Decree No. 08/2021/ND-CP on management of inland waterway activities

This topic focuses on the procedures for announcing operations and managing inland waterway ports and wharfs in Vietnam. It includes aspects such as quality inspection, renovation and upgrading, closure or suspension of operations based on specific conditions and current legal regulations.

Số hiệu08/2021/NĐ-CP
Loại văn bảnDecree
Cơ quan ban hànhMinistry of Construction
Người kýNguyễn Xuân Phúc — Thủ tướng
Cập nhật14/06/2026
NgànhTransport
Lĩnh vựcInland Waterways
Ngày ban hành28/01/2021
Ngày áp dụng15/03/2021
Ngày hết hiệu lực—
Tình trạngIn effect
✦ Tóm lược thông minh

This topic focuses on the procedures for announcing operations and managing inland waterway ports and wharfs in Vietnam. It includes aspects such as quality inspection, renovation and upgrading, closure or suspension of operations based on specific conditions and current legal regulations.

Đối tượng áp dụng

Port owners, port and wharf operators, competent authorities such as the Ministry of Transport, the Vietnam Inland Waterways Administration, Provincial Departments of Transport, and other relevant agencies.

Các điểm cốt lõi

  • Procedures for announcing new or resumed operations for ports and wharfs
  • Requirements for quality inspection of port and wharf construction works
  • Procedures for renovating and upgrading ports and wharfs
  • Closure or suspension of operations based on specific conditions and legal provisions.
  • Regulations on upgrading inland waterway wharfs to inland waterway ports

🌐 Tác động xã hội từ văn bản này

  • Ensuring safety for vessels and cargo transportation
  • Optimizing the operational efficiency of ports and inland waterway wharfs
  • Supporting economic and social development through effective management of the inland waterway transport system

❓ Câu hỏi thường gặp

What is the procedure for announcing the closure of a port or wharf?

The competent authority will review the proposal document from the Ministry of National Defense or the closure request from the port/wharf owner. If necessary, this authority must notify the operator at least 60 days before the expected closure date.

What factors need to be considered when renovating and upgrading a port or wharf?

When renovating and upgrading, the port/wharf owner must submit a proposal document to the competent authority with information about the planned scale, implementation time, and impact on transportation activities. The authority will review within five days.

How can an inland waterway wharf be upgraded to a port?

The wharf owner submits a proposal document to the competent authority, then carries out renovations according to construction regulations. Upon completion, the operator will file a declaration of conversion.

Toàn văn

THE GOVERNMENT

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 08/2021/NĐ-CP
Hanoi, January 28, 2021

DECREE

Regulations on Management of Inland Waterway Activities

Pursuant to the Law on Government Organization dated June 19, 2015; the Law Amending and Supplementing Certain Provisions of the Law on Government Organization and the Law on Organization of Local Administration dated November 22, 2019;June 2024;The Government issues this Decree on regulations concerning management of inland waterway activities., amended and supplemented by Decree No. 109/2025/NĐ-CP and Decree No. 193/2025/NĐ-CP This Decree stipulates the management of inland waterway activities, including: Investment in construction, operation, maintenance, and protection of inland waterway infrastructure; ensuring safety, security, and environmental protection on inland waterways, ports, inland waterway wharves, anchorage areas; management of activities of vessels, ships, seaplanes, foreign watercraft at ports, inland waterway wharves, anchorage areas; responsibilities for state management in inland waterway activities.

Pursuant to the Law on Inland Waterway Traffic dated June 15, 2004, and the Law Amending and Supplementing Certain Provisions of the Law on Inland Waterway Traffic dated June 17, 2014;

At the proposal of the Minister of Transport;

This Decree applies to organizations and individuals related to inland waterway activities in Vietnam.

PART I

GENERAL PROVISIONS

Article 1. Scope of Regulation

1. Inland waterway infrastructure includes: Inland waterway channels, channel protection zones, ports, inland waterway wharves, anchorage areas, ship basins, structures for vessel passage over dams and rapids; revetments, traffic dams; inland waterway navigation aids and auxiliary works such as elevation markers, coordinate markers, channel protection zone boundary markers, watch stations; facilities, architectural structures, equipment directly serving inland waterway transportation management and operation.

Article 2. Applicability

2. Vessel navigation channel is the water area delimited by inland waterway navigation aids for vessels to travel smoothly and safely (referred to as inland waterway channel in this Decree).

Article 3. Explanation of Terms

In this Decree, the following terms are understood as follows:

3. Dedicated port, inland waterway wharf is a port or wharf exclusively for loading and unloading raw materials, fuel, minerals, supplies, equipment for production purposes of the port or wharf owner or for new construction, conversion, repair and restoration of vessels, ships, foreign watercraft.

4. River passenger wharf is an inland waterway wharf specifically for river passenger and cargo transport from one bank to the other across rivers, canals, streams, lakes, and lagoons. A position on each bank constitutes a river passenger wharf.

5. Mooring wharf is an inland waterway wharf using floating structures, pontoons placed at a stable location on the water surface for berthing vessels to load and unload goods, embark and disembark passengers, and perform other support services.

6. Anchorage area is the water area outside the port or inland waterway wharf waters established by mooring buoys, mooring piles, or self-mooring systems for vessels, ships, seaplanes to anchor and transfer cargo and passengers or engage in other activities as prescribed.

7. Port, inland waterway wharf, anchorage area owner is an organization or individual owning port, inland waterway wharf, mooring buoys, piles and granted the right to use land and water areas of the port, inland waterway wharf, anchorage area.

8. Port, inland waterway wharf, anchorage area operator is the port, inland waterway wharf, anchorage area owner directly operating the port, inland waterway wharf, anchorage area or an organization or individual leasing the port, inland waterway wharf, anchorage area for operation or an organization or individual authorized to manage and operate the port, inland waterway wharf, anchorage area.

9. Person applying procedures for vessels, ships, seaplanes, foreign watercraft entering or leaving ports, inland waterway wharves, anchorage areas is the vessel, ship, seaplane, foreign watercraft owner, crew member, vessel driver, seaplane operator, or person authorized to apply entry and exit procedures at ports, inland waterway wharves, anchorage areas (hereinafter referred to as the person handling procedures).

10. Inland waterway vessel is a ship, boat, or other floating structure with or without a motor, specifically operating on inland waterways (referred to as vessel in this Decree).

11. Foreign watercraft is a watercraft flying the flag of another country.

MANAGEMENT OF INLAND WATERWAY INFRASTRUCTURE

11. Foreign watercraft is watercraft flying the flag of foreign nationality.

Chapter II

MANAGEMENT OF DOMESTIC INLAND WATERWAY INFRASTRUCTURE STRUCTURE

Mục 1 ||| GENERAL PROVISIONS ON MANAGEMENT OF INLAND WATERWAY INFRASTRUCTURE

Article 4. Principles for Investment and Construction of Inland Waterway Infrastructure

1\. Organizations and individuals, both domestic and foreign, investing in and constructing inland waterway infrastructure must comply with the provisions of this Decree, investment regulations, public investment regulations, construction regulations, land regulations, mineral resources regulations, environmental regulations, and other relevant legal provisions.

2\. Investment and construction of inland waterway channels, ports, inland waterway wharfs (excluding inland waterway wharfs serving construction of main projects), anchorage areas must be consistent with the planning of inland waterway infrastructure and related plans as stipulated by laws on planning. In cases where investment and construction projects for inland waterway channels, ports, inland waterway wharfs, and anchorage areas have not been included in or differ from approved plans, during the project preparation process, the investor must report to the competent authority for examination and adjustment to supplement the plan according to the laws on planning.

Article 5. Management and Maintenance of Inland Waterway Infrastructure

1\. Management Organization

a\. The Vietnam Inland Waterways Administration shall organize management and maintenance of inland waterway infrastructure within the scope of management of the Ministry of Transport;

b\. Provincial People's Committees (hereinafter referred to as provincial-level People's Committees) shall organize management and maintenance of inland waterway infrastructure within their scope of management;

c\. Organizations and individuals investing in and constructing inland waterway infrastructure without using state funds shall decide on organizing management and maintenance of the works in accordance with the provisions of this Decree and other relevant legal provisions.

2\. Maintenance of Inland Waterway Infrastructure

a\. Works belonging to inland waterway infrastructure shall be maintained to ensure normal operation and safety of the works;

b\. The management and maintenance activities of works belonging to inland waterway infrastructure include: management work; regular maintenance; periodic and emergency repairs, remediation of damaged works; activities aimed at improving the current condition of the works; supplementation and replacement of signaling devices, parts of the works, and equipment attached to the works; establishment of monitoring records for the works and obstructions; traffic safety assurance activities, and other activities as prescribed by relevant laws;

c\. The Minister of Transport shall provide detailed regulations on the management and maintenance of works belonging to inland waterway infrastructure.

Article 6. Ensuring Safety and Security in Inland Waterway Activities

1\. Projects and activities related to inland waterways must be ensured safe and secure in accordance with the provisions of this Decree and other relevant legal provisions.

2\. Responsibilities for Ensuring Safety and Security in Inland Waterway Activities

a\. Owners of works belonging to inland waterway infrastructure, port operators, inland waterway wharf operators, anchorage area operators; organizations and individuals organizing activities on inland waterways are responsible for ensuring and maintaining safety and security of the works and activities during the investment and construction period and management and exploitation in accordance with the law;

b\. All levels of People's Committees, specialized agencies managing inland waterway transport, relevant agencies and units are responsible for promoting and guiding the implementation of regulations on ensuring safety and security for works and activities related to inland waterways, ports, inland waterway wharfs, anchorage areas; inspecting and handling violations of regulations on ensuring safety and security of inland waterways, ports, inland waterway wharfs, anchorage areas in accordance with the law.

M ||| Section 2. MANAGEMENT OF INVESTMENT IN WATERWAY CONSTRUCTION AND EXPLOITATION OF INLAND WATERWAYS

A ||| Article 7. Classification and Technical Level of Inland Waterways

1. Inland waterways are classified into three types, namely: National inland waterways (hereinafter referred to as national waterways), local inland waterways (hereinafter referred to as local waterways), and specialized inland waterways (hereinafter referred to as specialized waterways).

2. National waterways are those that meet one of the following conditions:

a) Passing through two or more provinces or centrally governed cities playing an important role in serving the economy, national defense, and security;

b) Waterways within the territory of a province or centrally governed city directly connecting with coastal transport routes or directly connecting with two national waterways;

c) Waterways crossing borders or on borders.

3. Local waterways are those within the territory of a province or centrally governed city, except for cases specified in points b and c of Clause 2 of this Article.

4. Specialized waterways are those connecting port waters or specialized inland waterway terminals with national waterways or local waterways.

5. Inland waterways are classified into technical levels as prescribed by the Minister of Transport.

A ||| Article 8. Agreement on Technical Specifications for Construction of Inland Waterways

1. Before approving the investment project for construction of inland waterways, the investor must agree on the technical specifications of the waterway with the competent authority as stipulated in Clause 2 of this Article.

2. Competent Authority for Agreement

a) The Vietnam Inland Waterway Administration agrees on the technical specifications of national waterways and specialized waterways connected to national waterways;

b) The Department of Transport of a province or centrally governed city agrees on the technical specifications of local waterways and specialized waterways connected to local waterways.

3. Content of Agreement

a) Compliance with planning;

b) Scale and technical specifications.

4. Agreement Documents

a) Request for agreement on technical specifications for construction of inland waterways according to Model No. 01 attached to this Decree;

b) Copy of the approval document for the investment project from the competent authority (if applicable);

c) Preliminary design documents for inland waterways.

5. Procedure for Agreement

The investor submits one set of documents directly or by other appropriate means to the competent authority as stipulated in Clause 2 of this Article to agree on the technical specifications for construction of inland waterways.

Within five working days from the date of receipt of complete documents as prescribed, the competent authority as stipulated in Clause 2 of this Article shall issue an agreement document on technical specifications for construction of inland waterways and send it to the investor.

A ||| Article 9. Competence and Procedures for Announcing Opening and Managing Inland Waterways

1. Inland waterways must be announced open by the competent authority before they are put into operation.

2. Competence for Announcing Opening

a) The Ministry of Transport decides to announce the opening of national waterways and specialized waterways connected to national waterways;

b) The People's Committee of a province decides to announce the opening of local waterways and specialized waterways connected to local waterways.

3. Application Documents for Announcing Opening

a) Request for announcing opening of inland waterways according to Model No. 02 attached to this Decree;

b) Completion acceptance report for construction works put into use, final drawings of waterway construction works, and inland waterway navigation signal systems for new construction projects or improved and upgraded waterways;

c) Current map of the proposed waterway showing place names, mileage, signal positions, and existing structures on the waterway for waterways without construction projects.

4. Procedure for Announcing Opening

a) For national waterways: The Vietnam Inland Waterway Administration prepares the application documents and reports to the Ministry of Transport; within five working days from the date of receipt of complete documents, the Ministry of Transport issues a decision to announce the opening of the waterway;

b) For local waterways: The Department of Transport prepares the application documents and reports to the People's Committee of the province; within five working days from the date of receipt of complete documents, the People's Committee of the province issues a decision to announce the opening of the waterway;

c) For specialized waterways connected to national waterways: Organizations or individuals submit one set of documents directly or by other appropriate means to the Vietnam Inland Waterway Administration. Within five working days from the date of receipt of complete documents, the Vietnam Inland Waterway Administration reviews the documents, if they meet the requirements, it reports to the Ministry of Transport; within five working days from the date of receipt of the documents and report from the Vietnam Inland Waterway Administration, the Ministry of Transport issues a decision to announce the opening of the waterway;

d) For specialized waterways connected to local waterways: Organizations or individuals submit one set of documents directly or by other appropriate means to the Department of Transport. Within five working days from the date of receipt of complete documents, the Department of Transport reviews the documents, if they meet the requirements, it reports to the People's Committee of the province; within five working days from the date of receipt of the documents and report from the Department of Transport, the People's Committee of the province issues a decision to announce the opening of the waterway;

e) Decision to announce the opening of the waterway according to Model No. 03 attached to this Decree.

5. If an inland waterway already included in the approved planning only requires surveying and setting up signals for exploitation, the Ministry of Transport assigns the Vietnam Inland Waterway Administration, and the People's Committee of the province assigns the Department of Transport to organize the surveying and setting up of signals. After completing the surveying and setting up of signals, the procedures for announcing the opening of the waterway are carried out as prescribed in this Decree. The cost of surveying and setting up signals is guaranteed by the state budget from regular expenditure according to the budget classification.

6. Management of Inland Waterways

a) The Vietnam Inland Waterway Administration organizes the management of national waterways;

b) The People's Committee of a province directs the Department of Transport to organize the management of local waterways;

c) Organizations or individuals with specialized waterways organize the management of specialized waterways.

