying project levels to determine the authority for investment construction management.
- For works not listed in Table 1.1 Appendix I, the project level is determined based on the type and structural scale as specified in Table 2 Appendix II.
- The project level is determined based on the highest criterion between the level determined from the capacity scale and the structural scale.
🌐 이 문서의 사회적 영향
- To accurately determine the authority for investment construction management of the project.
- Ensuring the management and supervision of work quality appropriate to the level of each work within the project.
- Providing a legal basis for applying technical standards and design standards suitable to the project level.
❓ 자주 묻는 질문
How to determine the project level?
The project level is determined based on Table 1.1 Appendix I or Table 2 Appendix II in Circular number 06/2021/TT-BXD, depending on the type and scale of the work.
Why is the project level important?
The project level helps determine the authority for investment construction management of the project, ensuring that the quality of the work meets technical requirements and safety standards.
전문
|
| SOCIALIST REPUBLIC OF VIET NAM
|
CIRCULAR
REGULATIONS ON THE CLASSIFICATION OF CONSTRUCTION PROJECTS AND GUIDELINES FOR APPLICATION IN THE MANAGEMENT OF INVESTMENT CONSTRUCTION ACTIVITIES
Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on the classification of construction projects and guidelines for application in the management of investment construction activities has been amended and supplemented by:
1. Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on the classification of construction projects and guidelines for application in the management of investment construction activities;
2. Circular No. 09/2025/TT-BXD dated June 13, 2025, of the Minister of Construction amending and supplementing certain articles of circulars under the State management of the Ministry of Construction related to organizational restructuring, implementation of two-level local administration, and decentralization to local authorities.
Pursuant to the Law on Construction dated June 18, 2014; the Law Amending and Supplementing Certain Provisions of the Law on Construction dated June 17, 2020;
Pursuant to the Law on Architecture dated June 13, 2019;
Pursuant to the Government Decree No. 06/2021/NĐ-CP dated January 26, 2021 detailing certain provisions on quality management, construction works, and maintenance of construction projects;
Pursuant to Decree No. 15/2021/ND-CP dated March 3, 2021 of the Government detailing certain contents regarding project management of investment construction;
Pursuant to Decree No. 81/2017/NĐ-CP dated July 17, 2017 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;
At the proposal of the Director of the National Construction Quality Supervision Agency;
The Minister of Construction promulgates this Circular on the classification of construction projects and guidelines for applying project classification in the management of investment construction activities.[1]
Article 1. Scope of Regulation and Applicability
1[2]Scope of Application
This Circular provides detailed regulations on the classification of construction projects and guidelines for applying project classification in managing investment construction activities as stipulated in the Construction Law; specifically, Article 5, Clause 4 of the Construction Law 2014, amended and supplemented by Clause 3, Article 1 of the Law Amending and Supplementing Certain Provisions of the Construction Law 2020 and Clause 2, Article 3 of Decree No. 06/2021/NĐ-CP.
Thông tư này áp dụng đối với tổ chức, cá nhân có liên quan đến hoạt động kinh doanh đối tượng thủy sản nuôi chủ lực trên lãnh thổ Việt Nam.
This Circular applies to investors, project owners, asset owners, managers, users of construction works, domestic contractors, foreign contractors, state management agencies in construction, and other organizations and individuals related to investment construction activities within the territory of Vietnam.
Article 2. Principles for Determining Project Classification
1. The project classification specified in this Circular shall be determined based on the following criteria:
a) Level of importance, capacity scale: Applied to individual projects or a combination of projects or a production line consisting of multiple components within a construction project investment according to the types of projects specified in Appendix I of this Circular;
b) Structural scale: Applied to individual projects within a construction project investment according to the structural types specified in Appendix II of this Circular.
2. The project classification of an individual project is the highest level determined according to Appendices I and II of this Circular. In cases where an individual project is not specified in Appendix I of this Circular, its project classification shall be determined according to the provisions of Appendix II of this Circular, and vice versa.
3. The project classification of a combination of projects or a production line consisting of multiple components shall be determined as follows:
a) Where a combination of projects or a production line consisting of multiple components is specified in Appendix I of this Circular, the project classification shall be determined according to Appendix I of this Circular;
b) Where a combination of projects or a production line consisting of multiple components is not specified in Appendix I of this Circular, the project classification shall be determined according to the classification of the main project (within the combination of projects or production line) with the highest level. The classification of the main project is determined according to the provisions of Clause 2 of this Article.
4. The project classification of existing projects undergoing repair, renovation, or upgrading shall be determined as follows:
a) Where repair, renovation, or upgrading changes the criteria for determining project classification as stipulated in Clause 1 of this Article, the project classification of the project after repair, renovation, or upgrading shall be determined according to the provisions of this Article;
b) In other cases not covered by point a of this clause, the project classification of the project before and after repair, renovation, or upgrading remains unchanged.
5[3]The project classification of independently constructed new structures that are not part of phased investment projects of existing construction projects shall be determined according to the provisions of Clauses 1, 2, and 3 of this Article.
6[4]In cases where projects belong to phased investment projects, the criteria specified in Clause 1 of this Article corresponding to the completion stage shall be used to determine the project classification.
7[5]The determination of project classification for certain types of projects is guided by Appendix III attached to this Circular.
Article 3. Application of project levels in managing investment construction activities
1. The project levels prescribed in this Circular shall be applied as the basis for managing the following investment construction activities:
a) Determining the authority when reviewing feasibility study reports; reviewing or providing opinions on technology for investment construction projects using restricted transfer technologies or investment construction projects with potential negative environmental impacts using technology as stipulated in the Law on Technology Transfer; reviewing implementation design after basic design; inspecting acceptance work during construction and upon completion of construction works;
b) Classifying the capacity of construction activities of organizations and individuals to issue capacity certificates and practice certificates for construction activities;
c) Determining construction works exempt from building permits;
d) Determining construction works required to hold architectural design competitions as provided for in Clause 2, Article 17 of the Architecture Law;
đ) Determining construction works requiring separate technical guidelines to be established;
e) Determining construction works significantly affecting safety and public interests;
g) Determining construction works requiring mandatory professional liability insurance;
h) Determining construction works that must undergo periodic safety assessments during use;
i) Classifying construction accidents and determining the authority to resolve construction accidents;
k) Managing investment construction costs;
l) Determining the warranty period and amount for construction works;
m) Determining construction works that must establish maintenance procedures;
n) Other contents as prescribed by laws on managing investment construction works.
2. The application of project levels to manage investment construction activities as specified in point a, Clause 1 of this Article is as follows:
a) In cases where an investment construction project consists of only one independent main construction work: Apply the project level determined according to the provisions of Clause 2, Article 2 of this Circular;
b) In cases where an investment construction project includes multiple independent main construction works or is constructed along a route (consisting of multiple construction works arranged consecutively along the route): Apply the level of the highest main construction work determined according to the provisions of Clause 2, Article 2 of this Circular;
c) In cases where an investment construction project comprises a combination of main construction works or a production line consisting of multiple components: Apply the project level determined according to the provisions of Clause 3, Article 2 of this Circular;
d) In cases where an investment construction project includes multiple combinations of main construction works, multiple production lines, or a mixed combination: Apply the level of the highest combination of main construction works or production line determined according to the provisions of Clause 3, Article 2 of this Circular.
3. The principles for applying project levels to manage investment construction activities as specified from point b to point n, Clause 1 of this Article are as follows:
a) In cases where the scope of implementation is for a single independent construction work, apply the project level determined for Clause 2, Article 2 of this Circular that construction work;
b) In cases where the scope of implementation is for several construction works within an investment construction project, apply the project level determined for Clause 2, Article 2 of this Circular each reviewed construction work;
c) In cases where the scope of implementation is for an entire combination of construction works or an entire production line consisting of multiple components, apply the project level determined according to the provisions at Clause 3, Article 2 of this Circular. In cases where an investment construction project is implemented along a route, follow the provisions at point d of this clause;
d) In cases where the scope of implementation is for a single construction work, several construction works, or all construction works within an investment construction project implemented along a route, apply the project level determined for Clause 2, Article 2 of this Circular each construction work along the route.
4[6]. In cases of phased investment projects, use the project level prescribed at Clause 6, Article 2 of this Circular to apply project levels in managing investment construction activities as stipulated in Clauses 1, 2, and 3 of this Article.
5[7]. The application of project levels for certain types of construction works is guided in Appendix III issued together with this Circular.
Article 4. Provisions on Transition[8]
1. Projects for construction works under investment projects that have been decided to invest before this Circular takes effect shall be classified according to the provisions of the law at the time of approving the construction project investment plan.
2. In cases where the design of the construction work is adjusted after this Circular takes effect:
a) The adjustment of the construction design does not change the criteria for determining the classification of the construction work as stipulated in Clause 1 of Article 2 of this Circular, then the classification of the construction work shall be determined according to the provisions of the law at the time of approving the construction project investment plan;
b) The adjustment of the construction design changes the criteria for determining the classification of the construction work as stipulated in Clause 1 of Article 2 of this Circular, then the classification of the construction work shall be determined according to the provisions of this Circular.
Article 5. Effective Date[9]
1. This Circular takes effect from August 15, 2021 and replaces Circular No. 03/2016/TT-BXD dated March 10, 2016 of the Minister of Construction on the classification of construction works and guidance on application in investment construction management activities and Circular No. 07/2019/TT-BXD dated November 7, 2019 of the Minister of Construction on amending, supplementing, and replacing some provisions of Circular No. 03/2016/TT-BXD.
2. During implementation, if there are difficulties, organizations and individuals are requested to send their opinions to the Ministry of Construction for consideration and resolution./.
| MINISTRY OF CONSTRUCTION Number: 06/VBHN-BXD
| CERTIFIED CONSOLIDATED DOCUMENT
Hanoi, July 3, 2025
DEPUTY MINISTER |
ANNEX I
CLASSIFICATION OF CONSTRUCTION WORKS ACCORDING TO LEVEL OF IMPORTANCE OR CAPACITY SCALE
(Annexed to Circular No. 06/2021/TT-BXD dated June 30, 2021 of the Minister of Construction)
Table 1.1 Classification of construction works for civilian purposes (civilian construction works)
| Serial number | Civil construction installation. | Classification criteria | Level of Project | ||||
| Special | I | II | III | IV | |||
| 1.1.1 | Educational and training facilities | ||||||
| 1.1.1.1 Kindergarten, primary school, nursery school | Level of importance | Class III with all scales | |||||
| 1.1.1.2 Primary school | Total number of students in the entire school |
|
| ≥700 | <700 |
| |
| 1.1.1.3 Secondary school, high school, multi-level general education school | Total number of students in the entire school |
|
| ≥1.350 | <1.350 |
| |
| 1.1.1.4 University, college; vocational high school, vocational school, technical worker school, specialized school | Total number of students in the entire school |
| >8.000 | 5.000 ÷ 8.000 | <5.000 |
| |
| 1.1.2 | Medical facilities | ||||||
| 1.1.2.1 General hospital, specialized hospital from central to local level (Central hospitals must be at least Class I) | Total number of beds | >1.000 | 500 ÷ 1.000 | 250 ÷ <500 | <250 |
| |
| 1.1.2.2 Biosafety laboratory (Biosafety level determined according to the regulations of the health sector) | Biosafety level (BSL) |
| BSL level 4 | BSL level 3 | BSL level 1 and BSL level 2 |
| |
| 1.1.3 | ||| 2,000m² or more | ||||||
| 1.1.3.1 Outdoor sports stadium with grandstand (National stadium, national outdoor sports venue must be at least Class I) | Grandstand capacity (thousand seats) | >40 | >20 ÷ 40 | 5 ÷ 20 | <5 |
| |
| 1.1.3.2 Indoor sports venue with grandstand (National indoor sports venue must be at least Class I) | Grandstand capacity (thousand seats) | >7,5 | 5 ÷ 7,5 | 2 ÷ <5 | <2 |
| |
| 1.1.3.3[10] Golf course | Number of holes |
|
| ≥18 | <18 |
| |
| 1.1.3.4 Swimming pool, outdoor sports field | Level of importance |
|
|
| National competition standard | Recreational sports activities | |
| 1.1.4 | Cultural facilities | ||||||
| 1.1.4.1 Conference center, cultural house, club, discotheque, and other concentrated cultural facilities for large crowds (National conference center must be at least Class I) | Total capacity (thousand people) | >3 | >1,2 ÷ 3 | >0,3 ÷ 1,2 | ≤0,3 |
| |
| 1.1.4.2 Theater, cinema, circus | Total audience capacity (thousand people) | >3 | >1,2 ÷ 3 | >0,3 ÷ 1,2 | ≤0,3 |
| |
| 1.1.4.3 Museum, library, exhibition, display house | Level of importance |
| National | Provincial | Other cases |
| |
| 1.1.5 | Market | Number of business points |
|
|
| >400 | ≤400 |
| 1.1.6 | Religious facilities | Level of importance | Class III with all scales | ||||
| 1.1.7 | Government agency office, political organization, political-social organization | Level of importance | National Assembly House, Presidential Palace, Government Office, Party Central Committee Office; other extremely important facilities | Office of: Provincial Party Committee; Provincial People's Council, Provincial People's Committee; Ministries[11]Supreme People's Court, Supreme People's Procuracy[12] | Office:[13] Bureau, Department and equivalent level; Provincial People's Court, Provincial People's Procuracy[14] | Office of: District Party Committee, District People's Council, District People's Committee[15] |
|
Note:
- For other civilian construction works with usage purposes consistent with those listed in Table 1.1, Table 1.1 should be used to determine the classification based on the level of importance or capacity scale.
- Refer to examples of classifying civilian construction works in Appendix III.