7. Establishment and Announcement of List of Inland Waterways

a) The Vietnam Inland Waterway Administration compiles the list of national waterways and specialized waterways connected to national waterways, and submits it to the Ministry of Transport for announcement.

b) The Department of Transport shall establish a list of local waterways and dedicated waterways connected to local waterways, and submit it to the People's Committee of the province for publication. After publication, the list shall be sent to the Vietnam Inland Waterway Administration for consolidation and monitoring;

c) Organizations and individuals with dedicated waterways shall be responsible for reporting technical specifications of the dedicated waterways to the Vietnam Inland Waterway Administration and the Department of Transport to serve the establishment and publication of the list of inland waterways;

d) The list of inland waterways shall be updated, adjusted, and published every three years. The Vietnam Inland Waterway Administration shall compile the list of inland waterways nationwide and post it on the electronic information website of the Vietnam Inland Waterway Administration;

Article 10. Conversion of Inland Waterways

1. Conditions for converting inland waterways

a) Complying with the approved planning for inland waterway infrastructure;

b) Meeting the conditions stipulated in Article 7 of this Decree;

2. Authority for converting inland waterways

a) The Ministry of Transport shall decide on converting local waterways and dedicated waterways into national waterways, and national waterways into local waterways;

b) The People's Committee of the province shall decide on converting dedicated waterways into local waterways, and local waterways into dedicated waterways;

3. Documents for converting waterways

a) A request letter accompanied by a report on the current status of the proposed converted waterway from the Vietnam Inland Waterway Administration (for national waterways) and the Department of Transport (for local waterways);

b) A request letter from the People's Committee of the province (for cases of converting local waterways into national waterways or national waterways into local waterways);

4. In cases where local waterways are converted into national waterways or national waterways are converted into local waterways: The Vietnam Inland Waterway Administration shall take the lead in coordinating with the Department of Transport to prepare the documents, report to the People's Committee of the province and the Ministry of Transport. Within five working days from the date of receipt of all required documents, the People's Committee of the province shall send a letter to the Ministry of Transport. Within ten working days from the date of receipt of the letter from the People's Committee of the province, the Ministry of Transport shall issue a decision to announce the conversion of the waterway;

5. In cases where dedicated waterways are converted into national waterways: The Vietnam Inland Waterway Administration shall take the lead in coordinating with organizations and individuals with dedicated waterways to prepare the documents and submit them to the Ministry of Transport. Within ten working days from the date of receipt of all required documents, the Ministry of Transport shall issue a decision to announce the conversion of the waterway;

6. In cases where dedicated waterways are converted into local waterways, or local waterways are converted into dedicated waterways: The Department of Transport shall take the lead in coordinating with organizations and individuals with dedicated waterways to prepare the documents and submit them to the People's Committee of the province. Within ten working days from the date of receipt of all required documents, the People's Committee of the province shall issue a decision to announce the conversion of the waterway;

7. When there is a decision to convert the waterway, the Ministry of Transport and the People's Committee of the province shall coordinate with the Ministry of Finance to implement the transfer of assets in accordance with the laws on the management and use of state assets. After receiving approval for the asset transfer, the agency or unit receiving the assets shall manage, use, and operate in accordance with the regulations;

8. In cases where dedicated waterways are converted into national waterways or local waterways, they may be considered for partial reimbursement of investment capital (if any) to organizations and individuals with dedicated waterways in accordance with the law and guidelines issued by the Ministry of Finance.

Article 11. Announcing the Closure of Inland Waterway Channels

1. Inland waterway channels shall be considered for announcement of closure in the following cases:

a) When they do not ensure safe exploitation and transportation;

b) For reasons of ensuring national defense and security;

c) When there is no longer a need for exploitation and use.

2. Authority to announce the closure of inland waterway channels

The agency responsible for deciding to announce the opening of channels as stipulated in Clause 2, Article 9 of this Decree is also the agency with authority to decide on announcing the closure of channels.

3. Documents for channel closure

a) For the case stipulated in Point a, Clause 1 of this Article, there must be a record of the current condition inspection of the channel by the Vietnam Inland Waterways Administration (for national channels), the Department of Transport (for local channels); a record of the current condition inspection between the Vietnam Inland Waterways Administration and organizations or individuals having dedicated channels connected to national channels, or between the Department of Transport and organizations or individuals having dedicated channels connected to local channels. The record must include a conclusion on the channel's unsuitability for safe exploitation;

b) A request document from the Ministry of National Defense or the Ministry of Public Security requiring the closure of channels for the case stipulated in Point b, Clause 1 of this Article;

c) An application form for announcing the closure of inland waterway channels according to Model No. 04 attached to this Decree for the case stipulated in Point c, Clause 1 of this Article;

d) A plan for the recovery of inland waterway navigation signs prepared by the agency, organization, or individual managing the channel.

4. Procedures for closing national and local channels

a) For the case of closing channels as stipulated in Point a, Clause 1 of this Article: After inspection, if it does not ensure safe exploitation and transportation, the Vietnam Inland Waterways Administration or the Department of Transport shall issue a notice temporarily suspending exploitation and transportation to the direct management unit of the channel and publish it through mass media, while preparing a document requesting the announcement of closure of the channel to be submitted to the competent authority;

b) For the case of closing channels as stipulated in Point b, Clause 1 of this Article, the Ministry of National Defense or the Ministry of Public Security must notify in writing the reasons for closure and the closure date to the Vietnam Inland Waterways Administration or the Department of Transport. The notification period before the required closure date must be at least 30 days. Within five working days from receiving the notification from the Ministry of National Defense or the Ministry of Public Security, the Vietnam Inland Waterways Administration reports to the Ministry of Transport, and the Department of Transport reports to the provincial People's Committee;

c) For the case of closing channels as stipulated in Point c, Clause 1 of this Article, the Vietnam Inland Waterways Administration (for national channels) or the Department of Transport (for local channels) prepares a document requesting closure of the channel to be submitted to the Ministry of Transport or the provincial People's Committee and organizes the recovery of inland waterway navigation signs within 60 days from the effective date of the decision to close the channel;

d) Within ten working days from receiving all required documents, the Ministry of Transport or the provincial People's Committee issues a decision to announce the closure of the channel within their jurisdiction.

5. Procedures for closing dedicated channels

a) For the case stipulated in Point a, Clause 1 of this Article, the Vietnam Inland Waterways Administration or the Department of Transport must require organizations or individuals having dedicated channels to temporarily suspend exploitation and transportation and report to the Ministry of Transport or the provincial People's Committee;

b) For the case stipulated in Point b, Clause 1 of this Article, the Ministry of National Defense or the Ministry of Public Security must notify in writing the reasons and closure date to the organizations or individuals having dedicated channels, the Vietnam Inland Waterways Administration or the Department of Transport, and the Ministry of Transport or the provincial People's Committee. The notification period before the required closure date must be at least 30 days;

c) For the case stipulated in Point c, Clause 1 of this Article, organizations or individuals having dedicated channels submit directly one set of documents or by other appropriate means to the Vietnam Inland Waterways Administration (for national channels or dedicated channels connected to national channels) or the Department of Transport (for local channels or dedicated channels connected to local channels);

d) Within ten working days from receiving all required documents, the Vietnam Inland Waterways Administration reviews the documents, if conditions are met, reports to the Ministry of Transport, and the Department of Transport reviews the documents, if conditions are met, reports to the provincial People's Committee. Within ten working days from receiving all required documents and reports from the Vietnam Inland Waterways Administration and the Department of Transport, the Ministry of Transport or the provincial People's Committee issues a decision to announce the closure of the channel within their jurisdiction;

e) Organizations or individuals having dedicated channels are responsible for recovering inland waterway navigation signs within 60 days from the effective date of the decision to close the channel.

6. The decision to announce the closure of channels according to Model No. 05 attached to this Decree must be sent to relevant agencies, organizations, or individuals within two days from the date of signing the decision.

7. Costs for implementing the closure of national and local channels are guaranteed by the state budget from regular expenditure according to budget classification.

8. Costs related to the closure of dedicated channels are borne by the organizations or individuals having dedicated channels, except for the case stipulated in Point b, Clause 1 of this Article, which is borne by the agency proposing the closure.

Article 12. Survey of inland waterway channels

1. Inland waterway channels must be surveyed regularly, periodically, and urgently during exploitation.

2. Responsibility for surveying and creating charts

a) The Vietnam Inland Waterways Administration, Departments of Transport, and organizations or individuals with dedicated channels shall organize surveys, create charts, digitize charts (if applicable), establish, maintain, and provide databases of survey results and charts to serve management, announcement, and exploitation of channels;

b) Organizations or individuals conducting channel surveys must provide survey results to the agency specified in Clause 4, Article 13 of this Decree for channel announcements and bear responsibility for the data and information provided.

3. Funding for channel survey and chart creation

a) Funding for surveys serving national and local channel management and announcements as stipulated in this Decree shall be guaranteed from the state budget's regular expenditure according to budget classification;

b) Organizations or individuals managing dedicated channels shall be responsible for allocating funding for surveys serving management and announcements as stipulated in this Decree.

4. The Ministry of Transport shall specify detailed procedures for inland waterway channel surveys.

Article 13. Announcement of inland waterway channels

1. The announcement of inland waterway channels is a document issued and published by the agency or organization specified in Clause 4 of this Article based on survey results to serve management and provide information and guidance to crew members, drivers, and related organizations and individuals to ensure safe transportation.

2. Content of channel announcements

a) For initial channel announcements before exploitation: Name of the channel, length, coordinates of starting and ending points, mid-channel points; technical grade; shoals on the channel, names of obstructions and river-crossing structures on the channel;

b) For periodic channel announcements: Name of the channel, length, starting and ending points, coordinates of mid-channel points, width, depth, radius of curvature of the channel, technical grade; representative height of shoals on the channel, name and coordinates, height of obstructions and river-crossing structures on the channel that do not meet the waterway dimensions according to the technical grade, water level at the time of survey, and other issues requiring attention;

c) For regular channel announcements: Name of the channel; width and depth of the channel in areas with shoals and obstructions; water level at the time of survey; necessary warnings;

d) For urgent channel announcements: Name of the channel; description of the urgent situation; location (coordinates, mileage, depth, clearance height) of the urgent situation; width and depth of the channel in areas affected by the urgent situation; water level at the time of survey and impact of the urgent situation on transport activities; necessary warnings.

3. Forms of channel announcements

Announcements of inland waterway channels are made in writing; posted on electronic information websites, updated in databases, digital channel route charts (if available) of the announcing agency specified in Clause 4 of this Article or through mass media.

4. Responsibilities for announcements

a) The Vietnam Inland Waterways Administration announces initial national channels and dedicated channels connected to national channels;

b) Regional inland waterways agencies announce periodic, regular, and urgent national channels and dedicated channels connected to national channels;

c) Departments of Transport announce initial, periodic, regular, and urgent local channels and dedicated channels connected to local channels;

d) When there is an urgent situation on a channel affecting traffic safety, the direct managing and maintenance unit of the channel must promptly issue warnings directly in the affected area and report to the Vietnam Inland Waterways Administration, Regional Inland Waterways Agencies, or Departments of Transport.

5. Time for announcing national and local channels: Within two working days from the date of receiving the survey result report, the agency specified in Clause 4 of this Article shall check the data and announce inland waterway channels according to Model No. 06, Model No. 07, and Model No. 08 attached to this Decree;

6. Time for announcing dedicated channels: Organizations or individuals with dedicated channels submit requests for channel announcement publication according to Model No. 09 attached to this Decree to the agency specified in Clause 4 of this Article. Within three working days from the date of receiving the report from the organization or individual with dedicated channels, the responsible agency shall check the data and announce inland waterway channels.

Mục 3. MANAGEMENT OF INVESTMENT IN CONSTRUCTION AND OPERATIONS OF INLAND WATERWAY PORTS, WHARVES, AND ANCHORAGE AREAS

Article 14. General Provisions on Investment in Construction and Operations of Inland Waterway Ports, Wharves, and Anchorage Areas

1\. Investment in construction of inland waterway ports, wharves, and anchorage areas must be carried out in accordance with the laws on investment in construction and the provisions of this Decree.

2\. The water area of inland waterway ports, wharves, and anchorage areas shall not overlap with the navigation channel of inland waterways; the length of the water area of the port and wharf shall not exceed the reach adjacent to the river, canal, or stream that has been approved by the competent authority for the construction of the port and wharf.

3\. Inland waterway ports, wharves, and anchorage areas must be announced for operation by the competent authority in accordance with the law before they are put into exploitation and use. During the operation of inland waterway ports, wharves, and anchorage areas, the investor and the operator must comply with the regulations of the law on inland waterway transport and other relevant laws, and the contents of the announcement decision; vessels, equipment for loading and unloading goods, and equipment for anchoring serving the operations of the port, wharf, and anchorage area must be ensured to meet technical safety requirements.

4\. For inland waterway ports, wharves, and anchorage areas handling dangerous cargo, they must comply with the regulations of the law on the storage and transportation of dangerous goods.

5\. Inland waterway ports, wharves, and anchorage areas that have exceeded their operational period as stated in the announcement decision, if not extended, the port owner, wharf owner, and anchorage area owner must dismantle structures and equipment affecting traffic safety, sweep and clear obstructions in the water area of the port, wharf, and anchorage area within sixty days from the date of expiration of the operational period. The competent authority announcing the operation of the port, wharf, and anchorage area shall coordinate with the People's Committee of the commune, ward, town (hereinafter referred to as the People's Committee at the commune level) to supervise the dismantling of structures and facilities of the port and wharf, sweeping, and clearing obstructions in the water area of the port, wharf, and anchorage area.

6\. The management regulations on investment in construction and operation of inland waterway ports, wharves, and anchorage areas set forth in this Decree shall not apply to inland waterway ports, wharves, and anchorage areas performing defense and security tasks.

Article 15. Agreement on Technical Specifications for Construction of Inland Waterway Ports

1\. Content of Agreement

a\. Location for constructing inland waterway ports;

b\. Functionality of inland waterway ports;

c\. Scale of construction of inland waterway ports.

2. Competent Authority for Agreement

a\. The Ministry of Transport agrees on the technical specifications for constructing inland waterway ports receiving foreign watercraft;

b\. The Vietnam Directorate of Inland Waterways agrees on the technical specifications for constructing inland waterway ports on national inland waterways, dedicated inland waterways connecting to national inland waterways, inland waterway ports having waters and lands both on national inland waterways and local inland waterways, inland waterway ports located in the water area of seaports connected to national inland waterways, except cases stipulated in point a of Clause 2 of this Article and other cases decided by the Ministry of Transport;

c\. The Department of Transport agrees on the technical specifications for constructing inland waterway ports on local inland waterways, dedicated inland waterways connecting to local inland waterways, inland waterway ports located in the water area of seaports connected to local inland waterways, and wharves within the province or centrally governed city, except cases stipulated in point a of Clause 2 of this Article and other cases decided by the Ministry of Transport.

3\. Documents for agreement on technical specifications for construction of inland waterway ports include:

a\. Application for agreement on technical specifications for construction of inland waterway ports according to Model No. 10 attached to this Decree;

b\. Project dossier;

c\. Copy of the approval document for the project's investment orientation issued by the competent authority (if any);

d\. Plan showing the location for constructing inland waterway ports: Displaying place names, location of port, warehouse, yard, water area, river mileage (km), land area, adjacent structures (if any). The water area on the drawing must show the minimum width from the bank edge to the full width of the channel. The plan is established on the national coordinate system VN2000 and national elevation, with a scale of 1/500 to 1/1000.

4\. Documents for agreement on technical specifications for construction of wharves include:

a\. Application for agreement on technical specifications for construction of wharves according to Model No. 10 attached to this Decree;

b) Copy of the approval document for the investment project from the competent authority (if applicable);

c\. Layout plan showing the proposed location for constructing wharves: Displaying place names, location of structures, land area, water area in front of the wharf, river mileage (km) of the river, canal, or stream, and adjacent structures (if any).