Table 1.2 Classification of construction works for industrial production purposes (industrial construction works)
| Serial number | Civil construction installation. | Classification criteria ||| | Level of Project | ||||
| Special | I | II | III | IV | |||
| 1.2.1 | Construction works for producing building materials, building products | ||||||
| 1.2.1.1 Quarrying of minerals for building materials (limestone for cement, clay for cement, cement additives, kaolin, feldspar, fireclay, white clay, white sand, dolomite, stone for facing, limestone for lime, construction stone, other types of mineral building materials) | |||||||
| a) Works using explosives | Level of importance | Class II with all scales | |||||
| b) Works not using explosives | Annual production capacity (million m3 product/year) |
|
| ≥1 | <1 |
| |
| 1.2.1.2[16] Cement clinker plant, cement grinding plant, cement distribution plant | Annual production capacity (million tons/year) |
| ≥2 | <2 |
|
| |
| 1.2.1.3[17] (Repealed) |
|
|
|
|
|
| |
| 1.2.1.4 Ordinary concrete component manufacturing plant, concrete block manufacturing plant | Annual production capacity (thousand m3 finished product/year) |
|
| >150 | ≤150 |
| |
| 1.2.1.5 Centrifugal concrete component manufacturing plant, prestressed concrete component manufacturing plant, precast hollow concrete wall panel manufacturing plant | Annual production capacity (thousand m3 finished product/year) |
| >150 | 30 ÷ 150 | <30 |
| |
| 1.2.1.6 Lightweight concrete block manufacturing plant, lightweight concrete wall panel manufacturing plant | Annual production capacity (thousand m3 finished product/year) |
| >200 | 100 ÷ 200 | <100 |
| |
|
| 1.2.1.7 Brick and tile firing plant | Annual production capacity (million standard bricks/year) |
| >40 | 20 ÷ 40 | <20 |
|
| 1.2.1.9 Ceramic tile manufacturing plant | |||||||
| a) Ceramic tile manufacturing plant | Annual production capacity (million m2 product/year) |
| >5 | 3 ÷ 5 | <3 |
| |
| b) Artificial stone tile manufacturing plant | Annual production capacity (million m2 product/year) |
| >1 | 0,5 ÷ 1 | <0,5 |
| |
| c) Natural stone tile manufacturing plant | Annual production capacity (million m2 product/year) |
| >0,3 | 0,1 ÷ 0,3 | <0,1 |
| |
| 1.2.1.9 Sanitary ware manufacturing plant | Annual production capacity (million products/year) |
| >1 | 0,3 ÷ 1 | <0,3 |
| |
| 1.2.1.10 Building glass manufacturing plant | Annual production capacity (million m2 product/year) |
| ≥20 | <20 |
|
| |
| 1.2.1.11 Glass product manufacturing plant (tempered glass, laminated glass, multi-layer glass...) | Annual production capacity (million m2 product/year) |
|
| ≥0,2 | <0,2 |
| |
| 1.2.1.12[18] Industrial lime manufacturing plant and post-lime products | Annual production capacity (thousand tons of products/year) |
|
| ≥60 | <60 |
| |
| 1.2.1.13 Refractory material manufacturing plant | Annual production capacity (thousand tons of products/year) |
| >10 | 5 ÷ 10 | <5 |
| |
| 1.2.1.14 Cement sheet manufacturing plant with fiber core | Annual production capacity (million m2 product/year) |
|
| ≥0,3 | <0,3 |
| |
| 1.2.1.15 Dry mortar manufacturing plant | Annual production capacity (million tons of products/year) |
|
| ≥0,3 | <0,3 |
| |
| 1.2.1.16 Gypsum board manufacturing plant | Annual production capacity (million m2 product/year) |
| >20 | 10 ÷ 20 | <10 |
| |
| 1.2.2 | Metallurgical and machinery manufacturing works | ||||||
| 1.2.2.1 Metallurgical plant | |||||||
| a) Non-ferrous metallurgical plant | Annual production capacity (million tons of finished products/year) |
| >0,5 | 0,1 ÷ 0,5 | <0,1 |
| |
| b) Steel rolling and drawing plant | Annual production capacity (million tons of finished products/year) |
| >1 | 0,5 ÷ 1 | <0,5 |
| |
| 1.2.2.2 Iron and steel complex | Blast furnace capacity (thousand m3) | >1 | ≤1 |
|
|
| |
| 1.2.2.3 Power machinery and agricultural machinery manufacturing plant | Annual production capacity (thousand products/year) |
| >5 | 2,5 ÷ 5 | <2,5 |
| |
| 1.2.2.4 Machine tool and industrial equipment manufacturing plant | Annual production capacity (thousand products/year) |
| >1 | 0,5 ÷ 1 | <0,5 |
| |
| 1.2.2.5 Lifting equipment manufacturing plant | TSL (thousand tons of product/year) |
| >200 | ≤200 |
|
| |
| 1.2.2.6 Construction plant for construction machinery | |||||||
| a) Plant producing and assembling bulldozers, excavators, loaders | TSL (products/year) |
| >250 | ≤250 |
|
| |
| b) Plant producing and assembling static and vibratory rollers | TSL (products/year) |
| >130 | ≤130 |
|
| |
| c) Plant producing and assembling mobile cranes | TSL (products/year) |
| >40 | ≤40 |
|
| |
| 1.2.2.7 Construction plant for complete equipment | TSL (thousand tons of equipment/year) |
| >10 | 5 ÷ 10 | <5 |
| |
| 1.2.2.8 Plant producing and assembling transportation vehicles | |||||||
| a) Plant producing and assembling automobiles | TSL (thousand units/year) |
| >10 | 5 ÷ 10 | <5 |
| |
| b) Plant producing and assembling motorcycles | TSL (thousand units/year) |
| >500 | ≤500 |
|
| |
| c) Plant producing and assembling locomotives | TSL (thousand units/year) |
| >1 | 0,5 ÷ 1 | <0,5 |
| |
| d) Facility for building new inland waterway vessels | Gross tonnage of vessel (thousand DWT) |
| >30 | 10 ÷ 30 | 5 ÷ <10 | <5 | |
| đ) Facility for building new ocean-going vessels | Gross tonnage of vessel (thousand DWT) | >70 | >40 ÷ 70 | >20 ÷ 40 | >5 ÷ 20 | ≤5 | |
| 1.2.3 | Mining and mineral processing projects | ||||||
| 1.2.3.1 Underground coal mine | TSL (million tons of coal/year) |
| >1 | 0,3 ÷ 1 | <0,3 |
| |
| 1.2.3.2 Underground ore mine | TSL (million tons of ore/year) |
| >3 | 1 ÷ 3 | <1 |
| |
| 1.2.3.3 Open-pit coal mine | TSL (million tons of coal/year) |
|
| ≥2 | <2 |
| |
| 1.2.3.4 Open-pit ore mine | TSL (million tons of ore/year) |
|
| ≥2 | <2 |
| |
| 1.2.3.5 Coal washing and beneficiation plant | TSL (million tons/year) |
| >5 | 2 ÷ 5 | <2 |
| |
| 1.2.3.6 Ore beneficiation/enrichment plant (including bauxite beneficiation) | TSL (million tons/year) |
| >7 | 3 ÷ 7 | <3 |
| |
| 1.2.3.7 Alumina production facility | Level of importance | Class I with all scales | |||||
| 1.2.4 | Oil and gas projects | ||||||
| 1.2.4.1 Offshore extraction project (production platform) | Level of importance | Class I with all scales | |||||
| 1.2.4.2 Oil refining facility | Annual production capacity (million tons/year) | ≥10 | <10 |
|
|
| |
| 1.2.4.3 Gas processing facility | Annual production capacity (million m3 (cubic meters/day) | ≥10 | <10 |
|
|
| |
| 1.2.4.4 Biofuel production facility | Annual production capacity (thousand tons of products/year) | >500 | 200 ÷ 500 | <200 |
|
| |
| 1.2.4.5 Fuel storage depot | Total storage capacity (thousand cubic meters)3) | >100 | 5 ÷ 100 | 0,21 ÷ <5 | <0,21 |
| |
| 1.2.4.6 Liquefied natural gas storage facility, liquefied natural gas refueling station | Total storage capacity (thousand cubic meters)3) | >100 | 5 ÷ 100 | <5 |
|
| |
| 1.2.5 | Energy projects | ||||||
| 1.2.5.1 Thermal power plant | TCS (MW) | >2.000 | 600 ÷ 2.000 | 50 ÷ <600 | <50 |
| |
| 1.2.5.2 Nuclear power plant | Level of importance | Special class with all scales | |||||
| 1.2.5.3 Hydroelectric power plant | |||||||
| a) Power plant | Total installed capacity (MW) | >1.000 | >50 ÷ 1.000 | >30 ÷ 50 | ≤30 |
| |
| b) Reservoir | Reservoir volume corresponding to normal water level (million cubic meters)3) | >1.000 | >200 ÷ 1.000 | >20 ÷ 200 | ≥3 ÷ 20 | <3 | |
| c) Dam | (Scale and characteristics of dam) |
|
|
|
|
| |
| Height of largest earth or earth-rock dam (m) | A | >100 | >70 ÷ 100 | >25 ÷ 70 | >10 ÷ 25 | ≤10 | |
| B |
| >35 ÷ 75 | >15 ÷ 35 | >8 ÷ 15 | ≤8 | ||
| C |
|
| >15 ÷ 25 | >5 ÷ 15 | ≤5 | ||
| Height of largest concrete or reinforced concrete dam (m) | A | >100 | >60 ÷ 100 | >25 ÷ 60 | >10 ÷ 25 | ≤10 | |
| B |
| >25 ÷ 50 | >10 ÷ 25 | >5 ÷ 10 | ≤5 | ||
| C |
|
| >10 ÷ 20 | >5 ÷ 10 | ≤5 | ||
| Note: The class of hydroelectric power plant is determined according to the classification criteria for power plants, reservoirs, and dams (where Groups A, B, and C are typical geological foundation groups: Group A is rock foundation; Group B is sand and gravel, coarse soil, and semi-hard clay foundation; Group C is saturated clay foundation in plastic state). For pumped-storage hydroelectric power plants, after determining the class according to this section, it shall be reduced by one class but not lower than Class III under any circumstances. 2[19]. The class of facilities on the "Energy Line" such as Intake Structure, Conveyance Channel (canal, culvert, tunnel), Pressure Tower, Pressurized Pipeline, Outlet Channel or Tunnel, etc., is determined according to the highest class of the hydroelectric power plant specified in point a of item 1.2.5.3 and the scale classification specified in Appendix II of this Circular for the facility being considered. 3[20]. The class of facilities on the "Connection Line" such as Water-Raising Dam, Overflow Dam, Surface Spillway, Deep Spillway, Emergency Spillway, other water intake structures, etc., is determined according to the highest class of the Water-Raising Dam specified in point c of item 1.2.5.3 and the scale classification specified in Appendix II of this Circular for the facility being considered. 4. Other related facilities such as Operation Management House, Fence, Road, etc., in the construction project of hydroelectric power plant are classified according to the type of facility as guided in this Circular. | |||||||
| 1.2.5.4 Wind power plant | TCS (MW) |
| ≥50 | >15 ÷ <50 | >3 ÷ 15 | ≤3 | |
| 1.2.5.5 Solar power plant | TCS (MW) |
| ≥50 | >15 ÷ <50 | >3 ÷ 15 | ≤3 | |
| 1.2.5.6 Geothermal power plant | TCS (MW) |
| >10 | 5 ÷ 10 | <5 |
| |
| 1.2.5.7 Tidal power plant | TCS (MW) |
| >50 | 30 ÷ 50 | <30 |
| |
| 1.2.5.8[21] Waste-to-energy power plant | TCS (MW) |
| >15 | 5 ÷ 15 | <5 |
| |
| 1.2.5.9 Biomass power plant | TCS (MW) |
| >30 | 10 ÷ 30 | <10 |
| |
| 1.2.5.10 Biogas power plant | TCS (MW) |
| >15 | 5 ÷ 15 | <5 |
| |
| 1.2.5.11 Transmission line and substation | Voltage (kV) | ≥500 | 220 | 110 | >35 ÷ <110 | ≤35 | |
| 1.2.5.12 Retail fuel station/LNG refueling station; charging station/electric vehicle battery swap station. | Level of importance | Class III with all scales | |||||
| 1.2.6 | Chemical industry projects | ||||||
| 1.2.6.1 Production facility for fertilizer products and plant protection chemicals | |||||||
| a) Production facility for single and compound fertilizers (with chemical reactions, including: urea, DAP, MAP, SA, complex NPK, superphosphate, etc.) | TSL (thousand tons of product/year) |
| ≥50 | 10 ÷ <50 | <10 |
| |
| b) Production facility for other fertilizers (blending, mixing, thermal, microbial methods - without chemical reactions) | TSL (thousand tons of product/year) |
| ≥300 | 100 ÷ <300 | <100 |
| |
| c) Production facility, filling station, packaging plant for plant protection chemicals | TSL (thousand tons of product/year) |
| >15 | 10 ÷ 15 | <10 |
| |
| 1.2.6.2 Production facility for basic chemical products, petrochemicals, pharmaceutical chemicals, cosmetic chemicals, and other chemicals | |||||||
| a) Production facility for basic chemicals (acids, bases, chlorine...), hazardous toxic chemicals, inorganic and organic chemicals, other industrial chemicals (including pure chemicals, salts, flotation reagents for apatite...) | TSL (thousand tons of product/year) |
| ≥10 | <10 |
|
| |
| b) Production facility, warehouse, filling station for petrochemical products (plastic raw materials PP, PE, PVC, PS, ABS, PET, SV, fibers, DOP, SM, VCM, Polystyrene, PTA, MEG, BTX, synthetic rubber, and other products) | TSL (thousand tons of product/year) |
| ≥50 | <50 |
|
| |
| c) Production facility for pharmaceutical chemicals (extraction, purification of natural and synthetic active ingredients from chemicals) Note: Does not include production facilities for drugs and medical supplies; preliminary processing, compounding, and manufacturing of traditional Chinese medicine | Level of importance | Class I with all scales | |||||
| d) Production facility for cleaning agents and cosmetics (detergent cream, laundry powder, cleaning solutions, soap; shampoo, bath lotion, toothpaste, bathing soap, etc.) | TSL (thousand tons of product/year) |
| ≥15 | 10 ÷ <15 | <10 |
| |
| 1.2.6.3 Production facility for electrochemical products | |||||||
| a) Production facility for chemical batteries | TSL (million units/year) |
| >250 | 150 ÷ 250 | <150 |
| |
| b) Production facility, recycling of accumulators | TSL (thousand kWh/year) |
| >300 | 100 ÷ 300 | <100 |
| |
| c) Production facility for welding rods | TSL (thousand tons of product/year) |
|
|
| ≥3 | <3 | |
| 1.2.6.4 Production facility, warehouse, filling station for industrial gases (O2, N2, Ar, CO, CO2, He, H2, Xe, CH4, C2H2 and other industrial gases) | |||||||
| a) Production facility for industrial gases | TSL (thousand cubic meters/hour)3 b) Warehouse, filling station for industrial gases |
| >15 | 8,5 ÷ 15 | <8,5 |
| |
| Maximum capacity (tons) | 1.2.6.5 Production facility for rubber products |
| ≥100 | <100 |
|
| |
| a) Production facility for automobile tires and tractor tires | |||||||
| TSL (million units/year) | b) Production facility for motorcycle and bicycle tires |
| >1 | 0,5 ÷ 1 | <0,5 |
| |
| c) Production facility for conveyor belts | b) Production facility for motorcycle and bicycle tires |
|
| >5 | 1 ÷ 5 | <1 | |
| d) Production facility for technical rubber products | TSL (thousand cubic meters/hour)2 product/year) |
|
| >500 | 200 ÷ 500 | <200 | |
| TSL (million units/year) | 1.2.6.6 Production facility for paints and printing ink |
|
| >1,5 | 0,5 ÷ 1,5 | <0,5 | |
| a) Production facility for paints | |||||||
| b) Production facility for printing ink | TSL (thousand tons of product/year) |
| >100 | >20 ÷ 100 | 10 ÷ 20 | <10 | |
| 1.2.6.7 Ore apatite beneficiation plant | TSL (thousand tons of product/year) |
|
| >20 | 5 ÷ 20 | <5 | |
| 1.2.6.8 Production facility, storage of explosives and explosive precursors | TSL (thousand tons of product/year) |
| ≥100 | <100 |
|
| |
| a) Production facility for industrial explosives and explosive precursors | |||||||
| b) Warehouse for industrial explosives | Level of importance | Special class with all scales | |||||
| Underground warehouse, underground warehouse |
| ||||||
| Fixed above-ground warehouse and semi-underground warehouse | Level of importance | Class I with all scales | |||||
| Capacity (tons) | Mobile warehouse |
| >10 | ≤10 |
|
| |
| c) Warehouse for explosive precursors | Level of importance | Class II with all scales | |||||
| Hazardous chemical warehouse (excluding warehouses for industrial explosives and explosive precursors) |
| ||||||
| Fixed above-ground warehouse and semi-underground warehouse | Level of importance | Class I with all scales | |||||
| Capacity (tons) | Mobile warehouse |
| >50 | ≤50 |
|
| |
| c) Warehouse for explosive precursors | Level of importance | Class II with all scales | |||||
| 1.2.6.9[22] Light industry projects | 1.2.6.5 Production facility for rubber products |
| ≥1.000 | 500 ÷ <1.000 | 100 ÷ <500 | <100 | |
| 1.2.7 | 1.2.7.1 Food industry | ||||||
| a) Milk processing plant | |||||||
| TSL (million liters/year) | TSL (million liters/year) |
| >100 | 30 ÷ 100 | <30 |
| |
| b) Confectionery, instant noodle manufacturing plant | TSL (thousand tons of product/year) |
| >25 | 5 ÷ 25 | <5 |
| |
| c) Edible oil, flavoring manufacturing plant | TSL (thousand tons of product/year) |
| >150 | 50 ÷ 150 | <50 |
| |
| d) Alcohol, beer, soft drink manufacturing plant | TSL (million liters/year) |
| >100 | 25 ÷ 100 | <25 |
| |
| 1.2.7.2 Consumer industry | |||||||
| a) Spinning mill | TSL (thousand tons of product/year) |
| >75 | 30 ÷ 75 | <30 |
| |
| b) Textile weaving mill | TSL (million m2 product/year) |
| >25 | 5 ÷ 25 | <5 |
| |
| c) Printing and dyeing mill (textile and garment industry) | TSL (million m2 product/year) |
| >35 | 10 ÷ 35 | <10 |
| |
| d) Garment product manufacturing plant | 1.2.6.6 Production facility for paints and printing ink |
| >10 | 2 ÷ 10 | <2 |
| |
| đ) Leather processing plant and leather product manufacturing plant | 1.2.6.6 Production facility for paints and printing ink |
| >12 | 1 ÷ 12 | <1 |
| |
| e) Plastic product manufacturing plant | TSL (thousand tons of product/year) |
| >15 | 2 ÷ 15 | <2 |
| |
| g) Porcelain, glassware manufacturing plant | TSL (thousand tons of product/year) |
| >25 | 3 ÷ 25 | <3 |
| |
| h) Pulp and paper manufacturing plant | TSL (thousand tons of product/year) |
| >100 | 60 ÷ 100 | <60 |
| |
| i) Tobacco product manufacturing plant | TSL (million cigarette packs/year) |
| >200 | 50 ÷ 200 | <50 |
| |
| k) Electronics manufacturing/assembly plant (TVs, computers and equivalent products), refrigeration equipment manufacturing plant (air conditioners, refrigerators and equivalent products) | Annual production capacity (thousand products/year) |
| >300 | 100 ÷ 300 | <100 |
| |
| l) Information and electronics component manufacturing plant (printed circuit boards, ICs and equivalent products) | 1.2.6.6 Production facility for paints and printing ink |
| >400 | 300 ÷ 400 | <300 |
| |
| m) Currency printing plant | Level of importance | Special class with all scales | |||||
| 1.2.7.3 Agricultural, aquatic and seafood processing industry | |||||||
| a) Aquatic and seafood processing plant | TSL (tons of raw material/day) |
| >300 | 100 ÷ 300 | <100 |
| |
| b) Canned food processing plant | TSL (tons of raw material/day) |
|
| ≥100 | <100 |
| |
| c) Rice milling and polishing plant | TSL (thousand tons of product/year) |
| >200 | 100 ÷ 200 | 1 ÷ <100 | <1 | |
Note:
- Other industrial projects with purposes suitable for the types of projects listed in Table 1.2 shall use Table 1.2 to determine the level based on the degree of importance or capacity scale.
- Abbreviations in Table 1.2: TCS means Total Capacity; TSL means Total Output - Total Capacity (or Total Output) is calculated for all production lines within the project; QTC is standard criteria.
- Refer to examples of determining the level of industrial projects in Appendix III.
Table 1.3 Classification of infrastructure technical facilities (technical infrastructure facilities)
| Serial number | Civil construction installation. | Classification criteria | Level of Project | ||||
| Special | I | II | III | IV | |||
| 1.3.1 | Water supply facility | ||||||
| 1.3.1.1 Water treatment plant, clean water treatment facility (including sludge treatment facility) | Annual production capacity (thousand m3Volume of extracted water (m |
| ≥30 | 10 ÷ <30 | <10 |
| |
| 1.3.1.2 Raw water pumping station, clean water pumping station or pressure boosting station (including water storage tanks if applicable) | Annual production capacity (thousand m3Volume of extracted water (m |
| ≥40 | 12 ÷ <40 | <12 |
| |
| 1.3.2 | Drainage facility | ||||||
| 1.3.2.1 Stormwater retention pond | Area (ha) |
| ≥20 | 15 ÷ <20 | 1 ÷ <15 | <1 | |
| 1.3.2.2 Stormwater pumping station (including water storage tanks if applicable) | TCS (m3/s) |
| ≥25 | 10 ÷ <25 | <10 |
| |
| 1.3.2.3 Wastewater treatment facility | Annual production capacity (thousand m3Volume of extracted water (m |
| ≥20 | 10 ÷ <20 | <10 |
| |
| 1.3.2.4 Sewage pumping station (including water storage tanks if applicable) | TCS (m3/h) |
| ≥1.200 | 700 ÷ <1.200 | <700 |
| |
| 1.3.2.5 Sludge treatment facility | TCS (m3Volume of extracted water (m |
| ≥1.000 | 200 ÷ <1.000 | <200 |
| |
| 1.3.3 | Solid waste treatment facility (CTR) | ||||||
| 1.3.3.1 General solid waste treatment facility |
|
|
|
|
|
| |
| a) Transfer station | TCS (tons/day night) |
| ≥500 | 200 ÷ <500 | 100 ÷ <200 | <100 | |
| b) Solid waste treatment facility | TCS (tons/day night) | ≥500 | 200 ÷ <500 | 50 ÷ <200 | <50 |
| |
| 1.3.3.2 Hazardous solid waste treatment facility | TCS (tons/day night) |
| >100 | 20 ÷ 100 | <20 |
| |
| 1.3.4 | Park | Area (ha) |
| >20 | 10 ÷ 20 | 5 ÷ <10 | <5 |
| 1.3.5 | Cemetery National cemetery: Level I regardless of size | Area (ha) |
| >60 | 30 ÷ 60 | 10 ÷ <30 | <10 |
| 1.3.6 | Funeral home | Level of importance | National funeral home: Level I; others: Level II | ||||
| 1.3.7 | Crematorium | Level of importance | Class II with all scales | ||||
| 1.3.8 | Parking garage; open parking lot, machinery and equipment yard |
| |||||
| 1.3.8.1 Underground parking garage* | Number of parking spaces |
| ≥500 | 300 ÷ <500 | <300 |
| |
| 1.3.8.2 Above-ground parking garage* |
| ≥1.000 | 500 ÷ <1.000 | 100 ÷ <500 | <100 | ||
| 1.3.8.3 Open parking lot, machinery and equipment yard (without roof) | Total area (ha) |
|
|
| >2,5 | ≤2,5 | |
| 1.3.9 | Telecommunication signal transmission cable | Level of importance | International | Provincial | Within province |
|
|
| 1.3.10[23] | Land reclamation project 14. In Note 4(c) Chapter 84 and subheading 84.57: change the phrase "máy nhiều vị trí gia công chuyển dịch" to "máy gia công chuyển dịch đa vị trí." | Area (ha) |
|
| ≥300 | <300 |
|
Note:
- Other technical infrastructure facilities with purposes suitable for the types of facilities listed in Table 1.3 shall use Table 1.3 to determine the level based on the degree of importance or capacity scale.
- Abbreviations in Table 1.3: TCS means Total Capacity calculated for all production lines within the project.
- (*): For parking garages, the number of parking spaces is considered for passenger cars up to 9 seats or trucks under 3,500 kg. In case of mixed parking facilities including both cars and motorcycles, 6 motorcycle parking spaces are equivalent to 1 car parking space.
- Refer to examples of determining the level of technical infrastructure facilities in Appendix III.
Table 1.4 Classification of transportation service facilities (transportation facilities)
| Serial number | Civil construction installation. | Classification criteria | Level of Project | ||||
| Special | I | II | III | IV | |||
| 1.4.1 | Road facilities | ||||||
| 1.4.1.1[24] Expressway For elevated expressways (bridge-type), consider the criteria in this table and structural scale in Section 2.5.1 Table 2 of Appendix II | Design speed (km/h) | >100 | 100 | 80; 60 |
|
| |
| 1.4.1.2[25] Highway For elevated highways (bridge-type), consider the criteria in this table and structural scale in Section 2.5.1 Table 2 of Appendix II | Designed traffic volume (thousand vehicles/day night) or Design speed (km/h) | >30 or >100 | 10 ÷ 30 or 100 | 3 ÷ <10 or 80 | 0,5 ÷ <3 or 60 | <0,5 or ≤40 | |
| 1.4.1.3 Urban roads: - Determine the level of the facility according to all classification criteria, take the highest level determined as the facility level. - For urban roads with total length ≤1,000 m: After determining the facility level according to this table, reduce it by one level but not lower than Level IV. - Elevated urban roads consider the criteria in this table and structural scale in Section 2.5.1 Table 2 of Appendix II | a) Number of lanes |
| ≥8 | 6 | 2; 4 | 1 | |
| b) Design speed (km/h) | ≥80 | 60 | 50 | 40 | 20 ÷ 30 | ||
|
| 1.4.1.4 Traffic intersection (at-grade, at-grade separated) | Designed traffic volume (thousand vehicles/day night) | ≥30 | 10 ÷ <30 | 3 ÷ <10 | <3 |
|
| 1.4.1.5 Other types of roads: a) Rural roads b) Dedicated roads for transportation and travel for one or several organizations or individuals but not including items 1.4.1.1 to 1.4.1.3 (e.g., forestry roads, mining roads, temporary construction roads, roads in recreational areas, resorts, etc.) Note: Test vehicle roads classify according to item 1.4.1.2 c) Bicycle paths; pedestrian paths | Level of importance |
|
|
|
| All scales | |
| 1.4.2 | Railway facilities | ||||||
| 1.4.2.1 Urban railway (including underground railways, surface railways, elevated railways, automated guided monorails and steel wheel trams) | Level of importance | Special class with all scales | |||||
| 1.4.2.2 National railway, 1,435 mm gauge Note: High-speed railway is a type of national railway with design speed of 200 km/h or higher, 1,435 mm gauge, double track, electrified | Design speed (km/h) | ≥200 | 120 ÷ <200 | 80 ÷ <120 | <80 |
| |
| 1.4.2.3 National railway, 1,000 mm gauge; interlined railway, (1,435 - 1,000) mm gauge | Design speed (km/h) |
| 100 ÷ 120 | 60 ÷ <100 | <60 |
| |
| 1.4.2.4[26] Dedicated railway | Design speed (km/h) |
|
| ≥70 | <70 |
| |
| 1.4.3 | Bridge facilities | ||||||
| 1.4.3.1 Floating bridge | Converted traffic volume (vehicles/day night) |
| >3.000 | 1.000 ÷ 3.000 | 700 ÷ <1.000 | 500 ÷ <700 | |
| 1.4.4 | Inland waterway facilities | ||||||
| 1.4.4.1 Inland waterway vessel repair facility (berths, dry docks, ramps, jetties, etc.) | Gross tonnage of vessel (thousand DWT) |
| >30 | 10 ÷ 30 | 5 ÷ <10 | <5 | |
| 1.4.4.2 Inland waterway port, berth | |||||||
| a) Cargo port, berth | Gross tonnage of vessel (thousand DWT) | >5 | 3 ÷ 5 | 1,5 ÷ <3 | 0,75 ÷ <1,5 | <0,75 | |
| b) Passenger port, berth | Largest vessel size (seats) | >500 | 300 ÷ 500 | 100 ÷ <300 | 50 ÷ <100 | <50 | |
| 1.4.4.3 Ferry terminal | Traffic volume (converted vehicles/day night) | >1.500 | 700 ÷ 1.500 | 400 ÷ <700 | 200 ÷ <400 | <200 | |
| 1.4.4.4 Ship lock | Gross tonnage of vessel (thousand DWT) | >3 | 1,5 ÷ 3 | 0,75 ÷ <1,5 | 0,2 ÷ <0,75 | <0,2 | |
| 1.4.4.5[27] Inland waterway width (B) or depth (H) of navigable water: | |||||||
| a) On rivers, lakes, bays and island access routes | Width B (m) or depth H (m) of navigable water | B >120 or H >5 | B = 90 ÷ <120 or H = 4 ÷ 5 | B = 70 ÷ <90 or H = 3 ÷ <4 | B = 50 ÷ <70 or H = 2 ÷ <3 | B <50 or H <2 | |
| b) On canals | Width B (m) or depth H (m) of navigable water | B >70 or H >5 | B = 50 ÷ <70 or H = 4 ÷ 5 | B = 40 ÷ <50 or H = 3 ÷ <4 | B = 30 ÷ <40 or H = 2 ÷ <3 | B <30 or H <2 | |
| 1.4.5 | Marine facilities | ||||||
| 1.4.5.1 Port, cargo handling area, anchorage, storm shelter | |||||||
| a) Cargo and service port berth | Gross tonnage of vessel (thousand DWT) | >70 | >40 ÷ 70 | >20 ÷ 40 | >5 ÷ 20 | ≤5 | |
| b) Passenger terminal | Total tonnage of ships (thousand GT) | >150 | >100 ÷ 150 | >50 ÷ 100 | >30 ÷ 50 | ≤30 | |
| c) Cargo transfer area; anchorage area; typhoon shelter area | Gross tonnage of vessel (thousand DWT) | >70 | >40 ÷ 70 | >20 ÷ 40 | >5 ÷ 20 | ≤5 | |
| 1.4.5.2 Ship repair facilities; ship berthing basins; ship ramps and other ship lifting structures (inclined plane, dock, lift platform, etc.) | Gross tonnage of vessel (thousand DWT) | >70 | >40 ÷ 70 | >20 ÷ 40 | >5 ÷ 20 | ≤5 | |
| 1.4.5.3 Navigational channel | Width of single-lane channel B (m) or Depth of navigable water Hct (m) | B >190 or Hct ≥16 | 140< B ≤190 or 14≤ Hct <16 | 80< B ≤140 or 8≤ Hct <14 | 50< B ≤80 or 5≤ Hct <8 | B ≤50 or Hct <5 | |
| 1.4.5.4 Other maritime works: | |||||||
| a) Marine navigation buoys | Diameter of buoy D (m) | D ≥10 | 5≤ D <10 | 3≤ D <5 | 2≤ D <3 | D <2 | |
| b)[28] Coastal protection works, wave barriers, sand barriers, bank protection structures | Maximum height of structure (m) | >16 | >12 ÷ 16 | >8 ÷ 12 | >5 ÷ 8 | ≤5 | |
| 1.4.6 | ||| 500,000 passengers/year or according to item 1 | ||||||
| 1.4.6.1 Airport Terminal (Main Terminal) | Number of passengers (million passengers/year) | ≥10 | <10 |
|
|
| |
| 1.4.6.2 Airfield | Airport category according to International Civil Aviation Organization (ICAO) regulations | Airport category 4E or higher | Airport category lower than 4E |
|
|
| |
| 1.4.6.3[29] Air traffic control facilities | |||||||
| a) Air Traffic Control Center/Long Range Control Center | Level of importance | Class I with all scales | |||||
| b) Air Traffic Control Tower | International airport | Domestic airport, airfield |
|
|
| ||
| 1.4.6.4 Aircraft hangar | Level of importance | Class I with all scales | |||||
Note:
- For other transportation works with purposes suitable for the types listed in Table 1.4, use Table 1.4 to determine the level based on importance or capacity.