5. Procedure for Agreement

a\. Inland waterway ports receiving foreign watercraft

The investor submits two sets of documents directly or through appropriate means to the Vietnam Directorate of Inland Waterways (for inland waterway ports specified in point b of Clause 2 of this Article) and the Department of Transport (for inland waterway ports specified in point c of Clause 2 of this Article) for review. Within five working days from the date of receipt of complete documents as prescribed, the Vietnam Directorate of Inland Waterways and the Department of Transport will review the documents, and if they meet the conditions, send the review report and one set of documents to the Ministry of Transport.

Within five working days from the date of receipt of the review report from the Vietnam Directorate of Inland Waterways or the Department of Transport, the Ministry of Transport seeks opinions from the Ministry of National Defense, the Ministry of Public Security, and the People's Committee at the provincial level regarding the assurance of defense and security for the construction of inland waterway ports; within five working days from the date of receipt of the request document from the Ministry of Transport, the Ministry of National Defense, the Ministry of Public Security, and the People's Committee at the provincial level provide written opinions to the Ministry of Transport. Within five working days from the date of receipt of the unified document from the Ministry of National Defense, the Ministry of Public Security, and the People's Committee at the provincial level, the Ministry of Transport issues the agreement document on technical specifications for construction and sends it to the investor.

b\. Inland waterway ports not receiving foreign watercraft

The investor shall submit one set of documents directly or through other appropriate means to the Vietnam Inland Waterways Administration or the Department of Transport. Within five working days from the date of receiving complete documents as prescribed, the Vietnam Inland Waterways Administration or the Department of Transport shall issue a technical specification agreement document to send to the investor.

c) Inland waterway wharf

The investor shall submit one set of documents directly or through other appropriate means to the Department of Transport. For inland waterway wharfs on national inland waterways or specialized inland waterways connecting with national inland waterways, before issuing the agreement document, the Department of Transport shall seek opinions from the Regional Inland Waterways Management Agency. Within five working days from the date of receipt of the request document from the Department of Transport, the Regional Inland Waterways Management Agency shall issue a reply document. Within five working days from the date of receipt of the document from the Regional Inland Waterways Management Agency, the Department of Transport shall issue a technical specification agreement document to send to the investor.

d) For ports and inland waterway wharfs within the port area waters, before assessing and agreeing on technical specifications for construction, the Vietnam Inland Waterways Administration and the Department of Transport shall seek opinions from the Maritime Port Inspection Office in writing. Within five working days from the date of receipt of the request document, the Maritime Port Inspection Office shall issue a reply document.

6. The validity period of the technical specification agreement document for port and inland waterway wharf construction shall not exceed twenty-four months from the date of signing the document. After the agreement document expires, if the investor has not commenced construction and wishes to continue construction of the port or inland waterway wharf, they must reapply for the technical specification agreement procedure for port and inland waterway wharf construction as stipulated in this Article.

Article 16. Agreement on Technical Specifications for Construction of River Passenger Wharfs and Inland Waterway Wharfs for Main Project Construction

1\. Content of Agreement

a) Location of the wharf construction;

b) Function of the wharf;

c) Scale of the wharf construction.

2. Competent Authority for Agreement

The Department of Transport shall agree on the technical specifications for construction of river passenger wharfs and inland waterway wharfs for main project construction within its provincial or centrally-administered municipal jurisdiction. Based on specific conditions, the Department of Transport may delegate authority to the People's Committee of districts, cities, towns, or counties (hereinafter referred to as district level) to agree on the construction of river passenger wharfs and inland waterway wharfs for main project construction within their respective jurisdictions.

3. Documents for Agreement

a) Request form for agreement on inland waterway wharf construction according to Model No. 10 attached to this Decree;

b) Plan view of the proposed location for inland waterway wharf construction: Showing place names, locations of adjacent works, land and water areas in front of the wharf, river, canal, or creek mileage (km).

4. Procedure for Implementing the Agreement Process

The investor shall submit one set of documents directly or through other appropriate means to the competent authority as specified in Clause 2 of this Article; within five working days from the date of receiving complete documents as prescribed, the competent authority as specified in Clause 2 of this Article shall issue a technical specification agreement document to send to the investor.

5. The validity period of the agreement document shall not exceed twenty-four months for river passenger wharfs and three months for inland waterway wharfs for main project construction. After the agreement document expires, if the investor has not commenced construction of the wharf and wishes to continue construction, they must reapply for the wharf construction agreement process as stipulated in this Article.

6. In cases where a river passenger wharf has one or more counterflow wharf locations in another province or centrally-administered municipality, before agreeing on the construction of the wharf, the competent authority as specified in Clause 2 of this Article must reach consensus with the localities having the counterflow wharfs.

Article 17. Naming and Renaming Inland Waterway Ports, Wharfs, and Mooring Areas

1. Inland waterway ports, wharfs, and mooring areas must be named according to the following principles:

a) Inland waterway ports, wharfs, and mooring areas shall be named when investment projects for construction are established or when they are put into operation;

b) Names of inland waterway ports, wharfs, and mooring areas shall not be duplicated within a provincial administrative unit, nor shall they cause confusion with already announced names or be inconsistent with the name or function of such facilities;

c) The names of state agencies, armed forces units, political organizations, and social-political organizations shall not be used to name or partially name inland waterway ports, wharfs, and mooring areas without the consent of those agencies, units, or organizations;

d) Names of inland waterway ports, wharfs, and mooring areas shall not use terms or symbols that violate historical traditions, culture, ethics, and national customs and practices;

đ) The name of inland waterway ports, wharfs, and mooring areas shall be in Vietnamese, and may include an English name, starting with the phrase "Inland Waterway Port," "Inland Waterway Wharf," or "Mooring Area," followed by the specific name of the port, wharf, or mooring area.

2. When there is a need to rename an inland waterway port, wharf, or mooring area, the port, wharf, or mooring area owner shall submit a request form according to Form No. 11 attached to this Decree to the competent authority specified in Clause 2, Article 15 of this Decree. Within five working days from the date of receipt of the request, the competent authority specified in Clause 2, Article 15 of this Decree shall issue a document approving the renaming of the inland waterway port, wharf, or mooring area.

Article 18. Announcing Operation of Inland Waterway Ports and Wharfs

1. Authority to announce operations The agency responsible for agreeing on technical specifications for constructing inland waterway ports and wharfs as stipulated in Clause 2, Article 15 of this Decree is also the authority responsible for announcing the operation of inland waterway ports and wharfs.

2. Documents for announcing operations of inland waterway ports

a) Request form for announcing operations of inland waterway ports according to Form No. 12 attached to this Decree;

b) Certified copy or un-certified copy and presentation of original for comparison of the approval decision for the investment project for constructing the inland waterway port issued by the competent authority;

c) Certified copy or un-certified copy and presentation of original for comparison of land use documents for constructing the inland waterway port issued by the competent authority;

d) Copy of the decision approving the project or technical design of the inland waterway port construction project;

đ) Completion acceptance record of the construction project put into use; completion drawings of the ground plan, elevation view, and cross-section of the inland waterway port construction project;

e) Record of obstacle clearance survey results in the port waters; confirmation record of signal establishment at the port;

g) Certified copy of the technical safety and environmental protection certificate of pontoons, mooring buoys subject to inspection (if pontoons are used as port bridges);

h) Acceptance document on fire prevention and firefighting by the competent authority as prescribed;

i) Certified copy of the security suitability certificate for foreign inland waterway vessels received by the inland waterway port (for inland waterway ports receiving foreign inland waterway vessels);

k) Certified copy of the decision announcing the opening of dedicated channels by the competent authority (if applicable) for inland waterway ports with dedicated channels.

3. Documents for announcing operations of inland waterway wharfs

a) Request form for announcing operations of inland waterway wharfs according to Form No. 12 attached to this Decree;

b) Certified copy of the decision approving the investment project for constructing the inland waterway wharf issued by the competent authority or un-certified copy and presentation of original for comparison if there is an investment project for construction;

c) Certified copy of land use documents for constructing the inland waterway wharf or un-certified copy and presentation of original for comparison, except for floating wharfs;

d) Certified copy of the decision approving the economic-technical report of the investor (for inland waterway wharfs with an investment project for construction) or exploitation plan of the inland waterway wharf;

đ) Completion acceptance record of the construction project, completion drawings of the ground plan, elevation view, and cross-section of the construction project for inland waterway wharfs with an investment project for construction;

e) Certified copy of the technical safety and environmental protection certificate of floating structures, vessels, pontoons, or mooring buoys subject to inspection (if floating structures, vessels, or pontoons are used as wharf bridges or floating wharfs).

4. Procedure for announcing operations

a) Before putting inland waterway port or wharf construction projects into operation, the port or wharf owner shall directly submit or submit through appropriate means one set of documents to the Vietnam Inland Waterways Administration (for inland waterway ports receiving foreign inland waterway vessels on national inland waterways, dedicated national inland waterways connected to national inland waterways, and inland waterway ports specified in point b, Clause 2, Article 15 of this Decree), or the Department of Transport (for inland waterway ports receiving foreign inland waterway vessels on local inland waterways, dedicated local inland waterways connected to local inland waterways, and inland waterway ports and wharfs specified in point c, Clause 2, Article 15 of this Decree) requesting announcement of operations;

b) For inland waterway ports receiving foreign inland waterway vessels: Within five working days from the date of receipt of complete documents as prescribed, the Vietnam Inland Waterways Administration or the Department of Transport shall review the documents. If conditions are met, they shall report to the Ministry of Transport. Within five working days from the date of receipt of complete documents and the review report, the Ministry of Transport shall issue a decision announcing the operation of the inland waterway port;

c) For inland waterway ports not receiving foreign inland waterway vessels: Within five working days from the date of receipt of complete documents as prescribed, the Vietnam Inland Waterways Administration or the Department of Transport shall issue a decision announcing the operation of the inland waterway port.

d) For inland waterway wharfs: Within five working days from the date of receiving all required documents, the Department of Transport shall issue a decision to announce the operation of the inland waterway wharf.

5. The decision to announce the operation of ports and inland waterway wharfs shall be made according to Model No. 13 attached for implementation with this Decree.

6. The validity period of the decision to announce the operation of ports and inland waterway wharfs shall be based on the request of the port owner but shall not exceed the land use period for constructing the port or inland waterway wharf, or the project's operational period recorded in the investment certificate issued by the competent authority.

7. In cases where an inland waterway port has completed one or more berths and the investor wishes to operate them immediately, the investor must prepare documents in accordance with Clause 2 of this Article to request the competent authority to announce temporary operations. The validity period of the decision to announce temporary operations for the berth shall not exceed one year. This provision does not apply to inland waterway ports that receive foreign watercraft.

8. Announcing an inland waterway port capable of receiving foreign watercraft at an inland waterway port already announced for operation

a) In cases where an inland waterway port has been announced for operation and there is a need to receive foreign watercraft, the port owner must submit a report in writing to the Ministry of Transport; the Ministry of Transport will seek opinions from the Ministry of National Defense, the Ministry of Public Security, and the People's Committee of the province regarding national defense and security for the inland waterway port in accordance with Point a, Clause 5, Article 15 of this Decree. Within two working days from the date of receipt of the unified opinion from the Ministry of National Defense, the Ministry of Public Security, and the People's Committee of the province, the Ministry of Transport shall issue a written approval for the inland waterway port to receive foreign watercraft and send it to the port owner;

b) The port owner submits the application documents for announcing the inland waterway port in accordance with Point a and Point i, Clause 2 of this Article to the Ministry of Transport. Within five working days from the date of receipt of the port owner's documents, the Ministry of Transport shall issue a decision to announce the operation of the inland waterway port capable of receiving foreign watercraft.

9. Announcing the operation of an inland waterway port when there is no longer a need to receive foreign watercraft

a) In cases where an inland waterway port has been announced as capable of receiving foreign watercraft but the port owner no longer needs to receive such vessels, the port owner must submit a written document (specifying the reasons) to the Ministry of Transport. Within five working days from the date of receipt of the port owner's request, the Ministry of Transport shall issue a written approval and send it to the port owner;

b) The port owner submits the application for announcing the inland waterway port in accordance with Point a, Clause 2 of this Article to the Vietnam Directorate of Inland Waterways or the Department of Transport. Within five working days from the date of receipt of the port owner's application, the Vietnam Directorate of Inland Waterways or the Department of Transport shall issue a decision to announce the operation of the inland waterway port that does not receive foreign watercraft and send it to the port owner, simultaneously sending copies to the Ministry of National Defense, the Ministry of Public Security, and the People's Committee of the province for monitoring.

10. The agency responsible for announcing the operation of ports and inland waterway wharfs shall have the responsibility to send the announcement decision to the project investor, the Inland Waterway Port Office (hereinafter referred to as the Port Office), the Maritime Port Office (for ports and inland waterway wharfs within the maritime port area), the People's Committee of the commune where the port and inland waterway wharf are located, and related organizations and individuals within two working days from the date of signing the decision; update information about the announced ports and inland waterway wharfs on the database software of the Vietnam Directorate of Inland Waterways.

Article 19. Announcing the operation of river passenger ferry terminals and inland waterway terminals serving construction projects

1. The authority to announce the operation of river passenger ferry terminals and inland waterway terminals serving construction projects as stipulated in Clause 2 of Article 16 of this Decree shall also be the authority responsible for announcing the operation of such terminals.

2. Documents for announcing the operation

a) A request for announcing the operation according to Model No. 12 attached to this Decree;

b) Technical design documents, completion acceptance records of the project (if applicable), certified copies of land use certificates for building the terminal (for river passenger ferry terminals); certified copies of technical safety and environmental protection certificates of floating structures, vessels, pontoons, or mooring buoys subject to inspection (if using floating structures, vessels, or pontoons as terminals);

3. Procedure for announcing the operation

a) Before putting river passenger ferry terminals and inland waterway terminals serving construction projects into operation, the terminal owner shall submit one set of documents directly or through other appropriate means to the authority specified in Clause 2 of Article 16 of this Decree requesting the announcement of the operation;

b) Within five working days from the date of receiving complete documents as prescribed, the authority specified in Clause 2 of Article 16 of this Decree shall issue a decision announcing the operation of river passenger ferry terminals and inland waterway terminals serving construction projects;

c) The decision announcing the operation of river passenger ferry terminals and inland waterway terminals serving construction projects shall be made according to Model No. 13 attached to this Decree.

4. Validity period of the decision announcing the operation

a) The validity period of the decision announcing the operation of river passenger ferry terminals shall be as requested by the terminal owner but not exceeding the land use period granted by the competent authority;

b) The validity period of the decision announcing the operation of inland waterway terminals serving construction projects shall be as requested by the terminal owner but not exceeding the construction period of the main project.

5. The authority announcing the operation of river passenger ferry terminals and inland waterway terminals serving construction projects shall be responsible for sending the decision announcing the operation to the project investor, the Inland Waterway Transport Service Office, the People's Committee of the commune where the terminal is located, and related organizations and individuals within two working days from the date of signing the decision; and updating information on announced river passenger ferry terminals in the database software of the Vietnam Inland Waterway Administration.

Article 20. Re-announcing and extending the operation of ports and inland waterway terminals

1. Ports and inland waterway terminals must re-announce their operations in the following cases:

a) Changes in the scale or functions of ports and inland waterway terminals;

b) Changes in the land or water areas of ports and inland waterway terminals;

c) Changes in the owners of ports and inland waterway terminals.

2. Authority for re-announcing and extending the operation of ports and inland waterway terminals The authority announcing the operation of ports and inland waterway terminals as stipulated in Clause 1 of Article 18 and Clause 1 of Article 19 of this Decree shall also be the authority responsible for re-announcing and extending the operation of ports and inland waterway terminals.