- Refer to examples of determining the level of transportation works in Appendix III.
Table 1.5 Classification of agricultural and rural development works (agricultural and rural development works)
| Serial number | Civil construction installation. | Classification criteria | Level of Project | ||||
| Special | I | II | III | IV | |||
| 1.5.1 | Water conservancy works | ||||||
| 1.5.1.1 Water supply works (for irrigated area) or drainage works (for natural drainage area) | Area (thousand ha) |
| >50 | >10 ÷ 50 | >2 ÷ 10 | ≤2 | |
| 1.5.1.2 Reservoir corresponding to normal water level | Capacity (million m³)3) | >1.000 | >200 ÷ 1.000 | >20 ÷ 200 | ≥3 ÷ 20 | <3 | |
| 1.5.1.3 Raw water supply works for other water-consuming industries | Flow rate (m³/s)3/s) | >20 | >10 ÷ 20 | >2 ÷ 10 | ≤2 |
| |
| 1.5.1.4[30] Pumping station | |||||||
| a) Drainage pumping station, combined irrigation and drainage pumping station | Total flow rate (thousand m³/h)3/h) | ≥360 | 180 ÷ <360 | 72 ÷ <180 | 3,6 ÷ <72 | <3,6 | |
| b) Irrigation pumping station | Total flow rate (thousand m³/h)3/h) |
|
| ≥12 | 2 ÷ <12 | <2 | |
| 1.5.1.5[31] Floodgate For floodgates or spillways, classify according to the level of the dam or spillway | |||||||
| a) For the Mekong Delta region | Clear width (m) |
| >30 | 20 ÷ 30 | 3 ÷ <20 | <3 | |
| b) For other regions | Clear width (m) |
| >20 | 10 ÷ 20 | 1,5 ÷ <10 | <1,5 | |
|
| 1.5.1.6[32] Water conveyance and distribution system | ||||||
| 1.5.1.6.1 Drainage and irrigation system (canals, ditches, creeks, culverts, bridges) | |||||||
| a) For the Mekong Delta region | Flow rate (m³/s)3/s) |
| ≥100 | 50 ÷ <100 | 3 ÷ <50 | <3 | |
| b) For other regions | Flow rate (m³/s)3/s) |
| ≥50 | 20 ÷ <50 | 1,5 ÷ <20 | <1,5 | |
| 1.5.1.6.2 Water supply and irrigation system (canals, ditches, creeks, culverts, bridges) | |||||||
| a) For the Mekong Delta region | Flow rate (m³/s)3/s) |
| ≥40 | 20 ÷ <40 | 1 ÷ < 20 | <1 | |
| b) For other regions | Flow rate (m³/s)3/s) |
| ≥20 | 10 ÷ <20 | 0,5 ÷ <10 | <0,5 | |
| 1.5.1.6.3 Tunnel | |||||||
| a) For the Mekong Delta region | Flow rate (m³/s)3/s) |
| ≥100 | 50 ÷ <100 | 3 ÷ <50 | <3 | |
| b) For other regions | Flow rate (m³/s)3/s) |
| ≥50 | 20 ÷ <50 | 1,5 ÷ <20 | <1,5 | |
| 1.5.1.7[33] Pipeline | Flow rate (m³/s)3/s) |
| >1,8 | 1,5 ÷ ≤1,8 | 0,025 ÷ <1,5 | <0,025 | |
| 1.5.1.8[34] Embankment | Protected area (thousand ha) |
|
| ≥10 | 0,5 ÷ <10 | <0,5 | |
| 1.5.2 | Levee and flood control works: Classify according to the classification decision of the Ministry of Agriculture and Rural Development authorized by the Government under Clause 2 Article 2 of Decree No. 113/2007/ND-CP dated June 28, 2007 detailing and guiding implementation of certain provisions of the Law on Levees. | ||||||
Note:
- For other agricultural and rural development works (NN&PTNT) with purposes suitable for the types listed in Table 1.5, use Table 1.5 to determine the level based on importance or capacity.
- For livestock breeding, crop cultivation, forestry, salt production, aquaculture, new rural construction and other agricultural and rural development works, due to their specific nature, these projects often include various types of works such as civil works, industrial works, transportation works, water conservancy works, technical infrastructure works, etc., therefore, when classifying these works, it will depend on specific cases to apply appropriate classification based on the principles set out in this Circular.
- Refer to examples of determining the level of agricultural and rural development works in Appendix III.
ANNEX II
CLASSIFICATION OF CONSTRUCTION WORKS BY SCALE AND STRUCTURE
(Annexed to Circular No. 06/2021/TT-BXD dated June 30, 2021 issued by the Minister of Construction)
Table 2. Classification of construction works by scale and structure
| Serial number | Type of structure | Classification criteria | Level of Project | ||||
| Special | I | II | III | IV | |||
| 2.1 | 2.1.1 Building, Building-like structure The level of individual residential buildings or individual residential buildings combined with other civilian purposes is determined according to the structural scale specified in this section. Detached houses must not be lower than Level III 2.1.2 Multi-story building with floor (excluding structures in Section 2.2) 2.1.3 Large-span frame structure (excluding structures in Sections 2.3 and 2.5) Example: Welcome gate, bridge house, conveyor bridge, traffic sign support structure, large-span structures at toll stations and similar structures | a) Height (m) | >200 | >75 ÷ 200 | >28 ÷ 75 | >6 ÷ 28 | ≤6 |
| b) Number of floors | >50 | 25 ÷ 50 | 8 ÷ 24 | 2 ÷ 7 | 1 | ||
| c) Total floor area (thousand m²)2) |
| >30 | >10 ÷ 30 | 1 ÷ 10 | <1 | ||
| d) Largest span (m) | >200 | 100 ÷ 200 | 50 ÷ <100 | 15 ÷ <50 | <15 | ||
| đ) Depth below ground (m) |
| >18 | 6 ÷ 18 | <6 |
| ||
| e) Number of underground floors |
| ≥5 | 2 ÷ 4 | 1 |
| ||
| 2.2 | 2.2.1 Column, pier, tower structures in civil, industrial, and transportation works (excluding Section 2.2.3) Example: Monument, advertising column/tower, power transmission tower, chimney, traffic signal column, and similar structures. | Height of structure (m) | >200 | >75 ÷ 200 | >28 ÷ 75 | >6 ÷ 28 | ≤6 |
| 2.2.2 Column, pier, tower structures in technical infrastructure works Example: Antenna column, radio/TV transmission tower; BTS column; street light column, electric pole in lighting systems... | Height of structure (m) | ≥300 | 150 ÷ <300 | 75 ÷ <150 | >45 ÷ <75 | ≤45 | |
| 2.2.3 Lighthouse, beacon | Height of structure (m) |
| ≥58 | 26,5 ÷ <58 | 7,5 ÷ <26,5 | <7,5 | |
| 2.3 | Cable car route | a) Support column height (m) or Height above ground/water surface (m) | >200 | >75 ÷ 200 | >28 ÷ 75 | >6 ÷ 28 | ≤6 |
| b) Maximum distance (m) between two cable supports | ≥1.000 | 500 ÷ <1.000 | 200 ÷ <500 | 50 ÷ <200 | <50 | ||
| 2.4 | Tank, silo structure (Swimming pool, tank/reservoir containing liquids, gases, bulk materials; technical tanks housing machinery/equipment; Silo; Water tower and similar containment structures) For containment structures holding hazardous substances (dangerous to human health, animals, affecting plant life): after determining the work level according to this table, increase by one level, but not lower than Level II and no special level | a) Containment volume (thousand m³)3) |
| >15 | 5 ÷ 15 | 1 ÷ <5 | <1 |
| b) Height of containment structure (m) |
| ≥75 | >28 ÷ <75 | 6 ÷ 28 | <6 | ||
| c) Depth below ground (m) |
| >18 | >6 ÷ 18 | >3 ÷ 6 | ≤3 | ||
| 2.5 | Bridge (in transportation works) | ||||||
| 2.5.1[35] Road bridge: Consider criteria a, b 2.5.2[36] Railway bridge: Consider criteria b, c | a) Largest span (m) | >150 | >100 ÷ 150 | >42 ÷ 100 | >25 ÷ 42 | ≤25 | |
| b) Height of bridge pier (m) | >50 | 30 ÷ 50 | 15 ÷ <30 | 6 ÷ <15 | <6 | ||
| c) Largest span (m) | >100 | 50 ÷ 100 | 25 ÷ <50 | <25 |
| ||
| 2.5.3 Pedestrian and bicycle overpass; rural suspension bridge (for pedestrians, livestock, bicycles, motorcycles, and other simple vehicles; cable-stayed bridge, single span, located on rural roads and bridge width not exceeding 3.5 m) | a) Largest span (m) |
|
| >50 | 25 ÷ 50 | <25 | |
| b) Height of bridge pier or Height from bottom of girder to ground/water surface (m) |
|
| >30 | 15 ÷ 30 | <15 | ||
| 2.6 | 2.6.1 Tunnel (road tunnel, railway tunnel; hydraulic tunnel, hydroelectric tunnel...) This Section does not include the following types of tunnels: underground railway tunnels, technical pipe tunnels in factories (Section 2.10.4.b), and mining tunnels for resource extraction and minerals. | a) Total length (m) | >1.500 | 500 ÷ 1.500 | 100 ÷ <500 | <100 |
|
| b) Cross-sectional area according to the clear dimensions of the tunnel (m2) |
| ≥100 | 30 ÷ <100 | <30 |
| ||
| c) Tunnel shell structure |
|
| Has tunnel shell structure | Does not have tunnel shell structure |
| ||
| 2.6.2 Half-tunnel serving road and rail traffic and preventing soil and rock falls | Total length (m) |
| >1.500 | 500 ÷ 1.500 | 100 ÷ <500 | <100 | |
| 2.7 | Retaining wall, Embankment For retaining walls and embankments with total length ≤500 m: After determining the project level according to this Table, it shall be reduced by one level but not lower than Level IV. | ||||||
| 2.7.1 Retaining wall (soil and rock retaining walls on land, excluding structures in Section 2.9) Retaining walls used in projects under Sections 2.11 and 2.12 shall also consider the criteria of structures in these sections | |||||||
| a) Foundation is rock | Height of retaining wall (m) |
| >25 ÷ 40 | >15 ÷ 25 | >8 ÷ 15 | ≤8 | |
| b) Foundation is sand, gravel, clay in hard and semi-hard states |
|
| >12 ÷ 20 | >5 ÷ 12 | ≤5 | ||
| c) Foundation is saturated clay in plastic state |
|
| >10 ÷ 15 | >4 ÷ 10 | ≤4 | ||
| 2.7.2 Slope protection embankment (river, lake) used in various construction investment projects but excluding structures in Sections 2.9 and 2.11.2 | Height of slope protection (m) or Depth of water level (m) |
| >8 | >5 ÷ 8 | >3 ÷ 5 | ≤3 | |
| 2.8 | Dams and other hydraulic structures subject to pressure | ||||||
| 2.8.1 Earth dams, earth-rock dams of various types | |||||||
| a) Foundation is rock | Height of dam (m) | >100 | >70 ÷ 100 | >25 ÷ 70 | >10 ÷ 25 | ≤10 | |
| b) Foundation is sand, gravel, clay in hard and semi-hard states |
| >35 ÷ 75 | >15 ÷ 35 | >8 ÷ 15 | ≤8 | ||
| c) Foundation is saturated clay in plastic state |
|
| >15 ÷ 25 | >5 ÷ 15 | ≤5 | ||
| 2.8.2 Concrete dams, reinforced concrete dams of various types and other hydraulic structures subject to pressure | |||||||
| a) Foundation is rock | Height of dam (m) | >100 | >60 ÷ 100 | >25 ÷ 60 | >10 ÷ 25 | ≤10 | |
| b) Foundation is sand, gravel, clay in hard and semi-hard states |
| >25 ÷ 50 | >10 ÷ 25 | >5 ÷ 10 | ≤5 | ||
| c) Foundation is saturated clay in plastic state |
|
| >10 ÷ 20 | >5 ÷ 10 | ≤5 | ||
| 2.9 | Surface reinforcement structure of sloping roof (brick/stone cladding, concrete pouring or other solutions except for soil retaining walls in Section 2.7) | Height measured from base to top of sloping roof (m) |
|
|
| >30 | ≤30 |
| 2.10 | Pipeline/culvert For pipelines/culverts with total length ≤1,000 m: After determining the project level according to this Table, it shall be reduced by one level but not lower than Level IV | ||||||
| 2.10.1 Water supply pipeline (raw water or clean water) | Inner diameter of pipeline (mm) or Cross-sectional area inside the pipeline (m2) |
| ≥800 or ≥0,51 | 400 ÷ <800 or 0,13 ÷ <0,51 | 150 ÷ <400 or 0,02 ÷ <0,13 | <150 or <0,02 | |
| 2.10.2 Stormwater drainage culvert, combined culvert |
| ≥2,000 or ≥3,14 | 1,500 ÷ <2,000 or 1,77 ÷ <3,14 | 600 ÷ <1,500 or 0,28 ÷ <1,77 | <600 or <0,28 | ||
| 2.10.3 Sewage drainage culvert |
| ≥1,000 or ≥0,79 | 600 ÷ <1,000 or 0,28 ÷ <0,79 | 200 ÷ <600 or 0,03 ÷ <0,28 | <200 or <0,03 | ||
| 2.10.4 Cable culvert, trench, technical pipe (used in: telecommunications works; technical pipe tunnels in factories) For cable culverts, trenches, technical pipes with total length ≤1,000 m: After determining the project level according to this Table, it shall be reduced by one level but not lower than Level IV | |||||||
| a) Technical trench, cable culvert | Clear width (m) |
|
|
| >0,7 | ≤0,7 | |
| b) Technical pipe (Technical pipe tunnels in factories do not exceed Level I) | Clear width (m) | >7 | >3 ÷ 7 | ≤3 |
|
| |
| 2.10.5 Oil and gas pipeline | a) Inner diameter of pipeline (mm) |
| ≥300 | <300 |
|
| |
| b) Location |
| Undersea | Under river | On land |
| ||
| 2.11[37] | Seaport | ||||||
| 2.11.1 Coastal works: Seaport wharf; anchorage and loading areas, typhoon shelters; seaport bridge. | a) Wharf height (m) | >20 | >15 ÷ 20 | >10 ÷ 15 | >5 ÷ 10 | ≤5 | |
| b) Seaport wharf area (thousand m2) |
| ≥20 | >10 ÷ <20 | 1 ÷ 10 | <1 | ||
| 2.11.2 Coastal and estuary regulation structures (wave barriers, sand barriers, flow direction embankments, shore protection embankments...) 2.11.3 Ferry terminals, specialized ports, offshore facilities (floating docks, pneumatic embankments, multifunctional floating ports...) | Maximum height of structure (m) | >16 | >12 ÷ 16 | >8 ÷ 12 | >5 ÷ 8 | ≤5 | |
| 2.12[38] | Inland waterway port | ||||||
| 2.12.1 Ports, cargo and passenger terminals, inland waterway bridges; 2.12.2 River regulation structures | a) Wharf height (m) or structure height (m) |
| >8 | >5 ÷ 8 | >3 ÷ 5 | ≤3 | |
| b) Wharf area (thousand m2) |
| ≥10 | 5 ÷ <10 | 1 ÷ <5 | <1 | ||
| 2.13 | Berth | Water depth (m) | >20 | >15 ÷ 20 | >10 ÷ 15 | >5 ÷ 10 | ≤5 |
| 2.14 | Small-scale miscellaneous structures | ||||||
| 2.14.1 For installing dangerous amusement rides affecting community safety (roller coasters, steel towers, water slides, steel structures supporting ride equipment, etc.) | Total height including the structure and attached technological equipment (m) |
|
| >15 | ≤15 |
| |
| 2.14.2 Fences, walls; guardrails and similar structures | Height (m) |
|
|
| >6 | ≤6 | |
| 2.14.3 Brick, stone, or concrete block structures or concrete panels for small structures such as flower beds, monuments, graves, survey markers (on land)... and other small-scale structures: Level IV. | |||||||
Note:
1. Determining the project level based on the type and scale of the structure is carried out in the following sequence:
a) Based on the characteristics of the project, determine the type of structure according to the Sections in Table 2;
b) Determine the project level according to all classification criteria specified for the determined type of structure at point a (above). The highest level obtained shall be the project level.