3. Documents for requesting re-announcement of the operation

a) A request for re-announcing the operation of ports and inland waterway terminals according to Model No. 14 attached to this Decree;

b) Documents as prescribed at Points d, đ, e, g, h of Clause 2 of Article 18 of this Decree for changes in the structure of inland waterway port facilities;

c) Documents as prescribed at Points d, đ, e of Clause 3 of Article 18 of this Decree for changes in the structure of inland waterway terminal facilities;

d) Certified copies or copies accompanied by original documents for verification of the documents issued by the competent authority regarding changes in land or water areas (in the case stipulated in Point b of Clause 1 of this Article);

đ) Certified copies or copies presented with original documents for verification of documents proving changes in the owners of ports and terminals (in the case stipulated in Point c of Clause 1 of this Article).

4. Procedure for re-announcing the operation

a) The port manager shall submit one set of documents directly or through other appropriate means to the Vietnam Inland Waterway Administration or the Department of Transport;

b) For inland waterway ports that do not accept foreign watercraft, and inland waterway terminals, within five working days from the date of receiving complete documents as prescribed, the Vietnam Inland Waterway Administration or the Department of Transport shall issue a decision re-announcing the operation of the port or terminal;

c) For inland waterway ports that accept foreign watercraft, within five working days from the date of receiving complete documents as prescribed, the Vietnam Inland Waterway Administration or the Department of Transport shall review the documents. If conditions are met, they shall report to the Ministry of Transport. Within five working days from the date of receiving complete documents as prescribed and the review report, the Ministry of Transport shall issue a decision re-announcing the operation of the inland waterway port;

d) In the case of a change in the owner of the port or terminal, the new owner of the port or terminal must request a re-announcement of the operation within ten working days from the date of taking over the port or terminal.

5. The decision re-announcing the operation of ports and inland waterway terminals shall be made according to Model No. 13 attached to this Decree, only recording the changed contents in the decision.

6. Extending the operation of ports and inland waterway terminals

a) When the operation period recorded in the decision announcing the operation expires, if the port or terminal owner wishes to continue operating and has been granted an extension of the land use period by the competent authority, the operation may be extended;

b) Documents for requesting an extension of the operation include: A request for extending the operation of the port or terminal; relevant documents concerning the land use for the port or terminal that have been granted an extension of the use period by the competent authority;

c) The port or terminal owner shall submit one set of documents directly or through other appropriate means to the authority announcing the operation of the port or terminal. Within five working days from the date of receiving complete documents as prescribed, the authority announcing the operation of the port or terminal shall issue a document extending the operation of the port or terminal.

7. The agency responsible for re-publishing and extending the operation of inland waterway ports and wharves shall send the decision on re-publishing and the document extending the operation of such ports and wharves to the port and wharf managers, the Inland Waterway Transport Management Office, the People's Committee of the commune where the port and wharf are located, and related organizations and individuals within two working days from the date of signing the decision; update information on the re-published inland waterway ports and wharves on the Vietnam Inland Waterway Transport Administration's port and wharf database software.

Article 21. Quality inspection of inland waterway ports

1. The port owner or the port manager shall be responsible for conducting quality inspections of construction works. The content and procedures for conducting quality inspections of inland waterway port construction works shall be carried out in accordance with the laws on construction quality management and maintenance.

2. The Vietnam Inland Waterway Transport Administration and the Department of Transport shall organize inspections of compliance with regulations on quality inspections of inland waterway ports by managers under their jurisdiction.

Article 22. Repair, dredging, renovation, and upgrading of inland waterway ports and wharves

1. Inland waterway ports and wharves may be renovated and upgraded to change their scale and functions compared to the published decisions and in accordance with approved planning.

2. Before carrying out the renovation and upgrading of inland waterway ports and wharves, the port owner or wharf owner shall directly submit or use other appropriate methods to send a request document to the competent authority specified in Clause 2, Article 15 and Clause 2, Article 16 of this Decree to obtain opinions on the renovation and upgrading of inland waterway ports and wharves. The request document must clearly state the expected scale of the renovation and upgrade project; the time frame for implementing the renovation and upgrade project; the impact of the renovation and upgrade on vessel operations in the water area, cargo handling equipment, and passenger and cargo transportation activities; and adjacent structures.

Within five days from the date of receipt of the request document from the port or wharf owner, the competent authority specified in Clause 2, Article 15 and Clause 2, Article 16 of this Decree shall provide written opinions on the renovation and upgrading of inland waterway ports and wharves.

3. The renovation and upgrading of inland waterway ports and wharves shall be conducted in accordance with the laws on construction. Prior to repairing, renovating, upgrading, or dredging the water area of inland waterway ports and wharves, the port or wharf owner and the port or wharf manager must notify the Port Management Office (specifying the name of the port or wharf; time; scope of repair, renovation, upgrading, and dredging).

Article 23. Upgrading inland waterway wharves to inland waterway ports

1. An inland waterway wharf can be upgraded to an inland waterway port if it meets the following conditions:

a) The inland waterway wharf has been published as operational;

b) It is consistent with the approved planning by the competent authority.

2. Before implementing the upgrade of an inland waterway wharf to an inland waterway port, the inland waterway wharf owner shall directly submit or use other appropriate methods to send a request document to the competent authority specified in Clause 2, Article 15 of this Decree to obtain agreement on the upgrade of the inland waterway wharf. The request document must clearly state the expected scale of the upgrade; the time frame for implementing the upgrade project; the impact of the upgrade on vessel operations in the water area, cargo handling equipment, and passenger and cargo transportation activities; and adjacent structures.

Within five days from the date of receipt of the request document from the inland waterway wharf owner, the competent authority specified in Clause 2, Article 15 of this Decree shall provide written agreements on technical specifications for upgrading the inland waterway wharf to an inland waterway port.

3. The renovation and upgrading of inland waterway wharves shall be conducted in accordance with the laws on construction. Prior to renovating or upgrading an inland waterway wharf, the wharf owner and the wharf manager must notify the Port Management Office (specifying the name of the inland waterway wharf; time; scope of renovation and upgrade).

4. After completing the renovation and upgrade, the wharf manager must carry out the procedures for publishing the inland waterway port according to the provisions of Article 18 of this Decree. In cases where the inland waterway wharf meets the technical specifications and scale suitable for the technical level of an inland waterway port (without implementing construction projects), the application documents for publishing the inland waterway wharf as an inland waterway port shall be as follows:

a) A request form for converting an inland waterway wharf to an inland waterway port according to Model No. 15 attached to this Decree;

b) Written agreements on technical specifications from the competent authority regarding the upgrade of the inland waterway wharf to an inland waterway port;

c) As-built drawings of the inland waterway wharf;

d) Layout plans of the construction site, land, and water areas of the inland waterway wharf;

đ) Actual inspection and calculation reports of the inland waterway wharf conducted by a consulting entity with legal status.

Article 24. Closure and Temporary Suspension of Inland Waterway Ports and Wharfs

1. Inland waterway ports and wharfs shall be announced for closure in the following cases:

a) For reasons of ensuring national defense and security;

b) At the request of the port or wharf owner.

2. Authority to Announce Closure of Inland Waterway Ports and Wharfs The agency responsible for the operation of inland waterway ports and wharfs as stipulated in Clause 1, Article 18 and Clause 1, Article 19 of this Decree is also the authority with the power to announce the closure of inland waterway ports and wharfs.

3. Documents for Announcing Closure of Inland Waterway Ports and Wharfs

a) A proposal document from the Ministry of National Defense or the Ministry of Public Security in the case specified in Point a, Clause 1 of this Article;

b) A request for closure of the inland waterway port or wharf from the port or wharf owner in the case specified in Point b, Clause 1 of this Article.

4. Procedures for Announcing Closure of Inland Waterway Ports and Wharfs

a) The Ministry of National Defense or the Ministry of Public Security must notify the port or wharf manager at least 60 days before the expected closure date in the case specified in Point a, Clause 1 of this Article. The notification must clearly state the reason for closing the port or wharf. Within 10 days of receiving the notification, the port or wharf manager has the right to make recommendations and negotiate regarding the closure of the port or wharf with the issuing agency;

b) The Ministry of National Defense, the Ministry of Public Security, and the port or wharf owner send the proposal or request for closure of the port or wharf to the competent authority as stipulated in Clause 2 of this Article;

c) Within five working days from the date of receipt of the proposal or request from the agency or the port or wharf owner as stipulated in Point b of this clause, the competent authority issues a decision to announce the closure of the port or wharf;

d) The decision to announce the closure of the port or wharf follows Model No. 16 attached to this Decree;

đ) The agency issuing the decision to announce the closure of the port or wharf must send the decision to the port or wharf owner, the Port Management Unit, the People's Committee of the commune where the port or wharf is located, relevant organizations and individuals, and the Ministry of National Defense and the Ministry of Public Security (in the case specified in Point a, Clause 1 of this Article) within two working days from the date of signing, and remove the name of the port or wharf from the registry of port and wharf management.

5. Within thirty working days from the effective date of the decision to announce the closure of the port or wharf, the port or wharf owner is responsible for clearing obstacles in the port or wharf water area (if any), dismantling inland waterway navigation signals of the port or wharf. The cost of clearing obstacles in the port or wharf water area (if any) and dismantling inland waterway navigation signals of the port or wharf shall be borne by the port or wharf owner, except in the case of closure of the port or wharf as specified in Point a, Clause 1 of this Article, which shall be borne by the requesting agency.

6. Inland waterway ports and wharfs must suspend operations in the following cases:

a) When the facility exceeds its service life;

b) When the facility encounters an incident posing a risk to the safety of the facility, people, and vessels; affecting the safety of adjacent facilities, the environment, and the community as prescribed.

7. Temporary Suspension of Operations of Inland Waterway Ports and Wharfs

a) The port or wharf manager must notify the Port Management Unit in writing about the temporary suspension of operations of the port or wharf in the cases specified in Clause 6 of this Article;

b) Upon receiving the notification from the port manager in the case specified in Point a, Clause 6 of this Article, the Port Management Unit is responsible for notifying relevant agencies and units about the temporary suspension of operations of the port or wharf;

c) Upon receiving the notification from the port or wharf manager in the case specified in Point b, Clause 6 of this Article, the Port Management Unit is responsible for sending a document to the port or wharf manager requiring them to stop operating the port or wharf to repair damage or incidents, and simultaneously notifying relevant agencies and units about the temporary suspension of operations of the port or wharf;

d) The port or wharf may only resume operations once the incident has been resolved or the risks to safety have been eliminated and confirmed by the Port Management Unit;

đ) In the case where the port facility exceeds its service life and there is a need to continue using it, the port or wharf manager must conduct quality inspection of the facility, carry out repairs or renovations (if necessary) to ensure the safety and functionality of the facility, and request announcement of its operation according to this Decree.

Article 25. Establishment of Mooring Areas

1. Content of Agreement for Establishing Mooring Areas

a) Location and scope of the mooring area;

b) Purpose of use;

c) Scale of construction area (scope, mooring equipment).

2. Competent Authority for Agreeing to Establish Mooring Areas

a) The Vietnam Inland Waterway Administration agrees to establish mooring areas on national inland waterways, specialized inland waterways connecting with national inland waterways, mooring areas with waters both on national inland waterways and local inland waterways, and other cases decided by the Ministry of Transport;

b) The Department of Transport agrees to establish mooring areas on local inland waterways, specialized inland waterways connecting with local inland waterways, and other cases decided by the Ministry of Transport.

3. Documents for Agreeing to Establish Mooring Areas

a) Request form for agreeing to establish a mooring area according to Model No. 17 attached to this Decree;

b) Copy of the approval document for investment orientation from the competent authority;

c) Map of the proposed mooring area zone: must show the scope of the mooring area, bottom elevation, channel location, adjacent structures (if any) on the national coordinate system VN2000 and national height system, scale of the drawing from 1/500 to 1/2,000.

4. Procedure for Agreeing to Establish Mooring Areas

a) Before establishing a mooring area, the investor submits one set of documents directly or through appropriate means to the competent authority specified in Clause 2 of this Article requesting agreement to establish a mooring area;

b) Within five working days from the date of receiving complete documents as prescribed, the competent authority specified in Clause 2 of this Article issues an agreement document for establishing a mooring area and sends it to the investor.

Article 26. Announcement of Mooring Area Operations

1. Competent Authority for Announcing Mooring Area Operations The authority agreeing to establish a mooring area as stipulated in Clause 2 of Article 25 of this Decree is also the authority responsible for announcing mooring area operations.

2. Documents for Announcing Mooring Area Operations

a) Request form for announcing mooring area operations according to Model No. 18 attached to this Decree;

b) Acceptance certificate for completed works put into use;

c) Map of the mooring area zone;

d) Certificate of technical safety and environmental protection for buoys (if buoys are used);

e) Acceptance record of obstacle clearance survey.

3. Procedure for Announcing Mooring Area Operations

a) The investor submits one set of documents directly or through appropriate means to the competent authority specified in Clause 1 of this Article requesting announcement of mooring area operations;

b) Within five working days from the date of receiving complete documents as prescribed, the competent authority issues a decision announcing mooring area operations;

c) Decision announcing mooring area operations according to Model No. 19 attached to this Decree. The authority announcing mooring area operations is responsible for sending the decision announcing operations to the investor, Port Management Unit, Regional Inland Waterway Management Office, and related organizations and individuals within two working days from the date of signing the decision.

4. In necessary cases, the Vietnam Inland Waterway Administration and the Department of Transport may decide to establish and announce operations of mooring areas to serve vessels anchoring and avoiding storms and floods on inland waterways under their management. Prior to announcing mooring area operations, the Vietnam Inland Waterway Administration and the Department of Transport must conduct surveys and prepare documents as stipulated in Points b, c, d, and e of Clause 2 of this Article.

Article 27. Announcement of Closure of Mooring Areas

1. A mooring area shall be announced closed in the following cases:

a) For reasons of ensuring national defense and security;

b) For reasons to ensure traffic safety;

c) At the proposal of the investor.

2. Authority for Announcing the Closure of Mooring Areas

The agency responsible for announcing the operation of mooring areas as stipulated in Clause 1, Article 26 of this Decree shall concurrently have the authority to announce the closure of mooring areas.

3. Documents for Announcing the Closure of Mooring Areas

a) Documents from the Ministry of National Defense and the Ministry of Public Security for the case specified in point a, Clause 1 of this Article;

b) The investor's application for closing the mooring area for the case specified in point b, Clause 1 of this Article. The application follows Model No. 20 attached to this Decree;

c) Records of completion of signal recovery and mooring equipment; records of completion of sweeping obstacles in the water area of the mooring area.

4. Procedures for Announcing the Closure of Mooring Areas

a) For the case specified in point a, Clause 1 of this Article: The Ministry of National Defense and the Ministry of Public Security notify the investor at least 60 days before the planned closure date of the mooring area. The notification must clearly state the reason for closing the mooring area. If there is no objection from the investor, the Ministry of National Defense and the Ministry of Public Security send a document to the agency specified in Clause 2 of this Article;

b) For the case specified in point b, Clause 1 of this Article: The Vietnam Inland Waterway Administration and the Department of Transport notify the survey, record the current status of the mooring area that does not ensure traffic safety due to changes in inland waterway routes with the participation of the investor; request the investor to temporarily stop operating the mooring area;

c) For the case specified in point c, Clause 1 of this Article: The investor submits an application for closing the mooring area directly or through other appropriate means to the agency specified in Clause 2 of this Article requesting the announcement of the closure of the mooring area;

d) Within five working days from the date of receipt of the document from the Ministry of National Defense and the Ministry of Public Security or the record of the survey of the current status of the mooring area or the application of the investor, the competent agency specified in Clause 2 of this Article issues a decision to announce the closure of the mooring area.