2. Some terms used in the classification criteria of Table 2 are understood as follows:
a) Building, Building-like structure: A constructed structure in a cubic form, with parts above ground, composed of load-bearing structures, enclosures (which may or may not exist), and a roof.
b) Ground level or project ground level: Elevation taken according to approved planning (in areas without planning, take according to design elevation or current ground level with existing structures).
c) Above-ground floor: A floor whose floor level is higher than or equal to the project ground level.
d) Basement floor (or underground floor): A floor where more than half of its height lies below the project ground level.
đ) Half-basement floor (or half-underground floor): A floor where half of its height lies above or at the project ground level.
e) Mezzanine floor: An intermediate floor between floors, where its floor (mezzanine floor) lies between the floors with primary functions or between the roof and the floor directly below with primary function; the mezzanine floor has a smaller floor area than the floor directly below with primary function.
g) Attic floor: A floor within the space of a pitched roof, where the entire or part of its vertical surface is formed by the inclined or folded roof surface, and where standing walls (if any) do not exceed 1.5 m above the floor level.
h)||| Top floor or attic top floor: The topmost floor of a building used for enclosing stairwells, elevator shafts, building equipment (if any), and for access to the roof and rescue operations.
i) Technical floor: A floor used for arranging building technical equipment (may combine with emergency shelter spaces in the technical floor).
k) Underground depth: Depth measured from the project ground level to the upper surface of the deepest basement floor.
l) Largest span of building/structure: The maximum distance between the centers of adjacent columns (pillars, walls) used to support horizontal structures (beams, slab floors without beams, roof trusses, bridge trusses, cable-stayed structures...). For frame structures, the span value is taken as 50% of the value specified in Table 2.
m) Total floor area of the building/project: The total floor area of all floors, including basement floors, semi-basement floors, mezzanine floors, technical floors, attic floors, and penthouse floors. The floor area of a floor is the built-up floor area of that floor, including the enclosing walls (or shared walls belonging to the building) and the plan area of balconies, terraces, staircases, elevator shafts, technical boxes, chimneys.
3. Method of determination Height of the project/structure:
a) For projects/structures under item 2.1: Height is measured from ground level to the highest point of the structure (including the penthouse or pitched roof). For projects/structures placed on ground with different ground levels, height is measured from the lowest ground level. If there are technical equipment such as antenna towers, lightning rods, solar energy devices, metal water tanks, etc., at the top of the structure, the heights of these devices are not included in the height of the structure.
b) For structures under item 2.2: The height of the structure is measured from ground level to the highest point of the structure. For structures with different ground levels, height is measured from the lowest ground level.
The height of the structure in certain specific cases is defined as follows:
+ For structures supporting equipment under item 2.2.1: The height of the structure is calculated as the sum of the height of the supporting column/tower/pole and the equipment placed on the supporting column/tower/pole;
+ For structures installed on existing buildings under item 2.2.2: The height of the structure is measured from the base to the top of the installed structure (for example: a BTS tower 12 meters long, installed on the roof of a three-story existing building, the height of this BTS tower structure is calculated as 12 meters).
c) For structures under item 2.3:
- Height of supporting column: The distance from the top surface of the column foundation (supporting footing) to the top of the column;
- Height above ground/water level: The distance from the cable-stayed structure to the ground or water surface (average annual water level) below;
d) For structures containing items under item 2.4: Height of the containing structure is determined similarly to item 2.1
đ) For structures under item 2.5: Height of bridge pier is the distance from the top surface of the pier foundation (supporting footing) to the top of the pier;
e) For retaining walls and revetments under item 2.7:
- Height of wall: Measured from the lower ground surface to the top of the retaining wall;
- Height of revetment: Calculated as the sum of the sub-water and super-water parts of the structure.
g) For structures under item 2.8:
- Structures under item 2.8.1: Height of dam is measured from the lowest foundation surface after excavation (excluding the toe height) to the top of the dam;
- Structures under item 2.8.2: Height of dam is measured from the lowest toe of the dam to the top of the dam.
h) For structures under item 2.14.2: Height is measured from the ground to the top of the structure/project.
4. Method of determination Number of high floors of the project under item 2.1:
Number of high floors of the project: The total of all floors above ground and half/basement floors but excluding the attic floor. In some specific cases, the penthouse and mezzanine floors are not counted in the number of high floors:
- The penthouse is not counted in the number of high floors of the project when the penthouse roof area does not exceed 30% of the main roof area.
- Mezzanine floors are not counted in the number of high floors of the project in the following cases:
+ Single-family houses, single-family houses combined with other residential purposes: A mezzanine floor with an area not exceeding 65% of the area of the main-use floor directly below it, and only one mezzanine floor can be excluded from the number of high floors of the house.
+ Apartment buildings, mixed-use apartment buildings: Only one mezzanine floor is not counted in the number of high floors of the project when the mezzanine floor is solely used for technical areas (such as the bottom floor of a swimming pool, generator floor, or other equipment floors), with an area not exceeding 10% of the area of the floor directly below it and not exceeding 300 square meters.2.
+ Other projects: Mezzanine floors solely used for technical areas, with an area not exceeding 10% of the area of the main-use floor directly below it.
5. For open drainage channels and ditches (infrastructure works): Determine the project grade according to the reinforced structure of the channel bank or channel slope (choose the appropriate type according to item 2.7 or item 2.9 in Table 2).
6. Refer to examples of determining the project grade according to the type and scale of the structure in Appendix III.
ANNEX III
EXAMPLES OF DETERMINING PROJECT GRADE
(Annexed to Circular No. 06/2021/TT-BXD dated June 30, 2021 issued by the Minister of Construction)
3.1 Example 1: Civil use project (civil construction project) - High School A
The investment project "High School A" has a capacity of 1,500 students. The project includes the following works:
- Building A1 (Administrative Building): 8 stories high, total floor area 4,000 m²2;
- Building A2 (Classroom Building): 6 stories high, total floor area 4,650 m²2;
- Building A3 (Classroom Building): 4 stories high, total floor area 4,000 m²2;
- Building A4 (Classroom Building): 5 stories high, total floor area 5,000 m²2;
- Building A5 (Physical Education Building used for indoor training and competition sports, also used for large gatherings and meetings during school events): 2 stories high (18 m), with a 200-seat grandstand, total floor area 2,400 m²2, largest structural span 30 m, total capacity (when organizing events) 750 people;
- Building A6 (Dormitory): 5 stories high, total floor area 3,000 m²2;
- Building A7 (Cafeteria): 2 stories high, total floor area 600 m²2;
- Garden: Area 2 hectares;
- Internal road system within the school: One lane for walking, bicycles, motorcycles, and cars;
- Security fence: 3 meters high;
- Guard House: 1 story high, floor area 12 m²2.
The project grade is determined as follows:
a) Determination of the grade of the main complex of buildings:
High School A has a main complex of buildings used for educational purposes (including buildings from A1 to A5). The project grade based on capacity is determined according to the provisions at Clause 3, Article 2 of this Circular: Corresponding to item 1.1.1.3 of Table 1.1 in Appendix I and with a capacity of 1,500 students, High School A has a project grade based on capacity of Level II.
b) Determination of the grades of buildings within High School A:
- House A1: Not listed in Appendix I Table 1.1, therefore according to the provisions at Clause 2, Article 2 of this Circular, the level of the construction project is determined based on type and structural scale. According to Appendix II Table 2, this project corresponds to item 2.1.1; the level is determined based on total floor area: Level III, based on number of floors: Level II. The level of the House A1 construction project is Level II (the highest level determined).
- House A2: The method for determining the level is similar to that for House A1. The level of the House A2 construction project determined is: Class III.
- House A3: The method for determining the level is similar to that for House A1. The level of the House A3 construction project determined is: Class III.
- House A4: The method for determining the level is similar to that for House A1. The level of the House A4 construction project determined is: Class III.
- House A5: This project has its own capacity scale, therefore the level of the construction project is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
+ Determining the level based on capacity scale: Corresponds to item 1.1.3.2 in Appendix I Table 1.1 (type of sports facility): Level III; corresponds to item 1.1.4.1 in Appendix I Table 1.1 (type of facility with concentrated large crowds): Level II. The highest level of the project determined based on capacity scale: Level II;
+ Determining the level based on structural scale: Corresponds to item 2.1.1 in Appendix II Table 2; the level is determined based on height: Level III; based on number of floors: Level III; based on total floor area: Level III, based on largest span: Level III. The highest level of the project determined based on structural scale: Level III;
Therefore, the level of the House A5 construction project is Level II (the highest level determined from capacity scale and structural scale).
- House A6: The method for determining the level is similar to that for House A1. The level of the House A6 construction project determined is: Class III.
- House A7: The method for determining the level is similar to that for House A1. The level of the House A7 construction project determined is: Class III.
- Garden: Corresponds to item 1.3.4 in Appendix I Table 1.3, the level of the construction project is determined based on total floor area as Level IV.
- Internal school road system: Is a dedicated road specified in item 1.4.1.5 of Appendix I Table 1.4. The level of the construction project determined is: Level IV.
- Protective fence: Not listed in Appendix I Table 1.1, therefore according to the provisions at Clause 2, Article 2 of this Circular, the level of the construction project is determined based on type and structural scale. According to Appendix II Table 2, this project corresponds to item 2.14.2; the level of the construction project is determined based on height as Level IV.
- Guard house: The method for determining the level is similar to that for House A1. The level of the guard house construction project determined is: Level IV.
c) Applying the level of the construction project in managing investment construction activities:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: School A High School has a main set of projects, according to point c clause 2 Article 3 of this Circular, applying the level of the main set of projects (determined in part a Example) is Level II.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular; example classifying the construction activity capability of organizations and individuals participating in construction activities as follows:
+ In case the scope of implementation covers the entire set of projects: According to point c clause 3 Article 3 of this Circular, applying the level of the main set of projects (determined in part a Example) is Level II;
+ In case the scope of implementation covers some projects within the construction project: According to point b clause 3 Article 3 of this Circular, applying the level of each project under consideration (determined in part b Example); for example: House A1 uses the level of the construction project as Level II to apply; House A3 uses Level III to apply; Garden uses Level IV to apply;
+ In case the scope of implementation covers a single independent project: According to point a clause 3 Article 3 of this Circular, applying the level of the implemented project (determined in part b Example); for example: House A2 uses Level III to apply; similarly, if organizations or individuals only participate in implementing the protective fence or guard house, then use the level of the construction project as Level IV to apply.
3.2 Example 2: Civil Construction Project - Q General Hospital
The "Q General Hospital" construction investment project has a scale of 450 beds. The project includes the following constructions:
- Building Q1 (Office, Training and Research Center of the hospital): 9 floors high, total floor area 8,000 m²2;
- Building Q2 (Outpatient and Laboratory Center): 3 floors high, total floor area 2,500 m²2;
- Building Q3 (Emergency and Surgery): 2 floors high, total floor area 2,000 m²2;
- Building Q4 (Departments and Post-Surgery Treatment Areas): 22 floors high, total floor area 22,000 m²2;
- Building Q5 (Food Processing Area): 2 floors high, total floor area 1,000 m²2;
- Building Q6 (Cafeteria): 2 floors high, total floor area 600 m²2;
- Building Q7 (Morgue): 1 floor high, floor area 500 m²2;
- Building Q8 (Funeral Home): 1 floor high, floor area 600 m²2;
- Wastewater Treatment Plant: 1,500 m3/day-night;
- Solid Waste Incineration Plant: Capacity 5 tons/day-night;
- Ornamental Garden and Landscape System;
- Outdoor Parking Lot: 5,000 m²2;
- Internal Hospital Road System: One lane, for motorcycles and cars;
- Protective Wall: Height 4.5 meters;
- Guard Houses (4 houses): Each house is one floor high, area 12 m²2;
- Power System: Power lines and transformer station, voltage less than 35 kV;
- Water Supply System (Water Tank and Pump Station): Capacity 1,500 m³3/day-night;
- Sewage Drainage System: Pipe diameter D = 450 mm, length 900 m.