5. The decision to announce the closure of the mooring area follows Model No. 21 attached to this Decree. The agency responsible for announcing the closure of the mooring area has the responsibility to send the decision to announce the closure of the mooring area to the investor, the Port Management Unit, and related organizations and individuals within two days from the date of signing the decision.

6. Within fifteen working days from the date of receipt of the decision to announce the closure of the mooring area, the investor is responsible for recovering signals, mooring equipment, and sweeping obstacles in the water area of the mooring area. For the case specified in point a, Clause 1 of this Article, the costs for recovering signals, mooring equipment, and sweeping obstacles in the water area of the mooring area shall be borne by the agency proposing the closure of the mooring area.

Section 4 MANAGEMENT OF SIGNALS AND OTHER CONSTRUCTIONS BELONGING TO THE INFRASTRUCTURE OF INLAND WATERWAYS

Article 28. Establishment and Maintenance of Signals on Inland Waterways

1. Establishing signals on inland waterways is the act of agencies, organizations, and individuals installing signals on inland waterways, at the location of works, obstacles, and areas with activities affecting the safety of inland waterway traffic. Established signals must comply with national technical standards for inland waterway signals in Vietnam.

2. Works on inland waterways must establish signals, including:

a) Inland waterway channels;

b) Ports, inland waterway wharves, mooring areas;

c) Ship basins, structures for passing dams, waterfalls;

d) Dikes, dams, bridges, ferry terminals, fishing ports;

đ) Wind power plants, thermal power plants, hydroelectric power plants;

e) Structures crossing over the air or under the bottom of the channel;

g) Obstacles;

h) Floating restaurants, floating hotels (when moored);

i) Other works.

3. Activities on inland waterways must establish signals, including:

a) Construction activities; exploration, exploitation of natural resources, minerals;

b) Aquaculture and marine farming areas (fish cages, fish pens, fish beds, aquaculture and marine farming areas); organizing entertainment, sports, parades, festivals; markets, craft villages; training activities on inland waterways, protection zones of channels, waters outside the channel range with transport activities or within port and inland waterway wharf waters;

c) Areas organizing traffic regulation, permanent anti-drift support, traffic restriction;

d) Other activities affecting the safety of inland waterway traffic.

4. Responsibility for Approving Signal Plans and Establishing and Maintaining Signals on Inland Waterways

a) The Vietnam Inland Waterway Administration is responsible for approving signal plans and organizing the establishment and maintenance of the signal system on national channels;

b) The Department of Transport is responsible for approving signal plans and organizing the establishment and maintenance of the signal system on local channels;

c) Organizations and individuals with dedicated channels are responsible for establishing and maintaining the signal system on dedicated channels;

d) The owner of the work, organization, or individual causing obstacles; organizations and individuals organizing activities on inland waterways are responsible for establishing and maintaining signals according to regulations throughout the construction period of the work, organization of activities, and the existence period of the work and obstacles;

đ) Units managing and maintaining inland waterways, organizations, and individuals managing dedicated inland waterways are responsible for establishing signals in cases where vessels sink due to accidents, other unexpected situations causing traffic safety hazards on channels and protection zones. They also report immediately to the Regional Inland Waterway Management Agency or the Department of Transport.

5. Costs for Establishing Signals on Inland Waterways

a) Funding for establishing and maintaining the signal system on national channels and local channels, except for signals specified in point e of this clause, is guaranteed by the state budget according to the budget classification;

b) Funding for establishing and maintaining the signal system on dedicated channels is borne by the organization or individual with dedicated channels;

c) Funding for establishing and maintaining signals at works, obstacles, and activity areas specified in point d, Clause 4 of this Article is borne by the owner of the work, obstacle, organization, or individual organizing the activity.

d) For traffic signs at waterway works funded from the state budget within the management scope of the Ministry of Transport on national inland waterways, after completing the installation of signs, the project investor shall hand over the sign assets to the Vietnam Inland Waterways Administration for management and maintenance in accordance with regulations.

đ) For traffic signs at works funded from the state budget within the management scope of the provincial People's Committee on local inland waterways, after completing the installation of signs, the project investor shall hand over the sign assets to the Department of Transport for management and maintenance in accordance with regulations.

6. The Minister of Transport shall issue national technical standards for traffic signs on Vietnam's inland waterways.

Article 29. Competence and procedures for agreeing on the establishment of traffic signs on inland waterways for construction works and activities

1. The following signs must be agreed upon before establishment:

a) Special-purpose channel signs;

b) Signs for works specified in points d, đ, e of Clause 2 and those stipulated in Clause 3 of Article 28 of this Decree.

2. Competence for agreeing on the establishment of signs

a) The Regional Inland Waterways Office agrees on the establishment of special-purpose channel signs connecting to national channels, works, and activity areas specified in point b of Clause 1 of this Article on national inland waterways and special-purpose inland waterways connecting to national inland waterways, except for signs established at ports and inland waterway terminals.

b) The Department of Transport agrees on the establishment of special-purpose channel signs connecting to local channels, works, and activity areas specified in point b of Clause 1 of this Article on local inland waterways and special-purpose inland waterways connecting to local inland waterways.

3. Content of Agreement

a) Location of signs;

b) Quantity and size of signs;

c) Type of signs.

4. Documents for agreeing on the establishment of signs

a) A request for agreement on the establishment of signs according to Model No. 22 attached to this Decree;

b) A schematic diagram of the proposed sign location.

5. Procedure for Agreement

a) Organizations or individuals establishing signs submit one set of documents directly or through postal service or other appropriate means to the competent authority as stipulated in Clause 2 of this Article;

b) Within five working days from the date of receiving complete documents as prescribed, the competent authority as stipulated in Clause 2 of this Article shall send a document agreeing on the establishment of signs to the project investor.

c) Organizations or individuals managing special-purpose inland waterways have the responsibility to notify the establishment and put signs into use on special-purpose channels according to Model No. 23 attached to this Decree.

Article 30. Investment in constructing other works belonging to the infrastructure of inland waterways

Investment in building berths, works for passing ships through dams and waterfalls; revetments, traffic dams; high-water marks, coordinate marks, channel protection zone boundary marks, watch stations, and auxiliary works must comply with laws on investment construction, fire prevention, environmental protection, and climate change response; have suitable technological plans and designs ensuring quality and safety during construction, operation, exploitation, and use of the works.

Section 5 PROTECTION OF STRUCTURES IN THE INFRASTRUCTURE OF INLAND WATERWAYS

Article 31. General Provisions on Protection of Structures in the Infrastructure of Inland Waterways

1. Structures in the infrastructure of inland waterways must be protected to maintain their normal operation in accordance with the Law on Navigation in Inland Waterways and this Decree. Acts of encroachment, demolition, dredging, dismantling of the infrastructure of inland waterways contrary to regulations must be promptly detected, prevented, and dealt with according to the provisions.

2. Before putting structures in the infrastructure of inland waterways into operation and use, the project investor shall have the responsibility to notify in writing to the People's Committee of the commune where the structure is located for cooperation in protecting the structure. The notification content must clearly state the name of the structure, its scale, function, and the time of putting the structure into operation and use.

Article 32. Contents of Protection of Structures in the Infrastructure of Inland Waterways

1. Contents of protection of structures in the infrastructure of inland waterways as prescribed by the Law on Navigation in Inland Waterways and this Decree.

2. Protection of channels of inland waterways

a) Channels that are announced and put into use must be maintained according to design standards or channel standards based on technical levels and the ability to allocate state budget funds;

b) Structures above, under, and on the surface of the water must ensure safe depths according to published technical standards for inland waterways;

c) Within the channel area, fixed fishing gear and unauthorized mineral extraction activities are not allowed;

d) It is not permitted to dump soil, mud, sand, or other waste materials that cause sedimentation and change the bottom elevation of the channel.

3. Protection of the channel protection zone

a) The size of the channel protection zone must be maintained, and it cannot be narrowed or illegally encroached upon;

b) Within the channel protection zone, construction of houses and other structures, resource exploitation without approval from competent authorities, and placement of fixed fishing gear within the channel protection zone are prohibited;

c) When the channel changes into the channel protection zone, structures, mining, aquaculture, craft villages, floating markets must be relocated, reduced in scope, or cleared of obstructions within the new channel area.

4. For other structures in the infrastructure of inland waterways, the following actions are not allowed:

a) Storing materials, vessels, equipment causing erosion or damage to the structure;

b) Anchoring or tying vessels or animals to navigation aids, markers, water level marks, survey marks, boundary marks of the channel protection zone;

c) Using explosives or unauthorized mineral extraction activities or other acts affecting the structure;

d) Discharging harmful substances affecting the durability and lifespan of the structure.

Article 33. Scope of the Channel Protection Zone

The scope of the channel protection zone is determined from the edge of the channel outward on each side. For channels already included in approved plans, the scope is determined according to the technical level of the plan, specifically as follows:

1. Scope of the channel protection zone when the channel does not abut the shore

a) For inland waterway channels on lakes, bays, river mouths to the sea, coastal areas, and special-grade channels: from 20 meters to 25 meters;

b) For first and second-grade inland waterway channels: from 15 meters to 20 meters;

c) For third and fourth-grade inland waterway channels: from 10 meters to 15 meters;

d) For fifth and sixth-grade inland waterway channels: 10 meters.

2. Scope of the channel protection zone when the channel abuts the shore is calculated from the natural shoreline inward at least 5 meters; in cases where the channel passes through urban areas, cities, or towns, the scope of the channel protection zone is the red line according to the approved planning.

3. Based on the characteristics of each area, the Vietnam Inland Waterways Administration, in coordination with the Department of Transport, shall work with the Department of Natural Resources and Environment to determine the specific natural shoreline for the protection of the infrastructure of inland waterways.

4. If the scope of the channel protection zone overlaps with the safety zone of road bridges and railway bridges, the scope of the channel protection zone is measured from the edge of the channel to the natural shoreline and implemented according to the laws on protecting the safety zones of road bridges and railway bridges.

5. If the scope of the channel protection zone overlaps with the protection zone of maritime channels, it shall be implemented according to the laws on protecting maritime channel protection zones.

6. If the scope of the channel protection zone overlaps with the protection zones of flood prevention works, dyke protection works, and water conservancy works, it shall be implemented according to the laws on flood prevention, dyke protection, and the laws on the exploitation and protection of water conservancy works.

7. If the scope of the channel protection zone overlaps with the safety zone for water source protection, it shall be implemented according to the laws on protecting the channel protection zone.

8. When establishing a new investment project or upgrading and expanding inland waterway channels, the project investor must base the technical grade of the inland waterway channel on the infrastructure plan, simultaneously determine the scope of the channel protection zone, and implement boundary markers after completing the project.

Article 34. Management of Navigation Channel Protection Zones

1. Establishing management files for navigation channel protection zones

a) The management file for navigation channel protection zones must update structures affecting inland waterway safety, scope, appearance time, and handling process; boundary markers of the navigation channel protection zone;

b) The Vietnam Inland Waterways Administration organizes the establishment of management files for national navigation channel protection zones, the Department of Transport organizes the establishment of management files for local navigation channel protection zones, organizations and individuals with dedicated channels establish management files for dedicated channel protection zones.

2. When the navigation channel protection zone changes, the Vietnam Inland Waterways Administration, the Department of Transport, organizations, and individuals with dedicated channels must notify the owners of structures, organizations, and individuals engaged in activities on inland waterways to carry out relocation, narrowing, or removal of obstructions.

3. Organizations and individuals managing channels must implement boundary marker installation for navigation channel protection zones and inform the People's Committee of the commune where the boundary markers are located to coordinate in protection.

Article 35. Responsibilities for protecting infrastructure works within inland waterway transport systems

1. Organizations and individuals entrusted with managing works have the responsibility to take the lead and cooperate with People's Committees at all levels to protect infrastructure works within inland waterway transport systems.

2. Organizations and individuals who discover damage to infrastructure works within inland waterway transport systems must promptly report to the nearest People's Committee of the commune, inland waterway management unit, or police agency. Upon receiving the report, the relevant agencies and units must require the owner of the work to promptly implement measures to ensure smooth and safe transportation.

Chapter III MANAGEMENT OF INVESTMENT AND CONSTRUCTION OF WORKS NOT BELONGING TO INFRASTRUCTURE OF INLAND WATERWAY TRANSPORT ON INLAND WATERWAYS

Article 36. General provisions on investment and construction of works not belonging to infrastructure of inland waterway transport and related activities

1. Projects for construction not belonging to infrastructure of inland waterway transport and activities stipulated in Clauses 2 and 3 of this Article that relate to inland waterway traffic, navigation channel protection zones, or within port waters, inland waterway wharves, anchorage areas must agree with the competent authority specified in Clause 1 of Article 37 of this Decree when establishing investment projects and organizing activities.

2. Construction works include:

a) Works serving defense and security tasks;

b) Riverbank protection structures, hydropower dams, bridges, ferry terminals;

c) Wind power, thermal power, hydroelectric power plants;

d) Structures crossing over or under the navigation channel;

e) Other structures affecting inland waterway traffic safety.

3. Activities include:

a) Construction work activities (including dredging in port waters, inland waterway wharves, anchorage areas); resource exploitation, mineral extraction;

b) Aquaculture and marine farming areas (fish cages, fish pens, floats, fish beds, aquaculture and marine farming sites); organization of recreational, entertainment, drill, sports, festival activities; market fairs, craft villages, vocational training practices;

c) Other activities affecting inland waterway traffic safety.

Article 37. Competence to agree on matters related to inland waterways for works not belonging to inland waterway infrastructure and activities on inland waterways

1. Competence to agree

a) The Ministry of Transport shall agree on works and defense and security activities related to inland waterway traffic on national inland waterways and specialized inland waterways connected to national inland waterways;

b) Provincial People's Committees shall agree on works and defense and security activities related to inland waterway traffic on local inland waterways and specialized inland waterways connected to local inland waterways;

c) The Vietnam Inland Waterways Administration shall agree on matters related to inland waterways for works and activities on national inland waterways, specialized inland waterways connected to national inland waterways, and navigation channel protection zones, except in cases provided for in point a of this Clause;

d) Departments of Transport shall agree on matters related to inland waterways for works and activities on local inland waterways, specialized inland waterways connected to local inland waterways, and navigation channel protection zones, except in cases provided for in point b of this Clause.

đ) Harbor Supervision Services, Departments of Transport (where there is no Harbor Supervision Service) shall agree on dredging and improvement activities in port waters, inland waterway wharves, anchorage areas within their management scope.

2. Content of agreement

a) For permanent bridges, temporary bridges: location, dimensions of navigable clearance (width, height above waterline);

b) For rotating bridges, lifting bridges, floating bridges, hydropower works combined with transportation: location, dimensions of navigable clearance (width, height above waterline, length, depth of berth sill);

c) For overhead power lines, pipelines, structures crossing over channels: location, clearances of power lines, pipelines, structures crossing over channels;

d) For underground works, pipelines, power lines under the channel bottom: location; depth to top of underground works, pipelines, power lines;

đ) For construction sites, resource exploitation areas, mining areas: location, extent of the exploitation area, dredging depth, mining elevation;

e) Aquaculture areas, marine farming areas, fixed fishing gear placement areas; training practice activities; floating restaurant and hotel placement areas; market areas, craft villages, entertainment areas: location, extent of activities.