The project grade is determined as follows:
a) Determination of the grade of the main complex of buildings:
Q General Hospital has a main set of projects used for medical examination and treatment purposes (including projects Q1, Q2, Q3, Q4, Q7). The level of the construction project based on capacity scale is determined according to the provisions at Clause 3, Article 2 of this Circular: Corresponding to item 1.1.2.1 in Appendix I Table 1.1 and with a scale of 450 beds, Q General Hospital has a construction project level based on capacity scale as Level II.
b) Determining the levels of projects within Q General Hospital:
- Building Q1: Not listed in Appendix I Table 1.1, therefore according to the provisions at Clause 2, Article 2 of this Circular, the level of the construction project is determined based on type and structural scale. According to Appendix II Table 2, this project corresponds to item 2.1.1; the level of the Q1 construction project determined is Level II.
- Building Q2: The method for determining the level is similar to that for building Q1. The level of the Q2 construction project determined is: Class III.
- Building Q3: The method for determining the level is similar to that for building Q1. The level of the Q3 construction project determined is: Class III.
- Building Q4: The method for determining the level is similar to that for building Q1. The level of the Q4 construction project determined is: Level II.
- Building Q5: The method for determining the level is similar to that for building Q1. The level of the Q5 construction project determined is: Class III.
- Building Q6: The method for determining the level is similar to that for building Q1. The level of the Q6 construction project determined is: Class III.
- Building Q7: The method for determining the level is similar to that for building Q1. The level of the Q7 construction project determined is: Level IV.
- House Q8: The mortuary building is included in Table 1.3 Appendix I and is defined according to its level of importance. In this case, the construction level is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
+ Determining the level based on the degree of importance: Corresponding to item 1.3.6 Table 1.3 Appendix I, the construction level determined is Level II;
+ Determining the level based on structural scale: Corresponding to item 2.1.1 Table 2 Appendix II, the construction level determined is Level IV;
Therefore, the construction level of House Q8 determined is Level II (the highest level determined from the degree of importance and structural scale).
- Wastewater Treatment Station: Corresponding to item 1.3.2.3 Table 1.3 Appendix I, the construction level determined is Level III.
- Solid Waste Treatment Station: Corresponding to item 1.3.3.1.b Table 1.3 Appendix I, the construction level determined is Level III.
- Outdoor Parking Lot: Corresponding to item 1.3.8.3 Table 1.3 Appendix I, the construction level determined is Level IV.
- Water Supply System (water reservoir and pump station): Corresponding to item 1.3.1.2 Table 1.3 Appendix I; the construction level determined is: Class III.
- Sewage Drainage System: Not included in Table 1.3 Appendix I, therefore according to the provisions at Clause 2, Article 2 of this Circular, the construction level is determined based on type and structural scale. According to Table 2 Appendix II, this project corresponds to item 2.10.3; the construction level determined based on pipe diameter is Level III but the total length of the drainage system is less than 1,000 meters, so the construction level is reduced by one level to Level IV.
- Power Distribution System: Corresponding to item 1.2.5.11 Table 1.2 Appendix I, the construction level determined is Level IV.
- Determining the levels of Greenery and Garden Systems, Internal Road Systems, Fence Walls, and Guard Houses see Example 1 of this Appendix.
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 1 of this Appendix.
3.3 Example 3: Civil Construction Project - Complex X
The investment and construction project "Complex X" on Plot A within an urban area with complete technical infrastructure. Complex X includes the following projects:
- Building X1 (Residential Building): 15 floors high, 60 meters tall, total floor area 12,000 square meters2;
- Building X2 (Office Building): 18 floors high, 72 meters tall, total floor area 15,000 square meters2;
- Building X3 (Mixed-use Commercial and Residential Building): 25 floors high, 100 meters tall, total floor area 22,000 square meters2;
- Central Garden between buildings: Area 1,000 square meters2.
The project grade is determined as follows:
a) Determining the construction levels of projects in Complex X:
Complex X has several independent main projects including Buildings X1, X2, and X3, the construction level is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
- Building X1: Not included in Table 1.1 Appendix I of this Circular, therefore the construction level is determined based on type and structural scale. According to Table 2 Appendix II, this project corresponds to item 2.1.1; the construction level of Building X1 determined is Level II.
- Building X2: The construction level is determined similarly to Building X1. The construction level of Building X2 determined is: Level II.
- Building X3: The construction level is determined similarly to Building X1. The construction level of Building X3 determined is: Class I.
- Determining the construction level of the Central Garden see Example 1 of this Appendix.
b) Applying the construction level in managing investment and construction activities:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: Complex X has several independent main projects, according to point b clause 2 Article 3 of this Circular, apply the level of the main project with the highest level (Building X3, determined in part a of this example) is Primary Level.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular: The method of determination see Example 1 of this Appendix.
3.4 Example 4: Industrial Construction Project - Cement Plant A
The construction project "Cement Plant A" with a designed capacity of 2 million tons of cement per year. Raw materials inputs such as clay, limestone, coal, additives are supplied by other companies. The project includes the following projects:
- Projects belonging to the main production line (cement production line): Coal grinding house, Raw material grinding house, Powder silo, Transport from powder silo to heat exchanger tower, Heat exchanger tower, Rotary kiln columns, Clinker cooling house, Clinker silo, Transport from clinker silo to cement grinding house, Cement grinding house, Cement silo...
- Other independent projects in the project: Material warehouse; Mechanical workshop; Control house; Medical station; Drainage channel; Cable tunnel; Weighing station and other projects.
The project grade is determined as follows:
a) Determining the construction level of the main production line:
Cement Plant A project has a main production line, the construction level is determined according to the provisions at Clause 3, Article 2 of this Circular. This production line is determined based on production capacity, corresponding to item 1.2.1.2 Table 1.2 Appendix I for cement plants, the construction level of the main production line is Primary Level.
b) Determining the construction level of projects in Cement Plant A:
Industrial projects in the plant are determined based on the provisions at Clause 2, Article 2 of this Circular. Except for the Cement Grinding House which is included in Table 1.2 Appendix I and determined based on production capacity and structural scale, the remaining projects not included in Table 1.2 Appendix I, therefore the construction level is determined based on type and structural scale using Table 2 Appendix II of this Circular. Below are some examples:
- Coal Warehouse (round warehouse with a closed roof, diameter 120 meters): The project corresponds to item 2.1.1 Table 2 Appendix II; determined based on total floor area 11,300 square meters: Level II, based on the largest span structure 120 meters: Level I, based on height 20 meters: Level III. The construction level of the Coal Warehouse:2: Level II, based on the largest span structure 120 meters: Level I, based on height 20 meters: Level III. The construction level of the Coal Warehouse: Class I (the highest level determined).
- Conveyor Belt CC (transports coal from the Coal Warehouse to the Coal Grinding House: Box frame structure supported by columns; cross-section size of the box frame: 3 meters x 3 meters; column height above ground: from 9 meters to 24 meters; maximum span between two column centers: 30 meters): The project corresponds to item 2.1.3 Table 2 Appendix II; determined based on height H = 12 ÷ 27 meters (total height of columns and conveyor belt): Level III, based on span L = 30 meters: Level III. The construction level of the Coal Conveyor Belt: Class III (the highest level determined).
- Cement Silo 1 (Capacity V = 10,000 cubic meters; height H = 45 meters; diameter D = 20 meters): The project corresponds to group 2.4 Table 2 Appendix II; determined based on capacity: Level II, based on height: Level II. The construction level of Cement Silo 1:3; height H = 45 meters; diameter D = 20 meters): The project corresponds to group 2.4 Table 2 Appendix II; determined based on capacity: Level II, based on height: Level II. The construction level of Cement Silo 1: Level II (the highest level determined).
- Heat Exchanger Tower (8 floors high; height 82 meters; total floor area 5,400 square meters2): The project corresponds to item 2.1.2 Table 2 Appendix II; determined based on height: Level I, based on number of floors: Level II, based on total floor area: Level III. The construction level of the Heat Exchanger Tower: Class I (the highest level determined).
- Support column for rotary kiln (reinforced concrete pile foundation support system for rotary kiln with a diameter of 5 m. Height of the column itself: H1 = 9 m; height including equipment: H = 9 m + 5 m = 14 m): The corresponding project according to item 2.2.1 Table 2 Appendix II, the level of the project determined based on the structural height is Level III.
- Chim khói (reinforced concrete chimney with a height of 120 m): The corresponding project according to item 2.2.1 Table 2 Appendix II, the level of the project determined based on the height is Primary Level.
- Weighing station (vehicle weighing station): Structure in the form of an underground reinforced concrete tank, weighing equipment placed inside the tank; dimensions of the tank (Length x Width x Depth) = (5 m x 14 m x 4.5 m). According to Table 2 Appendix II, the corresponding project is item 2.4; the level determined based on the depth underground is Level III, according to the volume contained (V = 315 m3): Level IV. The level of the Weighing Station: Class III (the highest level determined).
- Method for determining the level of civil projects such as Control Room, Health Station, and other projects see Example 1 of this Appendix.
- Method for determining the level of technical infrastructure projects such as Machinery Parking Area, Wastewater Treatment Plant, Water Supply System, and other projects see Example 2 of this Appendix.
c) Applying the level of the construction project in managing investment construction activities:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: Project Cement Factory A has a main production line, according to point c clause 2 Article 3 of this Circular, apply the level of the main production line (already determined in item a of this example) is Primary Level.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular: Example of classification of construction capacity of organizations and individuals participating in construction activities as follows:
+ In case the scope of implementation covers the entire main production line: According to point c clause 3 Article 3 of this Circular, apply the level of the main production line (already determined in item a of this example) is Class I;
+ In case the scope of implementation covers an independent project (part of the main production line or another independent project within the project) or several projects within the construction investment project: Determination method see Example 1 of this Appendix.
3.5 Example 5 - Industrial Construction - Hydropower Plant B
The "Hydropower Plant B" investment and construction project has a designed capacity of 30 MW. The project includes the following works:
- Reservoir: Volume of 10 million m3;
- The "Headworks Complex" includes the following works: Main dam (height 30 m, concrete structure on rock foundation), Spillway, Auxiliary dam,...
- The "Power Line Complex" includes the following works: Hydropower plant (capacity 30 MW), Intake gate, Pressure tunnel, Surge tower, Penstock, Outlet gate, Tailrace channel,...
- Other works include: Transmission line and substation (voltage 110 kV), Internal road, management and control building (4 floors high, without basement), administrative building, guard house, gate, fence,...
- Temporary and auxiliary works for construction include: Cofferdam (height 7 m, earthfill structure), Diversion channel, Diversion culvert, temporary roads for construction,...
The project grade is determined as follows:
a) Determination of the grade of the main complex of buildings:
Hydropower Plant B belongs to a project with a combination of main works (including Reservoir, Main Dam, Hydropower Plant). The level of the combination of main works is determined according to the provisions at Clause 3, Article 2 of this Circular. According to the provisions at point b item 1.2.5.3 Table 1.2 Appendix I, the level of the combination of works is determined as follows:
- Reservoir: Corresponding to point b item 1.2.5.3 Table 1.2 Appendix I, the level of the work is determined based on the volume is Level III;
- Main Dam: Corresponding to point c item 1.2.5.3 Table 1.2 Appendix I, the level of the work is determined based on the height of the concrete dam on rock foundation is Level II;
- Hydropower Plant: Corresponding to point a item 1.2.5.3 Table 1.2 Appendix I, the level of the work is determined based on the capacity is Level III.
Therefore, the level of the combination of main works of Hydropower Plant B is Level II (based on the level of the main dam).
b) Determining the level of works belonging to Hydropower Plant B:
- Works of reservoir, main dam, power plant have been determined in item a of this example;
- Other works within the power plant are determined according to the provisions at Clause 2, Article 2 of this Circular. Below are some examples:
+ Transmission line and substation: Corresponding to Item 1.2.5.11 Table 1.2 Appendix I, the level of the work is determined based on voltage is Level II;
+ Internal road: Determination method see Example 1 of this Appendix;
+ Management and control building: This work is not included in Table 1.1 Appendix I Circular, therefore the level of the work is determined based on type and scale of the structure. According to Table 2 Appendix II, this work corresponds to item 2.1.1; the determined level is Level III.
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 1 of this Appendix.
3.6 Example 6: Industrial Construction - Mechanical Factory C
The "Mechanical Factory C" investment and construction project aims to produce small mechanical products according to orders from other enterprises. Products of this factory are quite diverse and depend on customer requirements, so at the time of project planning, specific product types and production volumes cannot be determined. The project includes the following works:
- Warehouse: One floor high, largest span 24 m, total floor area 6,000 m2, height from ground outside the building to the top of the roof 12 m;
- Main production building (houses machines and assembly lines: lathe, press, welding...): Industrial building one floor high, three spans, largest span 60 m, total building area 10,000 m2, building height 18 m (from ground outside the building to the top of the roof);
- Office building (used for offices, dining hall, workers' rest rooms...);
- Parking lot (concrete parking lot, for materials and machinery): area 1 hectare; and other works such as Guard House, Fence, Substation...
The project grade is determined as follows:
a) Determining the level of the main work:
Mechanical Factory C has one main work which is the Main Production Building. The level of the main work is determined according to the provisions at Clause 2, Article 2 of this Circular are Level II (the level of the Main Production Building is determined in item b of this example).
b) Determining the level of works belonging to Mechanical Factory C:
- Works of warehouse and main production building in Mechanical Factory C are determined according to the provisions at Clause 2, Article 2 of this Circular. These works do not have significant importance or capacity levels and are not included in Table 1.2 Appendix I of this Circular, therefore their levels are determined based on type and scale of the structure.
+ Warehouse: According to Table 2 Appendix II, this work corresponds to item 2.1.1; the level is determined based on height: Level III, based on number of floors: Level IV, based on total floor area: Level III, based on largest span: Level III. The level of the Warehouse: Class III (the highest level determined).
+ Main Production Building: According to Table 2 Appendix II, this work corresponds to item 2.1.1; the level is determined based on height: Level III, based on number of floors: Level IV, based on total floor area: Level III, based on largest span: Level II. The level of the Main Production Building: Level II (the highest level determined).