Article 38. Procedures for agreeing on matters related to inland waterways for works not belonging to inland waterway infrastructure and activities on inland waterways

The project investor for construction works, organizations, individuals organizing activities shall submit one set of application documents directly or through appropriate means to the competent authority specified in Clause 1 of Article 37 of this Decree to agree on matters related to inland waterways. The application includes:

1. A request for agreement on construction work according to Model No. 24 attached to this Decree.

2. Cross-section drawings of the work showing on cross-sectional river views.

3. Drawings of the construction site area on the national coordinate system VN2000, national elevation system. On the drawing, show the location of the work and natural elevations, terrain, objects of the river, canal in the construction area, adjacent works (if any) and the following documents:

a) For permanent bridges, temporary bridges: data on navigable clearance dimensions (location, width, height above waterline); longitudinal section drawings of the work shown on cross-sectional river, canal views;

b) For rotating bridges, lifting bridges, floating bridges, lift bridges, hydropower works combined with transportation: data on navigable clearance dimensions (location, width, height above waterline, length, depth of berth sill); operation plan and technology; design drawings of the location, expected water area for vessel anchorage while waiting to pass the work;

c) For pipelines, power lines, structures crossing over channels: drawings, data on clearances, showing the highest point of the pipeline, power line (lowest point of the power line including safety clearance of the power grid), structure crossing over the channel;

d) For underground works, power lines, pipelines under the channel bottom: drawings showing distance, elevation of the top of the work to the designed channel bottom elevation, channel range and inland waterway navigation channel protection zone;

đ) For dam works, hydropower plants, irrigation works: plans and drawings of the port, inland waterway wharf or cargo transfer area upstream and downstream of the work; loading and unloading plans;

e) For defense and security works; wind power, thermal power works; ferry terminals, revetments: drawings showing the layout of the port area; revetment structures, other rectification works; dimensions, structures of wharves, revetments, other rectification works and auxiliary works; port water areas.

4. For activities specified in Clause 3 of Article 36 of this Decree, the application includes:

a) A request for agreement according to Model No. 24 attached to this Decree;

b) Drawings showing the activity area range, channel range and inland waterway navigation channel protection zone, distance to related works in the area and traffic safety signal arrangement plan;

c) Cross-sectional drawings and marker records to determine the range, dredging depth, resource and mineral exploitation depth (for dredging and improvement activities in port waters, inland waterway wharves, dedicated channel entrances to ports, inland waterway wharves, anchorage areas; resource and mineral exploitation).

5. Within five working days from the date of receipt of complete application documents as prescribed, the competent authority specified in Clause 1 of Article 37 of this Decree shall issue an agreement letter to the project investor.

Article 39. Notification of Putting Non-Inland Waterway Infrastructure Works into Operation

1. Within five working days from the date of completion acceptance of the works for operation, the project investor shall send a written notification to the Inland Waterway Administration Region (for works on national inland waterways, navigation channel protection zones, areas outside the scope of national channels, specialized inland waterways connecting with national inland waterways) and the Department of Transport (for works on local inland waterways, navigation channel protection zones, areas outside the scope of local channels, specialized inland waterways connecting with local inland waterways).

2. Content of the notification

a) Name of the work;

b) Location (mileage, place name, coordinates);

c) Main parameters of the work;

d) Time of commencement of exploitation.

3. The notification of putting non-inland waterway infrastructure works into operation shall be made according to Model No. 25 attached to this Decree.

Chapter IV SAFETY AND SECURITY GUARANTEES, ENVIRONMENTAL PROTECTION IN INLAND WATERWAY ACTIVITIES

Section 1 SAFETY GUARANTEES IN INLAND WATERWAY ACTIVITIES

Article 40. Safety Guarantees in Cases of Restricted Traffic

1. Cases of restricted traffic on inland waterways include:

a) Obstacles on the channel causing hindrance to traffic;

b) Construction of works on the channel, navigation channel protection zones, port waters, inland waterway berths, anchorage areas, and unorganized waters with transport activities that create situations affecting traffic safety;

c) Works on inland waterways limiting the channel standards already published;

d) Disaster prevention and rescue operations;

đ) National defense and security activities;

e) Exercise, sports, festival, entertainment, vocational training practice, market, craft village activities.

2. Authority to announce restricted traffic

a) The Vietnam Inland Waterway Administration announces restricted traffic for cases ensuring national defense and security on national inland waterways, specialized inland waterways connecting with national inland waterways, and unorganized waters with transport activities adjacent to national navigation channel protection zones;

b) The Inland Waterway Administration Region announces restricted traffic for cases stipulated in Clause 1 of this Article on national inland waterways, specialized inland waterways connecting with national inland waterways, and unorganized waters with transport activities adjacent to national navigation channel protection zones, except for cases stipulated in point a of this Clause;

c) The Department of Transport announces restricted traffic for cases stipulated in Clause 1 of this Article on local inland waterways, specialized inland waterways connecting with local inland waterways, and unorganized waters with transport activities within the province or centrally-administered city, except for waters stipulated in points a and b of this Clause;

d) The Port Office announces restricted traffic in port waters, inland waterway berths, and anchorage areas under its management.

3. Procedures for announcing restricted traffic on inland waterways

a) Before commencing construction of works or organizing activities on inland waterways, the project investor or the organization or individual conducting the construction work or organizing the activity shall submit a written request for announcement of restricted traffic on inland waterways (clearly stating the location and time of restricted construction) and the approved traffic safety assurance plan to the competent authority specified in Clause 2 of this Article;

b) Within five working days from the date of receipt of complete files as prescribed, the competent authority specified in Clause 2 of this Article shall issue a written announcement of restricted traffic on inland waterways to the project investor or the organization or individual;

c) In case of sudden obstacles; disaster prevention and rescue activities on inland waterways that limit the published channel standards, the competent authority specified in Clause 2 of this Article shall determine measures to ensure traffic safety based on actual requirements and announce restricted traffic on inland waterways.

4. The Minister of Transport shall provide detailed regulations on traffic control, collision avoidance, and restricted traffic on inland waterways.

Article 41. Traffic Safety Assurance Plan for Inland Waterway Transport

1. Projects constructing works or areas of operation related to inland waterway transport (on channels, channel protection zones, port waters, inland waterway wharfs, anchorage areas, and unorganized waters with transportation activities) as stipulated in Clause 2 and Clause 3, Article 36 of this Decree must have plans and measures to ensure traffic safety throughout the construction period of the work and during the organization of operations.

2. Responsibility for Establishing and Implementing the Plan The project investor or construction contractor, organizations, or individuals organizing activities related to inland waterway transport shall be responsible for establishing and implementing the traffic safety assurance plan that has been approved by the competent authority.

3. Authority to Approve the Traffic Safety Assurance Plan

a) The Vietnam Inland Waterways Administration shall approve the traffic safety assurance plan for works and activities ensuring national defense and security on national inland waterways and specialized inland waterways connected to national inland waterways;

b) The Regional Inland Waterways Management Office shall approve the traffic safety assurance plan for works and activities on national inland waterways; specialized inland waterways connected to national inland waterways, and unorganized waters with transportation activities adjacent to national channel protection zones, except in cases provided for in point a and point d of this clause;

c) The Department of Transportation shall approve the traffic safety assurance plan for works and activities on local inland waterways; specialized inland waterways connected to local inland waterways, and unorganized waters with transportation activities within the province or centrally governed city, except in cases provided for in point d of this clause. Based on actual circumstances, the Department of Transportation shall submit to the provincial People's Committee for authorization and delegation to the district People's Committee to approve the traffic safety assurance plan;

d) The Port Management Office shall approve the traffic safety assurance plan for repair, renovation, upgrading, and other activities within port waters, inland waterway wharfs, and anchorage areas under its management.

4. Content of the Traffic Safety Assurance Plan

a) General information about the work, investment construction projects, and organized activities;

b) Construction and activity implementation timeframes;

c) Construction and activity implementation plans;

d) Measures to ensure traffic safety;

đ) Organization and coordination plan for traffic safety assurance.

5. Documents for Requesting Approval of the Traffic Safety Assurance Plan

a) Application for approval of the traffic safety assurance plan according to Model No. 26 attached to this Decree;

b) Construction plan, construction time, and progress schedule for the work, and organized activities;

c) Traffic safety assurance plan;

d) Copy of the overall layout drawing of the work, construction area, and organized activity area.

6. Approval Procedure

a) Before commencing construction of the work or organizing activities as stipulated in Clause 1 of this Article, the project investor or organization or individual shall submit one set of documents directly or through appropriate means to the competent authority specified in Clause 3 of this Article requesting approval;

b) Within five working days from the date of receipt of complete documents as prescribed, the competent authority specified in Clause 3 of this Article shall issue a document approving the traffic safety assurance plan to the project investor or organization or individual.

7. In case of accidents or incidents on inland waterways due to force majeure causing traffic disruption, the Vietnam Inland Waterways Administration or the Department of Transportation or organizations or individuals with dedicated channels must promptly organize the establishment and implementation of a traffic safety assurance plan at the accident or incident site.

8. Ensuring traffic safety for dredging activities in inland waterway channels, port waters, inland waterway wharfs, and anchorage areas shall be carried out in accordance with the Government's regulations on dredging inland waterway waters.

Mục 2 ||| SECTION 2 ENSURING SECURITY AT INLAND WATERWAY PORTS RECEIVING FOREIGN WATERBORNE VESSELS AND DOMESTIC INLAND WATERWAY TRAFFIC

Article 42. Ensuring security at inland waterway ports receiving foreign waterborne vessels

1. Ensuring security at inland waterway ports receiving foreign waterborne vessels means implementing measures to ensure security and safety for people, vessels, and facilities at the port through organizing security assessments, developing security plans approved by competent authorities, and issuing appropriate security certificates for inland waterway ports receiving foreign waterborne vessels.

2. Security measures apply to foreign waterborne vessels and international shipping vessels with a gross tonnage of 500 GT or more.

3. Security levels for inland waterway ports receiving foreign waterborne vessels are divided into three levels.

a) Security Level 1 is a level where appropriate security protection measures must be maintained continuously.

b) Security Level 2 is a level where additional security protection measures must be maintained during periods of high risk of a security incident.

c) Security Level 3 is a level where specific security protection measures must be maintained during limited periods when a security incident may occur or is about to occur, even though the specific target may not be identified.

4. Security measures for inland waterway ports receiving foreign waterborne vessels must be appropriate to each security level.

a) Security Level 1 ensures the continuous implementation of all security tasks in the security plan; monitoring all activities within the port area; controlling restricted areas in the port; inspecting and supervising cargo handling areas; inspecting and supervising the receipt of vessel supplies; ensuring timely exchange of security information.

b) Security Level 2 implements additional protective measures specified in the security plan for each activity mentioned in point a of this clause.

c) Security Level 3 implements enhanced special protective measures specified in the security plan for each activity mentioned in point a of this clause.

5. Security assessment for inland waterway ports receiving foreign waterborne vessels shall be organized and implemented initially and annually by the port operator according to Model No. 27 attached to this Decree, with the participation of representatives of specialized state management agencies at the port.

6. Security plan for inland waterway ports receiving foreign waterborne vessels

a) The security plan for inland waterway ports receiving foreign waterborne vessels (hereinafter referred to as the security plan) shall be established by the port operator according to Model No. 28 attached to this Decree and submitted to the competent authority for approval to ensure the application of port protection measures, for people, vessels, goods, cargo transportation units, and vessel supplies within the port range, avoiding risks from a security incident.

b) The security plan must be developed and maintained based on the security assessment of the inland waterway port. The security plan must provide appropriate measures for each security level stipulated in Clause 3 of this Article.

7. The security commitment for inland waterway ports receiving foreign waterborne vessels shall be implemented based on the assessment of potential risks that may arise from communication activities between waterborne vessels and the port or between waterborne vessels themselves concerning people, property, and the environment according to Model No. 29 attached to this Decree.

8. The security commitment must be established by the master or security officer of the foreign waterborne vessel, ship, or port security staff or organization responsible for shore-side security on behalf of the port owner and must be committed by the port owner or vessel owner to implement appropriate security measures in accordance with the security level of the port or foreign waterborne vessel, ship. The owner of the foreign waterborne vessel, ship, or port owner may request a security commitment in any of the following cases:

a) The foreign waterborne vessel, ship has a higher security level than the port, anchorage area, or other foreign waterborne vessel it is communicating with;

b) There is an agreement on security commitments between countries for certain international routes or for specific vessels on those routes;

c) There is a security threat or security incident related to the foreign waterborne vessel, ship, or port;

d) The foreign waterborne vessel, ship is in the port but does not require the port to have and enforce the approved security plan for inland waterway ports;

đ) The foreign waterborne vessel, ship is conducting communication activities with other foreign waterborne vessels, ships, but does not require having and enforcing an approved security plan for foreign waterborne vessels, ships;

e) The content of the security commitment must be committed by the port security staff or the master or security officer of the foreign waterborne vessel, ship to implement appropriate security measures in accordance with the security level of the port and the foreign waterborne vessel, ship.

9. Staff, civil servants, and officials of specialized management agencies, employees of port enterprises engaged in ensuring security at inland waterway ports must complete training courses on port security at training institutions specializing in security according to the port security training program approved by the Ministry of Transport and obtain a certificate of completion of the training course.

Article 43. Procedures for Approving Security Assessments, Security Plans, and Issuing Security Compliance Certificates for Domestic Inland Waterway Ports Receiving Foreign Vessels

1. The port management entity shall prepare the dossier in accordance with Clauses 2, 3, and 4 of this Article and submit three copies directly or through other appropriate means to the Port Management Office.

2. The dossier for requesting approval of the security assessment includes:

a) A request for approval of the security assessment in Form No. 30 attached to this Decree;

b) The security assessment prepared in accordance with Clause 5 of Article 42 of this Decree;

c) Participants in the security assessment meeting including: the county-level public security agency, the Border Guard Post at the port border gate, the provincial traffic police department, the Customs Branch, the Port Management Office, the county-level preventive health center, the county-level plant quarantine agency, and the animal quarantine agency at the border gate.

3. The dossier for requesting approval of the security plan and issuance of the security compliance certificate for domestic inland waterway ports receiving foreign vessels includes:

a) A request for approval of the security plan and issuance of the security compliance certificate for domestic inland waterway ports receiving foreign vessels in Form No. 31 attached to this Decree;

b) The security assessment that has been approved by the competent authority;

c) The security plan.

4. The dossier for annual confirmation of the security compliance certificate for domestic inland waterway ports includes:

a) A request for annual confirmation of the security compliance certificate for domestic inland waterway ports receiving foreign vessels in Form No. 32 attached to this Decree;

b) The security assessment must include opinions from the agencies specified in point c of Clause 2 of this Article;

c) Minutes of training sessions, drills, or exercises according to the approved security plan;

d) The original security compliance certificate (to be confirmed on the back page of the certificate).

5. Within five working days from the date of receipt of the complete dossier as prescribed, the Port Management Office shall review the dossier and report the results of the review along with two copies of the dossier to the Vietnam Inland Waterways Administration. Within five working days from the date of receipt of the complete dossier and the report from the Port Management Office, the Vietnam Inland Waterways Administration shall approve the security assessment, security plan, and issue the security compliance certificate for domestic inland waterway ports receiving foreign vessels, and annually confirm the security compliance certificate for domestic inland waterway ports.