- Method for determining the level of works such as Office Building, Parking Lot, Guard House, Fence, Substation see the relevant provisions Examples 1 to Example 4 of this Appendix.
c) Applying the level of the construction project in managing investment construction activities:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: Factory Machinery C has a main project which is the Main Production Facility, according to point a clause 2 Article 3 of this Circular, apply the level of the main project (determined at point a of this Example) as Level II.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular: The method of determination see Example 1 of this Appendix.
3.7 Example 7: Engineering Infrastructure Project (EIP) - Hanoi TV Tower
The construction project "Hanoi TV Tower" is 600 meters high. The project includes the following works:
- Main Tower: Height 600 meters;
- P1 (Outdoor Parking Lot): Area 1 hectare;
- P2 (Green Space with Trees): Area 5 hectares.
The project grade is determined as follows:
a) Determining the level of the main work:
The "Hanoi TV Tower" project has a main work being the Main Tower and auxiliary works. Determine the level of the main work according to the provisions at Clause 2, Article 2 of this Circular. The Main Tower does not have a degree of importance or capacity scale, therefore the level of the work is determined based on type and structural scale. The determined level is special level (the level of the Main Tower is determined at point b of this Example).
b) Determine the levels of works belonging to the Hanoi TV Tower project:
- Main Tower: According to Table 2 Appendix II, this work corresponds to item 2.2.2; the determined level of the work is based on height as special level.
- Work P1: Level IV (method for determining the level of the work see Example 1 of this Appendix).
- Work P2: Class III (method for determining the level of the work see Example 1 of this Appendix).
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 6 of this Appendix.
3.8 Example 8: Engineering Infrastructure Project (EIP) - Water Plant A
The investment construction project "Water Plant A" has a capacity of 50,000 cubic meters/day-night to supply water for a residential area. The project includes the following works:3- A1 (Raw Water Pipeline from Source to Plant): Inner diameter D = 1,000 mm, length 5,000 meters;
- A2 (Water Storage and Treatment Tank): Volume 12,000 cubic meters, half above ground and half underground, underground depth 5 meters, height 3 meters;
- A3 (Backup Clean Water Storage Tank): Volume 3,000 cubic meters;3- A4 (Clean Water Pumping Station): Capacity 70,000 cubic meters/day-night placed in a building 1 story high, height 8 meters, total floor area 1,000 square meters;
- A5 (Main Water Supply Pipeline): Inner diameter D = 800 mm, length 10,000 meters;3- A4 (Clean Water Pumping Station): Capacity 70,000 cubic meters/day-night placed in a building 1 story high, height 8 meters, total floor area 1,000 square meters;
- A6 (Branch Water Supply Pipeline): Inner diameter D = 600 mm, length 15,000 meters;3- A7 (Water Distribution Pipeline): Diameter D = 125 mm; and other works.2;
The Water Plant A project has a main production line directly serving the extraction, production, and supply of water (including works from A1 to A7). The level of the work based on capacity scale is determined according to the provisions at
: Corresponding to item 1.3.1.1 Table 1.3 Appendix I and with a clean water supply capacity of 50,000 cubic meters/day-night, Water Plant A has a level of work based on capacity scale as
b) Determine the levels of works belonging to the Water Plant A project:
The project grade is determined as follows:
a) Determining the construction level of the main production line:
Works belonging to Water Plant A determine their level according to the provisions at Clause 3, Article 2 of this Circular- Work A1: There is no capacity scale (not in Table 1.3 Appendix I), therefore the level of the work is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to item 2.10.1; the determined level of work A1 is3- Work A2: There is no capacity scale (not in Table 1.3 Appendix I), therefore the level of the work is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to group 2.4; determine the level of the work based on storage volume: Level II, based on underground depth: Level III, based on height: Level IV. The level of work A2: Primary Level.
- Work A3: The method for determining the level is similar to that for work A2. The determined level of work A3 is:
- Work A4: This work has a capacity scale, the level is determined as follows: Clause 2, Article 2 of this Circular as follows:
+ Determining the level based on capacity scale: Corresponding to item 1.3.1.2 Table 1.3 Appendix I, the determined level of the work is Level I; Primary Level.
+ Determining the level based on structural scale: Corresponding to item 2.1.1 Table 2 Appendix II, determine the level of the work based on number of floors: Level IV, based on height: Level III, based on total floor area: Level III. The highest level determined based on structural scale: Level III. Level II (the highest level determined).
Therefore, the level of work A4 is Class III.
- Work A5: The method for determining the level is similar to that for work A1. The determined level of work A5 is:
- Work A6: The method for determining the level is similar to that for work A1. The determined level of work A6 is:
- Work A7: The method for determining the level is similar to that for work A1. The determined level of work A7 is:
Example 4 of this Appendix Primary Level (the highest level determined from capacity scale and structural scale).
3.9 Example 9: Engineering Infrastructure Project (EIP) - Car Park, Parking Lot Class I.
a) Car Park A (underground car park without upper floors): Level II.
Underground car park with 3 basement floors, depth 18 meters (from ground surface to basement floor 3), total floor area 5,000 square meters, number of parking spaces: 400 cars. The level of this work is determined according to the provisions at Level IV.
c) Applying the construction level in managing investment and construction activities: The method of determination see - Determining the level based on capacity scale: Corresponding to item 1.3.8.1 Table 1.3 Appendix I, the level of the work is determined based on number of parking spaces as Level II;.
- Determining the level based on type and structural scale: Corresponding to item 2.1.1 Table 2 Appendix II, determine the level of the work based on number of basement floors: Level II, based on underground depth: Level II, based on total floor area: Level III. The highest level determined based on structural scale is Level II;
Therefore, the level of the Car Park A is
b) Car Park B (with upper and basement floors):2Elevated car park with 3 upper floors and 2 basement floors with a total floor area of 12,000 square meters (basement floor area: 4,500 square meters, upper floor area: 7,500 square meters), number of parking spaces: 400 cars (150 spaces in basement and 250 spaces in upper part). The level of this work is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
- Determining the level based on capacity scale: Corresponding to items 1.3.8.1 and 1.3.8.2 Table 1.3 Appendix I, the level of the work is determined based on number of parking spaces for basement part: Level III, based on number of parking spaces for upper part: Level III. The highest level determined based on capacity scale is Level III;
- Determining the level based on type and structural scale: Corresponding to item 2.1.1 Table 2 Appendix II, the level of the work is determined as Level II;
Therefore, the level of the Car Park B is Level II (the highest level determined from capacity scale and structural scale).
(the highest level determined from capacity scale and structural scale).
c) Parking Lot C without car park building:2 Parking Lot C: Reinforced concrete pavement area 10,000 square meters and without a car park building. The level of this work is determined according to the provisions at2as follows: The work corresponds to item 1.3.8.3 Table 1.3 Appendix I, the level of the work is determined based on total area as23.10 Example 10: Transportation Infrastructure Project - Expressway A Clause 2, Article 2 of this Circular as follows:
The investment construction project "Expressway A" is 200 kilometers long, design speed 120 km/h. On this expressway there are the following works:
- A1 (Expressway): Design speed 120 km/h;
Thus, the construction level of Building B for Parking is Level II (the highest level determined based on capacity scale and structural scale).
c) Parking Lot C without a parking building:
Parking Lot C: A reinforced concrete surface area of 10,000 m²2 and without a parking building. The construction level of this project is determined according to the provisions at Clause 2, Article 2 of this Circular as follows: The project corresponds to item 1.3.8.3 Table 1.3 Appendix I, the construction level is determined based on the total area as Level IV.
3.10 Example 10: Transportation Project - Highway A
The investment and construction project "Highway A" is 200 km long with a design speed of 120 km/h. Along this route, there are the following projects:
- A1 (Expressway): Design speed 120 km/h;
- A2 (Road Bridge): 4 spans, largest span 40 m, height of bridge pier 20 m;
- A3 (Tunnel for Road Traffic): Mountain tunnel with reinforced concrete lining, length 300 m, cross-sectional area of the tunnel 200 m²;2;
- A4 (Toll Station): Frame structure with roof, height to top of construction: 15 m, length of largest span: 40 m; and other minor structures: Signpost columns, signpost frames, pedestrian underpasses, guardrails;
The project grade is determined as follows:
The Highway Project A is constructed along a route including several main works directly serving transportation (including works A1, A2, and A3) and auxiliary works (A4 and other minor structures). The classification of these works is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
a) Determining the classification of main works:
- Work A1: A work with capacity scale and without regulations determining classification based on type and structural scale. According to the provisions at Section 1.4.1.1 Table 1.4 Appendix I, the work classification is determined based on the design speed as special level.
- Work A2: Without importance level or capacity scale (not listed in Table 1.4 Appendix I), therefore the work classification is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to Section 2.5.1, determining the work classification based on the largest span: Class III, based on the height of the bridge pier: Class II. Classification of Work A2: Level II (the highest level determined).
- Work A3: Without importance level or capacity scale (not listed in Table 1.4 Appendix I), therefore the work classification is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to Group 2.6.1, determining the work classification based on total length: Class II, based on cross-sectional area: Class I, based on tunnel shell structure: Class II. Classification of Work A3: Class I (the highest level determined).
b) Determining the classification of auxiliary works:
- Work A4: Without importance level or capacity scale (not listed in Table 1.4 Appendix I), therefore the work classification is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to Section 2.1.3, determining the work classification based on height: Class III, based on the largest span: Class III. Classification of Work A4: Class III (the highest level determined).
- Other minor structures (signpost columns, signpost frames, pedestrian underpasses, guardrails...): Determined according to the provisions at Clause 2, Article 2 of this Circular. If the work does not have (or does not have a suitable type) in Table 1.4 Appendix I, then the classification is determined based on type and structural scale (using Table 2 Appendix II).
c) Applying the level of the construction project in managing investment construction activities:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: The Highway Project A is constructed along a route including several main works, according to point b clause 2 Article 3 of this Circular, applying the highest classification of the main works is special level (classification of Work A1 - already determined in point a Example here) to implement.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular: Example of classifying the construction activity capacity of organizations and individuals participating in construction activities for one, some, or all works within the investment construction project along the route carried out according to the provisions at point d clause 3 Article 3 Circular this as follows:
+ In case of implementation scope for one work, for example Work A1, apply the work classification (already determined in point a Example here) of Work A1 is special level;
+ In case of implementation scope for some works, for example Work A2 and A3, apply the work classification (already determined in point a Example here) of Work A2 is Level II (for road bridge) and of Work A3 is Primary Level (for traffic tunnel);
+ In case of implementation scope for all works, apply the work classification (already determined in point a and b Example here) of the works along the route.
3.11 Example 11: Transportation - Lighthouse M
"Lighthouse M" built on an island, 50 m high above ground level outside the construction. The classification of "Lighthouse M" is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
Work "Lighthouse M" is not listed in Table 1.4 Appendix I, therefore the work classification is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to Section 2.2.3; the work classification is determined based on the height of the structure as Level II.
3.12 Example 12 - Agricultural and Rural Development - Farm A
The investment construction project "Farm A", area 30 hectares includes the following works:
- A1: Irrigation water supply system for irrigated area 25 hectares;
- A2: Drainage system for area 29.5 hectares;
- A3 (Greenhouse for seedling cultivation): One-story building, height 12 m, largest span 30 m, total area 4,000 m²2;
and other works: Office building, Workers' accommodation, Internal roads; Substation and power lines; Domestic water supply system (water reservoir and pipelines); Wastewater drainage system; Warehouses; Parking lots, Fence.
The project grade is determined as follows:
The Farm A project includes several main works directly serving irrigation and farming tasks (including works A1, A2, and A3) and other auxiliary works. The classification of these works is determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
a) Determining the classification of main works:
- Work A1: A work with capacity scale and without regulations determining classification based on type and structural scale. According to the provisions at Section 1.5.1.1 Table 1.5 Appendix I, the work classification is determined based on the irrigated area as Level IV.
- Work A2: A work with capacity scale and without regulations determining classification based on type and structural scale. According to the provisions at Section 1.5.1.1 Table 1.5 Appendix I, the work classification is determined based on the drainage area as Level IV.
- Work A3: Without importance level or capacity scale (not listed in Table 1.5 Appendix I), therefore the work classification is determined based on type and structural scale. According to Table 2 Appendix II, this work corresponds to Section 2.1.1; the work classification is determined as Level III.
b) See the determination method for other works presented in this Appendix.
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 3 of this Appendix.
3.13[39] Example 13: Investment Construction Project Passenger Railway Station C
The project includes the following works:
- A1: Railway within the station, track gauge 1,000 mm and crossover track, track gauge (1,435 - 1,000) mm; design speed 100 km/h;
- A2: Two-story station building, total floor area 500 m²2;
- A3: Warehouse, area 2,000 m²2, because of the truss span 12 m, height 8 m;
- A4: Pedestrian overpass within the station, width of deck 3.5 m, longest span 40 m;
- A4: Passenger shelter, area Sm=1,000 m²2, because of the truss span 9 m, height of roof 4.5 m.
The project grade is determined as follows:
The railway passenger station C construction project includes main works A1 and A2 serving rail transportation and auxiliary works A3, A4, and A5.
a) Determination of the grade of the main complex of buildings:
The main works of this station are not listed in Appendix I Table 1.4, therefore according to the provision at point b clause 3 Article 2 of this Circular, the level of the works is determined based on the highest level of the main works as follows:
- Work A1 corresponds to item 1.4.2.2 of Table 1.4 in Appendix I; the level of the work is determined as Level II (based on design speed);
- Work A2 is not listed in Table 1.4 of Appendix I, therefore the level of the work is determined based on type and scale of structure. According to Table 2 of Appendix II, this work corresponds to item 2.1.1 (Building, Building-like Structure); the level of the work is determined as Level III (the highest level determined based on number of floors);
Thus, the level of the main works of the railway passenger station C is Level II (taken from the level of work A1).
b) Determining the level of works within the station area
- Works A1 and A2 have been determined their levels in section a of this Example;
- Work A3 is not listed in Appendix I, therefore the level of the work is determined based on type and scale of structure. According to Table 2 of Appendix II, this work corresponds to item 2.1.1 (Building, Building-like Structure); the level of the work is determined as Level III (the highest level determined based on height and total floor area);
- Work A4 is not listed in Appendix I, therefore the level of the work is determined based on type and scale of structure. According to Table 2 of Appendix II, this work corresponds to item 2.5.3; the level of the work is determined as Level III (based on the largest span of structure);
- Work A5 is not listed in Appendix I, therefore the level of the work is determined based on type and scale of structure. According to Table 2 of Appendix II, this work corresponds to item 2.1.3 (Large-span Frame Structure); the level of the work is determined as Level IV (the highest level determined based on height and the largest span of structure).
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 1 of this Appendix.