The security assessment approval certificate, the security plan approval certificate, and the security compliance certificate for domestic inland waterway ports receiving foreign vessels shall be in Forms No. 33, No. 34, and No. 35 attached to this Decree.

6. The security compliance certificate for domestic inland waterway ports receiving foreign vessels shall have a validity period of five years and must be annually confirmed by the Vietnam Inland Waterways Administration.

Article 44. Inspection and Supervision of Security at Domestic Inland Waterway Ports Receiving Foreign Vessels

1. The Vietnam Inland Waterways Administration and the Port Management Office within their assigned functions, tasks, and authorities shall organize inspections, supervision, and handling of violations related to security work at domestic inland waterway ports. The list of items to be inspected for security work at domestic inland waterway ports is in Form No. 36 attached to this Decree.

2. The port management entity shall be responsible for organizing inspections of the implementation of security work to serve the purpose of security assessments and the development of security plans.

3. Foreign vessels and ships entering or leaving domestic inland waterway ports receiving foreign vessels must comply with maritime laws and regulations on security and safety as applicable to vessels entering or leaving Vietnamese seaports, except where otherwise provided by law.

4. The port management entity of domestic inland waterway ports receiving foreign vessels must ensure conditions for safety and security in accordance with the provisions.

Article 45. Inland Waterway Pilots

1. Mandatory Pilotage System

Foreign inland waterway vessels operating on inland waterways or entering and leaving inland waterway ports must be accompanied by a pilot, except for inland waterway vessels of the Kingdom of Cambodia operating in accordance with the Agreement between the Government of the Socialist Republic of Vietnam and the Royal Government of Cambodia on inland waterway transport. If necessary, the master of the vessel may request pilotage services.

2. The activities of pilots on inland waterways or within port waters shall be carried out in accordance with the regulations on pilots under maritime laws and shall be performed by marine pilots.

Section 3 PROTECTION OF THE ENVIRONMENT IN INLAND WATERWAY ACTIVITIES

Article 46. Protection of the Environment in Investment Construction, Maintenance, Renovation, and Upgrading of Inland Waterway Infrastructure

1. Project owners of construction, maintenance, renovation, and upgrading projects of inland waterway infrastructure have the responsibility to:

a) Organize the preparation of environmental impact assessment reports or environmental protection plans to submit to competent authorities for approval or confirmation in accordance with environmental protection laws;

b) Determine and allocate funds for environmental protection work within the total investment amount of the project; incorporate waste treatment measures and measures to minimize negative impacts on the environment into the basic design, technical design, tender documents, and contracts with construction contractors of the project, as approved or confirmed by the competent authority;

c) Organize management, supervision, and report to state authorities on environmental protection work during construction activities in accordance with construction and environmental protection laws.

2. Construction contractors must comply with environmental protection laws, environmental standards and technical regulations, and fully meet environmental protection requirements stipulated in the contract signed with the project owner.

3. Environmental monitoring and supervision consultants must adhere to environmental monitoring technical procedures, environmental standards, and bear responsibility before the project owner and the law for information and data created during environmental monitoring and supervision work.

Article 47. Protection of the Environment in Port and Inland Waterway Terminal Operations

Managers of port and inland waterway terminal operations have the responsibility to:

1. Develop and implement oil spill response plans in accordance with regulations for inland waterway ports and terminals that trade in petroleum products.

2. Allocate personnel to manage and carry out environmental protection work at the port and terminal.

3. Collect and treat wastewater generated during port and terminal operations to ensure compliance with environmental technical standards; conduct regular wastewater monitoring before and after treatment as required in the approved documentation; retain monitoring data to serve inspection of the wastewater treatment system's operation.

4. Collect, classify, and store various types of solid waste and hazardous waste generated during port and terminal operations for disposal or hire organizations with waste disposal functions to receive, transport, and dispose of such waste according to regulations.

5. Provide facilities, tools, and equipment at the port and terminal to receive general solid waste from vessels, ships, foreign inland waterway vessels, and seaplanes; post and provide lists of organizations with waste disposal functions to receive, transport, and dispose of hazardous waste generated from vessels, ships, foreign inland waterway vessels, and seaplanes.

6. Minimize dust and limit noise and vibration that negatively affect the surrounding environment and workers.

7. Arrange isolation and ensure safe distances in receiving and storing dangerous goods and flammable and explosive goods in accordance with regulations.

Article 48. Environmental Protection in the Activities of Building New, Repairing, Converting, Restoring, and Dismantling Vessels

The owner of the facility engaged in building new, repairing, converting, restoring, and dismantling vessels shall be responsible for:

1. Developing and implementing environmental protection plans and oil spill response plans as prescribed.

2. Assigning personnel to manage and carry out environmental protection work within the facility's operations.

3. Collecting and treating wastewater, solid waste, and hazardous waste generated during the facility's operations according to regulations.

Article 49. Environmental Protection for Vessels, Ships, Seaplanes, and Foreign Inland Waterway Vessels Operating on Inland Waterways

1. Ships must comply with national technical standards regarding ship systems to prevent marine pollution.

2. Vessels must comply with national technical standards concerning the prevention of pollution caused by inland waterway vessels.

3. Management of General Waste

a) Vessels, ships, foreign inland waterway vessels operating on inland waterways and coastal routes must cover goods to prevent them from falling off and causing dust pollution;

b) Waste and pollutants from vessels, ships, foreign inland waterway vessels must be collected and stored on board until they can be transferred to port reception facilities or handed over to organizations authorized to handle such waste according to regulations;

c) Vessels, ships, foreign inland waterway vessels must be equipped with wastewater treatment devices or storage tanks before being moved ashore for treatment;

d) Information about dumping waste must be recorded in the vessel’s garbage logbook;

đ) If the vessel carries goods that may cause pollution, preventive measures against pollution corresponding to those goods must be taken;

4. Management of Hazardous Waste

Vessels, ships, foreign inland waterway vessels, seaplanes generating hazardous waste must comply with legal provisions governing the management of hazardous waste.

5. No discharge of oil, ballast water, cooling water, or water mixed with oil containing pollutants into the environment beyond permissible environmental standards; dispersants shall not be used to disperse oil spills into water bodies.

6. Upon discovering a risk or act of environmental pollution or an oil spill, the person in charge of the vessel, ship, foreign inland waterway vessel must immediately apply effective countermeasures and report the environmental pollution incident or potential oil spill to the nearest specialized administrative agency.

7. Vessels, ships, seaplanes, foreign inland waterway vessels operating on inland waterways, within port waters, at wharves, and anchorage areas must be subject to inspection and supervision by specialized state administrative agencies regarding environmental protection regulations.

8. Vessels, ships, seaplanes, foreign inland waterway vessels anchored in port waters, at wharves, and anchorage areas must not engage in the following activities:

a) Cleaning chimneys or emitting black smoke;

b) Washing cargo holds or decks causing environmental pollution;

c) Pumping out dirty water, oil, water mixed with oil residues, and other harmful liquids;

d) Dumping garbage or other solid waste from the vessel, ship into the water or onto piers, wharves;

đ) Rust removal or painting the vessel causing environmental pollution.

9. The master of vessels, ships, seaplanes, foreign inland waterway vessels when operating on inland waterways and within port waters, at wharves must comply with the following requirements:

a) When discovering a risk or act of environmental pollution, immediately notify the Port Authority and record the time, location, and nature of the pollution incident in the vessel’s logbook;

b) If the pollution incident arises from the vessel’s own operation, immediately implement effective countermeasures and promptly inform the Port Authority.

10. Persons in charge of vessels, ships, foreign inland waterway vessels causing environmental damage or pollution must compensate and be dealt with according to regulations.

Chapter V PROCEDURES FOR VESSELS ENTERING AND LEAVING DOMESTIC PORTS AND WHARVES, ANCHORAGE AREAS

Article 50. Procedures for vessels, ships, seaplanes, foreign watercraft entering and leaving domestic ports and wharves

1. Vessels, ships, seaplanes, foreign watercraft entering and leaving domestic ports and wharves must complete procedures to obtain permission to enter and leave such ports and wharves.

2. Prior to entering or leaving domestic ports and wharves, the person handling the procedures shall notify the port authority about the vessel (registration number), the time of entry or departure from the port and wharf, and the type of cargo or number of passengers. Notification may be made via text message, telephone, or other means. The master or operator of the vessel or seaplane may only bring the vessel or seaplane into or out of the port or wharf with the approval of the port authority. The notification period is as follows:

a) Two hours before for cargo-carrying vessels;

b) One hour before for passenger-carrying vessels and seaplanes.

3. Procedures for vessels and seaplanes entering and leaving domestic ports and wharves may be conducted directly, through electronic procedures, or other methods as prescribed.

4. Vessels, ships, seaplanes, and foreign watercraft entering and leaving domestic ports and wharves must pay fees and charges as prescribed.

5. The provisions on procedures for vessels entering and leaving domestic ports and wharves, anchorage areas set forth in this Decree do not apply to vessels entering and leaving such ports and wharves, anchorage areas for national defense and security purposes.

Article 51. Forms, Time, and Locations for Handling Procedures for Vessels, Ships, Seaplanes, Foreign Watercraft Entering and Leaving Domestic Ports and Wharves

1. Forms for handling procedures for vessels, ships, seaplanes, foreign watercraft entering and leaving domestic ports and wharves

a) Submitting and presenting documents directly at the Port Authority;

b) Electronic procedures through the Ministry of Transport's electronic portal (for domestic cargo-carrying vessels and ships, seaplanes);

c) Electronic procedures under the National Single Window mechanism (for vessels and ships entering and exiting the country, foreign watercraft);

d) Electronic procedures through the ASEAN Single Window mechanism;

đ) Other forms as prescribed by law.

2. Time for handling procedures: within thirty minutes from the time all required documents are received, except for ships and foreign watercraft.

3. Location for handling procedures by submitting and presenting documents directly for vessels, ships, seaplanes, foreign watercraft handling procedures at the office of the Port Authority or at the port or wharf, or possibly on board the vessel (in cases where the vessel comes from an area related to disease outbreaks involving people, animals, or plants).

4. The process of electronic procedures under the National Single Window mechanism and electronic procedures through the ASEAN Single Window mechanism shall be carried out in accordance with relevant laws.

Article 52. Documents for Issuing Permission to Enter Domestic Ports and Wharves for Vessels and Seaplanes

1. The person handling the procedures shall submit the following documents:

a) Departure permit from the port and wharf, in case of electronic procedures;

b) Passenger list (for passenger-carrying vessels).

2. The person handling the procedures shall present the original of the following documents:

a) Certificate of vessel registration, seaplane registration (or certified copy from a financial institution if the vessel is pledged or mortgaged);

b) Certificate of technical safety and environmental protection of the vessel;

c) Certificate of professional qualifications and professional certificates of crew members, operators;

d) Crew logbook (if available);

đ) Transportation contract or warehouse exit invoice or goods transportation certificate;

e) Civil liability insurance (for vessels required by law to have civil liability insurance);

g) Certificate of airworthiness for seaplanes;

h) Permit for transporting dangerous goods, transportation plan for oversized and overweight cargo (for vessels transporting dangerous goods, oversized and overweight cargo).

3. The inspector must return the documents specified in Clause 2 of this Article to the person handling the procedures after inspection, unless otherwise provided by law.

4. If the documents specified in Clause 2 of this Article are stored in an electronic database, the person handling the procedures does not need to present them.

Article 53. Documents for Issuing Port Departure Permit for Vessels and Seaplanes at Inland Waterway Wharfs

1. The person handling the procedure shall submit and present the following documents:

a) Documents to be submitted: passenger list (for passenger transport vessels);

b) Documents to be presented: transportation contract or cargo manifest or goods export certificate; certificates of professional competence of crew members if there has been any change from when the vessel entered the port or inland waterway wharf.

2. For newly built, converted, or repaired vessels that are launched for operation, the vessel owner or the new construction, conversion, or repair facility must present to the Harbor Supervision Authority the following documents:

a) Inspection report confirming the vessel's operational readiness issued by the Inspection Agency.

b) Safety assurance plan during the launching of the vessel prepared by the new construction, conversion, or repair facility.

Article 54. Inspection and Issuance of Permits for Vessels and Seaplanes Entering and Leaving Ports and Inland Waterway Wharfs

1. The person handling the procedure may choose one of the forms prescribed in Clause 1 of Article 51 of this Decree to handle the procedures for vessels and seaplanes entering and leaving ports and inland waterway wharfs, subject to the following provisions:

a) In cases where the procedure is carried out directly at the place of handling, the person handling the procedure shall submit and present the documents stipulated in Articles 52 and 53 of this Decree to the Harbor Supervision Authority;

b) In cases where the procedure is conducted electronically, the person handling the procedure shall provide the documents stipulated in Articles 52 and 53 of this Decree through electronic software (selected by the person handling the procedure).

2. Inspection of Crew Member and Vessel Documents

a) In cases where documents are received directly from the person handling the procedure, the Harbor Supervision Authority shall check the compliance of the documents according to the regulations;

b) In cases where documents are received through electronic procedures, the Harbor Supervision Authority shall only check based on the database without directly inspecting the documents of the vessel, crew members, or vessel drivers, and if any errors are detected, a direct inspection will be conducted.

3. Kiểm tra phương tiện

a) Cảng vụ kiểm tra phương tiện trên cơ sở giấy chứng nhận an toàn kỹ thuật và bảo vệ môi trường của phương tiện;

b) Nếu phát hiện có vi phạm thì Cảng vụ thông báo, xử lý và hướng dẫn người làm thủ tục có biện pháp khắc phục, thay đổi bảo đảm đúng quy định.

4. Phương tiện, thủy phi cơ được cấp giấy phép vào, rời cảng, bến thủy nội địa khi bảo đảm các điều kiện theo quy định tại Nghị định này.

5. Phương tiện được cấp phép rời cảng, bến thủy nội địa vẫn neo tại vùng nước cảng, bến thủy nội địa quá 24 giờ thì phải đổi lại giấy phép rời cảng, bến thủy nội địa để điều chỉnh thời gian rời cảng, bến thủy nội địa,

6. Giấy phép vào, rời cảng, bến thủy nội địa có thể là bản giấy hoặc giấy phép điện tử. Giấy phép vào, rời cảng, bến thủy nội địa của phương tiện, thủy phi cơ theo Mẫu số 37, Mẫu số 38 tại phụ lục ban hành kèm theo Nghị định này.

7. Giấy phép vào, rời cảng, bến thủy nội địa do Cảng vụ đường thủy nội địa cấp và giấy phép rời cảng biển, cảng, bến thủy nội địa do Cảng vụ Hàng hải cấp được lưu trữ bằng giấy hoặc điện tử. Thời gian lưu trữ giấy phép vào, rời cảng, bến thủy nội địa bằng giấy là 02 năm, kể từ ngày phát hành. Hết thời hạn lưu trữ, Cảng vụ, Cảng vụ Hàng hải có trách nhiệm hủy giấy phép vào, rời cảng, bến thủy nội địa.

Điều 55. Thủ tục vào, rời cảng thủy nội địa đối với phương tiện vận tải thủy qua biên giới Việt Nam - Campuchia

1. Đối với phương tiện thủy nội địa của Vương quốc Campuchia vào, rời cảng thủy nội địa Việt Nam và phương tiện Việt Nam rời cảng thủy nội địa Việt Nam đi Campuchia, ngoài các thủ tục quy định tại Điều 51, Điều 52, Điều 53 và Điều 54 Nghị định này, còn phải xuất trình giấy phép vận tải thủy qua biên giới do cơ quan có thẩm quyền cấp.