3.14[40] Example 14: Investment Construction Project for Transportation - Aviation (Runway Area)
The investment construction project for the Runway Area of International Airport A (Class 4E airport) includes the following works:
- A1: Runway, size 3,000x45 (m); runway shoulders each side width 7 m;
- A2: Taxiway E1, size 150x30 (m); taxiway shoulders each side width 5 m;
- A3: Taxiway E2, size 150x45 (m); taxiway shoulders each side width 5 m;
- A4: End-of-runway blast pads (RESA), size 240x90 (m);
- A5: Constructing the runway area as prescribed;
- A6: Other auxiliary works:
+ Drainage system: Constructing circular drainage pipes with diameter D1000, length 2,000 m;
+ Drainage ditch (canal) system: Constructing ditch M1 with rubble concrete, size Bđ =1 m, Bm =4 m, Htb =1.5 m; ditch M2 with BTXM structure, size Bđ =1 m, Bm =4 m, Htb =1.5 m;
+ Service road: Constructing service roads in the runway area with length 7,000 m, width 3.5 m;
+ Aviation security fence: Constructing aviation security fence with brick structure height 2.45 m, total length 2,500 m.
The project grade is determined as follows:
The investment construction project for the Runway Area of International Airport A includes several main works (including works A1, A2, A3, A4, A5) directly serving transportation and auxiliary works (mentioned in section A6 above). The levels of these works are determined according to the provisions at Clause 2, Article 2 of this Circular as follows:
a) Determining the classification of main works:
- Work A1: Important work without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.6.2 of Table 1.4 in Appendix I, the level of the work is determined as special level.
- Work A2: Important work without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.6.2 of Table 1.4 in Appendix I, the level of the work is determined as special level.
- Work A3: Important work without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.6.2 of Table 1.4 in Appendix I, the level of the work is determined as special level.
- Work A4: Important work without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.6.2 of Table 1.4 in Appendix I, the level of the work is determined as special level.
- Work A5: Important work without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.6.2 of Table 1.4 in Appendix I, the level of the work is determined as special level.
b) Determining the level of auxiliary works (A6):
- Service road: Work not included in item 1.4.6.2 of Table 1.4 in Appendix I and without specific regulations determining level based on type and scale of structure. According to the provisions at item 1.4.1.5 of Table 1.4 in Appendix I, the level of the work is determined as Level IV.
- Drainage system: Work not listed in Appendix I (no importance level or capacity scale), therefore the level of the work is determined based on type and scale of structure. According to item 2.10.2 of Table 2 in Appendix II, the level of the work is determined as Level III.
- Drainage ditch system: Work not listed in Appendix I (no importance level or capacity scale), therefore the level of the work is determined based on type and scale of structure. According to note 5 of Table 2 in Appendix II, determine the level of the work based on reinforced bank structure, corresponding to item 2.9 of Table 2 in Appendix II, the level of the work is determined as Level IV.
- Aviation security fence: Work not listed in Appendix I (no importance level or capacity scale), therefore the level of the work is determined based on type and scale of structure. According to item 2.14.2 of Table 2 in Appendix II, the level of the work is determined as Level IV.
c) Applying the construction level in managing investment and construction activities: The method of determination see Example 1 of this Appendix.
3.15[41] Example 15: Investment Construction Project for Expressway B Route in Two Stages (Phased Investment)
According to the approved investment decision, the investment construction project for Expressway B Route is 200 km long, with a design speed of 120 km/h. On this route, there are the following works:
- Expressway B1: Design speed 120 km/h; pavement width 32.25 m;
- Highway Bridge B2.1: 4 spans, largest span 40 m, bridge pier height 20 m;
- Highway Bridge B2.2: 4 spans, largest span 40 m, bridge pier height 25 m;
- Highway Tunnel B3.1 and B3.2: Mountain tunnel, with concrete lining, each tunnel tube is 300 m long and cross-sectional area 200 m2;
- Toll station B4: Structural frame, with roof, height to top of structure 15 m, maximum span length 40 m.
The investment project for constructing Expressway B Route will be carried out over 60 months in two implementation phases (investment periods):
- Phase 1 of the Expressway B construction project (36 months) includes:
+ Expressway B1 Phase 1 (investment period): Design speed 80 km/h; road base width 17 m; put into operation first.
+ Road bridge B2.1.
+ Traffic tunnel B3.1.
- Phase 2 of the Expressway B construction project (24 months) includes:
+ Expressway B1 Phase 2 (final phase): Design speed 120 km/h; road base width 32.25 m;
+ Road bridge B2.2;
+ Traffic tunnel B3.2;
+ Toll station B4.
The project grade is determined as follows:
a) Determining the level of main works in the Expressway B project:
The Expressway B project is constructed along a route with several main works being invested and constructed in two implementation phases (investment periods), the level of works is determined according to the provisions of Clause 2 and Clause 6 Article 2 of this Circular. as follows:
- Expressway B1 (final phase): Special grade (according to the design speed at item 1.4.1.1 Table 1.4 Appendix I).
- Road bridges B2.1 and B2.2: Level II (highest grade determined according to the height of the bridge pier at item 2.5.1 Table 2 Appendix II).
- Traffic tunnels B3.1 and B3.2: Class I (highest grade determined according to the cross-sectional area of the tunnel based on the clear width at item 2.6.1 Table 2 Appendix II).
b) Determining the level of auxiliary works in the Expressway B project:
- Toll station B4: Class III (highest grade determined according to the height and maximum span length at item 2.1.3 Table 2 Appendix II).
c) Applying the level of works in managing investment and construction activities in Phase 1 of the Expressway B project.
The Expressway B project is invested and constructed in implementation phases (investment periods), therefore, the application of the level of works is as follows:
- Using the level of the construction project to determine the authority as provided in point a clause 1 Article 3 of this Circular: Phase 1 of the Expressway B project is constructed along a route with several main works, according to the provisions of Point b Clause 2 and Clause 4 Article 3 of this Circular,applying the highest level of main works (Expressway B1 final phase, already determined in item a Example above) is special level.
- Using the level of the construction project to manage investment construction activities is regulated from point b to point n clause 1 Article 3 of this Circular; for example, classifying the construction activity capacity of organizations and individuals participating in construction activities for one, some, or all works in Phase 1 of the Expressway B project is implemented according to the provisions of Point d Clause 3 and Clause 4 Article 3 of this Circular as follows:
+ In case the scope of implementation is for one work, such as Expressway B1 Phase 1 (investment period), apply the level of works for Expressway B1 final phase (already determined in item a Example above) is special level;
+ In case the scope of implementation is for some works, such as Works B2.1 and B3.1, apply the level of works (already determined in item a Example above) of Work B2.1 is Grade II (for road bridges) and of Work B3.1 is Grade I (for traffic tunnels);
+ In case the scope of implementation is for all works, apply the level of works (already determined in item a Example above) of the works along the route.
d) Applying the level of works in managing investment and construction activities in Phase 2 of the Expressway B project: Similar to item c/.
[1] Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities is promulgated based on the following grounds:
"Pursuant to the Construction Law dated June 18, 2014; the Law Amending and Supplementing Certain Provisions of the Construction Law dated June 17, 2020;
Pursuant to the Law on Architecture dated June 13, 2019;
Pursuant to the Government Decree No. 06/2021/NĐ-CP dated January 26, 2021 detailing certain provisions on quality management, construction works, and maintenance of construction projects;
Pursuant to Decree No. 175/2024/NĐ-CP dated December 30, 2024, of the Government detailing certain provisions and measures for implementation of the Construction Law on management of construction activities;
Pursuant to Decree No. 33/2025/NĐ-CP dated February 25, 2025 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;
At the proposal of the Director of the National Construction Quality Supervision Agency;
The Minister of Construction promulgates the Circular amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities."
Circular No. 09/2025/TT-BXD dated June 13, 2025, of the Minister of Construction amending and supplementing certain articles of Circulars under the Ministry of Construction's state management domain related to organizational restructuring, implementation of two-level local government, and delegation of authority to local governments is promulgated based on the following grounds:
"Pursuant to the Law on Issuance of Legal Normative Documents dated February 19, 2025;
Pursuant to Resolution No. 190/2025/QH15 dated February 19, 2025 of the National Assembly on handling certain issues related to the restructuring of the state apparatus;
Pursuant to Decree No. 33/2025/NĐ-CP dated February 25, 2025 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Construction;
Decree No. 140/2025/NĐ-CP dated June 12, 2025, of the Government on division of authority of two-level local governments in the Ministry of Construction's state management domain;
Decree No. 144/2025/NĐ-CP dated June 12, 2025, of the Government on decentralization and delegation of authority in the Ministry of Construction's state management domain;
At the proposal of the Director of the Legal Department;
The Minister of Construction promulgates the Circular amending and supplementing certain articles of Circulars under the Ministry of Construction's state management domain related to organizational restructuring, implementation of two-level local government, and delegation of authority to local governments."
[2] This clause is amended and supplemented according to the provisions of Clause 1 Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities, which takes effect from May 20, 2025.
[3] This clause is added according to the provisions of Clause 2 Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities, which takes effect from May 20, 2025.
[4] This clause is added according to the provisions of Clause 2 Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities, which takes effect from May 20, 2025.
[5] This clause is added according to the provisions of Clause 2 Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance on application in management of investment and construction activities, which takes effect from May 20, 2025.
[6] This paragraph was added pursuant to Clause 3, Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, issued by the Minister of Construction to amend and supplement certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, issued by the Minister of Construction on classification of construction projects and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[7] This paragraph was added pursuant to Clause 3, Article 1 of Circular No. 02/2025/TT-BXD dated March 31, 2025, issued by the Minister of Construction to amend and supplement certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, issued by the Minister of Construction on classification of construction projects and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[8] Clause 5, Article 33 of Circular No. 09/2025/TT-BXD dated June 13, 2025, issued by the Minister of Construction to amend and supplement certain provisions of Circulars under the Ministry of Construction's administrative domain related to organizational restructuring, implementation of two-level local government, and delegation to local governments, which shall take effect from July 1, 2025, provides as follows:
"5. Transitional provisions for the content stipulated in Article 10 of this Circular."
a) The classification level of construction projects within investment construction projects decided upon before July 1, 2025, shall be determined according to the legal provisions at the time of the investment decision.
b) In cases where construction projects have been submitted to specialized agencies for review or reviewed for adjustment of feasibility study reports or design drawings implemented after the basic design before July 1, 2025, and meet the conditions for review, the determination of the project classification level and its application in managing investment construction activities shall be based on the legal provisions at the time of submission for review.
c) In cases where there is an adjustment to the construction design before July 1, 2025, but it does not change the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the legal provisions at the time of the investment decision; if the adjustment changes the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the provisions of this Circular./.
[9] Article 2 of Circular No. 02/2025/TT-BXD dated March 31, 2025, issued by the Minister of Construction to amend and supplement certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, issued by the Minister of Construction on classification of construction projects and guidance for application in investment construction management activities, which shall take effect from May 20, 2025, provides as follows:
“Article 2. Implementation clause
1. This Circular shall take effect from May 20, 2025.
2. The classification level of construction projects within investment construction projects decided upon before the effective date of this Circular shall be determined according to the legal provisions at the time of the investment decision.
3. In cases where construction projects have been submitted to specialized agencies for review or reviewed for adjustment of feasibility study reports or design drawings implemented after the basic design before the effective date of this Circular and meet the conditions for review, the determination of the project classification level and its application in managing investment construction activities shall be based on the legal provisions at the time of submission for review.
4. In cases where there is an adjustment to the construction design from the effective date of this Circular:
a) If the adjustment does not change the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the legal provisions at the time of the investment decision;
b) If the adjustment changes the level of importance, capacity scale, or structural scale, the project classification level shall be determined according to the provisions of Circular No. 06/2021/TT-BXD amended and supplemented by this Circular./.
Article 31 Circular No. 09/2025/TT-BXD dated June 13, 2025, of the Minister of Construction amending and supplementing certain provisions of Circulars under the State management of the Ministry of Construction related to organizational restructuring, implementation of two-level local administration, and decentralization to local authorities, shall take effect from July 1, 2025, is stipulated as follows:
“Article 31. Effective date
1. This Circular shall take effect from July 1, 2025.
[10] This Section has been amended and supplemented according to the provisions at Item 1 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[11] The phrase "General Bureau and equivalent level" has been abolished according to Clause 2, Article 10 of Circular No. 09/2025/TT-BXD, shall take effect from July 1, 2025.
[12] The phrase "high level" has been abolished according to Clause 2, Article 10 of Circular No. 09/2025/TT-BXD, shall take effect from July 1, 2025.
[13] The phrase "Office of the Party Committee; People's Council, People's Committee at district level" has been abolished according to Clause 2, Article 10 of Circular No. 09/2025/TT-BXD, shall take effect from July 1, 2025.
[14] The phrase "People's Court, People's Procuracy at provincial level" has been replaced by the phrase "People's Court, People's Procuracy at provincial and regional levels" according to Clause 1, Article 10 of Circular No. 09/2025/TT-BXD, shall take effect from July 1, 2025.
[15] The phrase "District Office and equivalent level; People's Court, People's Procuracy at district level" has been abolished according to Clause 2, Article 10 of Circular No. 09/2025/TT-BXD, shall take effect from July 1, 2025.
[16] This Section has been amended and supplemented according to the provisions at Item 2 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[17] This Section has been abolished according to the provisions at Item 3 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[18] This Section has been amended and supplemented according to the provisions at Item 2 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[19] This Point has been amended and supplemented according to the provisions at Item 4 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[20] This Point has been amended and supplemented according to the provisions at Item 4 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification and guidance for application in construction investment management activities, shall take effect from May 20, 2025.
[21] This Section is amended and supplemented pursuant to the provisions of Section 5 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[22] This Section is added pursuant to the provisions of Section 6 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[23] This Section is added pursuant to the provisions of Section 7 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[24] This Section is amended and supplemented pursuant to the provisions of Section 8 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[25] This Section is amended and supplemented pursuant to the provisions of Section 8 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[26] This Section is amended and supplemented pursuant to the provisions of Section 9 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[27] This Section is amended and supplemented pursuant to the provisions of Section 10 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[28] This Point is amended and supplemented pursuant to the provisions of Section 11 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[29] This Section is amended and supplemented pursuant to the provisions of Section 12 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain articles of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[30] This Section is added pursuant to Article 13 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[31] This Section is added pursuant to Article 13 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[32] This Section is added pursuant to Article 13 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[33] This Section is added pursuant to Article 13 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[34] This Section is added pursuant to Article 13 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[35] This Section is amended and supplemented pursuant to Article 14 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[36] This Section is amended and supplemented pursuant to Article 14 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[37] This Section is amended and supplemented pursuant to Article 15 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[38] This Section is amended and supplemented pursuant to Article 16 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[39] This Section is added pursuant to Article 17 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[40] This Section is added pursuant to Article 17 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.
[41] This Section is added pursuant to Article 17 of the Appendix issued together with Circular No. 02/2025/TT-BXD dated March 31, 2025, of the Minister of Construction amending and supplementing certain provisions of Circular No. 06/2021/TT-BXD dated June 30, 2021, of the Minister of Construction on classification of construction works and guidance for application in investment construction management activities, which shall take effect from May 20, 2025.