2. Trường hợp phương tiện thủy nội địa của Vương quốc Campuchia và phương tiện thủy Việt Nam nhập cảnh, xuất cảnh vào, rời cảng thủy nội địa Việt Nam áp dụng hình thức điện tử thì thực hiện theo quy định tại Điều 56, Điều 57 Nghị định này.

3. Phương tiện thủy nội địa của Vương quốc Campuchia và phương tiện thủy Việt Nam nhập cảnh, xuất cảnh vào, rời cảng thủy nội địa Việt Nam không áp dụng hình thức điện tử thì thực hiện theo hình thức nộp, trình giấy tờ trực tiếp tại Cảng vụ.

4. Khi phương tiện đến cửa khẩu phải xuất trình các loại giấy tờ đã làm thủ tục xuất cảnh tại cảng xuất cảnh cho các cơ quan quản lý nhà nước tại cửa khẩu kiểm tra trước khi phương tiện rời khỏi lãnh thổ Việt Nam.

5. Trường hợp phương tiện không thể xuất cảnh đi Campuchia theo kế hoạch, người làm thủ tục phải thông báo và nộp lại các loại giấy tờ đã làm thủ tục xuất cảnh tại cửa khẩu cảng xuất cảnh để hủy hồ sơ xuất cảnh.

6. Giấy phép rời cảng thủy nội địa cấp cho phương tiện Việt Nam và phương tiện thủy nội địa của Vương quốc Campuchia rời cảng thủy nội địa Việt Nam đi Campuchia theo Mẫu số 39 tại Phụ lục ban hành kèm theo Nghị định này.

Điều 56. Thủ tục điện tử đối với phương tiện thủy nội địa Việt Nam, Campuchia nhập cảnh vào cảng thủy nội địa Việt Nam

1. Chậm nhất 02 giờ, trước khi phương tiện dự kiến đến cửa khẩu, người làm thủ tục phải khai báo giấy tờ theo phương thức điện tử thông qua Cổng thông tin một cửa quốc gia, gồm:

a) Thông báo phương tiện đến cảng thủy nội địa theo Mẫu số 48 tại Phụ lục ban hành kèm theo Nghị định này;

b) Giấy phép rời cảng thủy nội địa theo Mẫu số 39 tại Phụ lục ban hành kèm theo Nghị định này;

c) Bản khai chung theo Mẫu số 40 tại Phụ lục ban hành kèm theo Nghị định này;

d) Danh sách thuyền viên theo Mẫu số 41 tại Phụ lục ban hành kèm theo Nghị định này;

đ) Danh sách hành khách theo Mẫu số 42 tại Phụ lục ban hành kèm theo Nghị định này;

e) Bản khai hàng hóa theo Mẫu số 43 tại Phụ lục ban hành kèm theo Nghị định này hoặc hợp đồng vận chuyển hoặc hóa đơn xuất kho hoặc giấy vận chuyển hàng hóa;

g) Bản khai kiểm dịch thực vật đối với hàng hóa thuộc diện kiểm dịch thực vật theo Mẫu số 44 tại Phụ lục ban hành kèm theo Nghị định này;

h) Bản khai kiểm dịch động vật đối với hàng hóa thuộc diện kiểm dịch động vật theo Mẫu số 45 tại Phụ lục ban hành kèm theo Nghị định này;

i) Bản khai vũ khí và vật liệu nổ (nếu có) theo Mẫu số 46 tại Phụ lục ban hành kèm theo Nghị định này;

k) Bản khai người trốn trên tàu (nếu có) theo Mẫu số 47 tại Phụ lục ban hành kèm theo Nghị định này.

2. Các giấy tờ phải xuất trình

a) Giấy tờ xuất trình cho Cảng vụ gồm: Giấy chứng nhận an toàn kỹ thuật và bảo vệ môi trường của phương tiện, giấy tờ liên quan đến hàng hóa vận tải trên phương tiện, giấy chứng nhận đăng ký phương tiện (hoặc bản sao có xác nhận của tổ chức tín dụng trong trường hợp phương tiện đang cầm cố, thế chấp), giấy chứng nhận khả năng chuyên môn, chứng chỉ chuyên môn của thuyền viên, người lái phương tiện, bản sao giấy chứng nhận bảo hiểm trách nhiệm dân sự (đối với phương tiện thuộc diện bắt buộc phải có bảo hiểm trách nhiệm dân sự), giấy phép vận tải thủy qua biên giới Việt Nam - Campưchia;

b) Giấy tờ xuất trình cho Cơ quan Hải quan: Giấy tờ liên quan đến hàng hóa vận tải trên phương tiện;

c) Giấy tờ xuất trình cho Bộ đội Biên phòng cửa khẩu: Hộ chiếu và giấy tờ có giá trị đi lại quốc tế của thuyền viên, hành khách (nếu có);

d) Giấy tờ xuất trình cho cơ quan kiểm dịch thực vật: Giấy chứng nhận kiểm dịch thực vật (đối với hàng hóa thuộc diện kiểm dịch thực vật);

đ) Giấy tờ xuất trình cho cơ quan kiểm dịch động vật: Giấy chứng nhận kiểm dịch động vật của nước xuất hàng (đối với hàng hóa thuộc diện kiểm dịch động vật);

e) Giấy tờ xuất trình cho cơ quan kiểm dịch y tế: Giấy chứng nhận tiêm chủng quốc tế của thuyền viên, người lái phương tiện, hành khách (trong trường hợp xuất phát hoặc đi qua vùng có dịch hoặc bị nghi ngờ mắc bệnh hoặc tác nhân gây bệnh truyền nhiễm).

3. Kiểm tra các loại giấy tờ liên quan đến phương tiện và thuyền viên

a) Cảng vụ kiểm tra các thông tin khai báo, tra cứu dữ liệu phương tiện, thuyền viên Việt Nam trên cơ sở dữ liệu điện tử của các cơ quan có thẩm quyền để giải quyết thủ tục cấp giấy phép cho phương tiện vào cảng thủy nội địa;

b) Cảng vụ chỉ yêu cầu người làm thủ tục nộp, xuất trình các giấy tờ trong trường hợp cơ sở dữ liệu không có thông tin của phương tiện, thuyền viên, người lái phương tiện hoặc không đủ dữ liệu điện tử để kiểm tra, đối chiếu hoặc không bảo đảm điều kiện của chứng từ điện tử và người làm thủ tục chỉ khai báo dữ liệu lần đầu về phương tiện, thuyền viên trên phần mềm điện tử (do người làm thủ tục lựa chọn). Cảng vụ làm thủ tục đầu tiên kiểm tra, đối chiếu dữ liệu khai báo với bản chính xuất trình để giải quyết thủ tục cho phương tiện vào cảng thủy nội địa hoặc khi có sự thay đổi. Cơ sở dữ liệu về thuyền viên, người lái phương tiện, phương tiện, cảng thủy nội địa được lưu giữ trên Cổng thông tin một cửa quốc gia để làm cơ sở dữ liệu cho những lần làm thủ tục tiếp theo;

c) Thời hạn xuất trình các giấy tờ không có trong cơ sở dữ liệu: Chậm nhất 02 giờ, kể từ khi phương tiện đã neo đậu tại cầu cảng hoặc 04 giờ phương tiện đã neo đậu tại vị trí khác trong vùng nước cảng thủy nội địa

4. Trách nhiệm làm thủ tục của cơ quan quản lý nhà nước chuyên ngành tại cảng thủy nội địa

a) Cảng vụ có trách nhiệm kiểm tra các giấy tờ quy định tại các điểm a, b, c, d, đ, e khoản 1, điểm a khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại các điểm a, b, c khoản 1 Điều này, trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

b) Cơ quan Hải quan chịu trách nhiệm kiểm tra các giấy tờ quy định tại các điểm a, c, d, đ, e khoản 1 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại điểm b khoản 2 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

c) Bộ đội Biên phòng cửa khẩu chịu trách nhiệm chính kiểm tra các giấy tờ quy định tại các điểm a, b, c, d, đ, i, k khoản 1, điểm c khoản 2 của Điều này và có thẩm quyền quyết định cuối cùng đối với các giấy tờ quy định tại các điểm i, k khoản 1, điểm c khoản 2 Điều này, trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

đ) Cơ quan kiểm dịch thực vật có trách nhiệm kiểm tra các giấy tờ quy định tại các điểm c, g khoản 1, điểm đ khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại điểm g khoản 1 Điều này, trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

d) Cơ quan kiểm dịch động vật có trách nhiệm kiểm tra các giấy tờ quy định tại các điểm c, h khoản 1, điểm đ khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ tại điểm h khoản 1 Điều này, trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

c) Cơ quan kiểm dịch y tế có trách nhiệm kiểm tra giấy tờ quy định tại điểm e khoản 2 Điều này và có thẩm quyền quyết định cuối cùng đối với giấy tờ đã kiểm tra trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau.

5. Cấp phép điện tử

Chậm nhất 30 phút, kể từ khi người làm thủ tục hoàn thành các thủ tục khai báo điện tử và xuất trình đầy đủ các giấy tờ theo quy định, trên cơ sở ý kiến phản hồi của các cơ quan liên quan, Cảng vụ cấp giấy phép điện tử cho phương tiện vào cảng thủy nội địa thông qua Cổng thông tin một cửa quốc gia.

Điều 57. Thủ tục điện tử đối với phương tiện thủy nội địa Việt Nam, Campuchia xuất cảnh rời cảng thủy nội địa Việt Nam

1. Chậm nhất 02 giờ, trước khi phương tiện rời cảng thủy nội địa, người làm thủ tục khai báo giấy tờ sau đây theo hình thức điện tử thông qua Cổng thông tin một cửa quốc gia

a) Thông báo phương tiện rời cùng thủy nội địa theo Mẫu số 48 tại Phụ lục ban hành kèm theo Nghị định này;

b) Danh sách thuyền viên, người lái phương tiện với đầy đủ chức danh;

c) Danh sách hành khách (đối với phương tiện chở hành khách);

d) Bản khai hàng hóa, hợp đồng vận chuyển hoặc hóa đơn xuất kho hoặc giấy vận chuyển (đối với phương tiện chở hàng hóa).

2. Các chứng từ phải xuất trình

a) Giấy tờ xuất trình cho Cảng vụ: Giấy tờ liên quan đến hàng hóa vận tải trên phương tiện; giấy tờ xác nhận việc nộp phí, lệ phí quy định của pháp luật, trừ trường hợp thanh toán điện tử; giấy chứng nhận khả năng chuyên môn, chứng chỉ chuyên môn của thuyền viên, người lái phương tiện; giấy tờ liên quan tới những thay đổi so với giấy tờ khi làm thủ tục cho phương tiện vào cảng thủy nội địa;

b) Giấy tờ xuất trình cho Cơ quan Hải quan: Giấy tờ liên quan đến hàng hóa vận tải trên phương tiện;

c) Giấy từ xuất trình cho Bộ đội Biên phòng cửa khẩu: Hộ chiếu và giấy tờ có giá trị đi lại quốc tế của thuyền viên, hành khách (nếu có);

d) Giấy tờ xuất trình cho cơ quan kiểm dịch thực vật: Giấy chứng nhận kiểm dịch thực vật (đối với hàng hóa thuộc diện kiểm dịch thực vật);

đ) Giấy tờ xuất trình cho cơ quan kiểm dịch động vật: Giấy chứng nhận kiểm dịch động vật của nước xuất hàng (đối với hàng hóa thuộc diện kiểm dịch động vật);

e) Giấy tờ xuất trình cho cơ quan kiểm dịch y tế: Giấy chứng nhận tiêm chủng quốc gia của thuyền viên, người lái phương tiện, hành khách (trong trường hợp xuất phát hoặc đi qua vùng có dịch hoặc bị nghi ngờ mắc bệnh hoặc tác nhân gây bệnh truyền nhiễm).

3. Kiểm tra các loại giấy chứng nhận của phương tiện và thuyền viên.

a) Cảng vụ kiểm tra các thông tin khai báo, tra cứu dữ liệu của phương tiện, thuyền viên trên cơ sở dữ liệu điện tử của các cơ quan có thẩm quyền để giải quyết thủ tục cấp giấy phép rời cảng thủy nội địa cho phương tiện;

b) Cảng vụ chỉ yêu cầu người làm thủ tục nộp, xuất trình các giấy tờ trong trường hợp cơ sở dữ liệu không có dữ liệu của phương tiện, thuyền viên, người lái phương tiện hoặc không đủ dữ liệu điện tử để kiểm tra, đối chiếu hoặc không bảo đảm điều kiện của chứng từ điện tử và người làm thủ tục chỉ việc khai báo dữ liệu lần đầu về phương tiện, thuyền viên trên phần mềm điện tử (do người làm thủ tục lựa chọn). Cảng vụ làm thủ tục cuối cùng kiểm tra, đối chiếu dữ liệu khai báo với bản chính xuất trình để giải quyết thủ tục cho phương tiện rời cảng thủy nội địa Việt Nam hoặc khi có sự thay đổi. Cơ sở dữ liệu về thuyền viên, người lái phương tiện, phương tiện rời cảng thủy nội địa Việt Nam được lưu giữ trên phần mềm điện tử để làm cơ sở dữ liệu cho những lần làm thủ tục tiếp theo.

4. Thời hạn nộp hoặc xuất trình các giấy tờ không có trong cơ sở dữ liệu: Chậm nhất 02 giờ, trước khi phương tiện rời cảng và cửa khẩu. Đối với phương tiện chở khách có thể thực hiện ngay tại thời điểm phương tiện chuẩn bị rời cảng và cửa khẩu.

5. Trách nhiệm làm thủ tục của cơ quan quản lý nhà nước chuyên ngành tại cảng thủy nội địa

a) Cảng vụ có trách nhiệm kiểm tra các giấy tờ quy định tại khoản 1 và điểm a khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại điểm a khoản 1 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

b) Cơ quan hải quan chịu trách nhiệm trong việc kiểm tra các giấy tờ quy định tại khoản 1, điểm b khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại điểm b khoản 2 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

c) Bộ đội Biên phòng cửa khẩu chịu trách nhiệm trong việc kiểm tra các chứng từ quy định tại các điểm a, b, c khoản 1, điểm c khoản 2 Điều này; chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại các điểm b, c khoản 1 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

d) Cơ quan kiểm dịch thực vật có trách nhiệm kiểm tra các giấy tờ quy định tại điểm a khoản 1 và điểm d khoản 2 Điều này, chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại các điểm d khoản 2 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

đ) Cơ quan kiểm dịch động vật có trách nhiệm kiểm tra các chứng từ quy định tại điểm a khoản 1 và điểm đ khoản 2 Điều này, chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại các điểm đ khoản 2 Điều này trong trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau;

e) Cơ quan kiểm dịch y tế có trách nhiệm kiểm tra giấy tờ quy định tại điểm e khoản 2 Điều này, chịu trách nhiệm chính và có thẩm quyền quyết định cuối cùng đối với giấy tờ quy định tại các điểm e khoản 2 Điều này trang trường hợp các cơ quan quản lý nhà nước cùng tham gia xử lý và có ý kiến khác nhau.

6. Cấp phép điện tử

a) Chậm nhất 30 phút, kể từ khi người làm thủ tục hoàn thành các thủ tục khai báo điện tử và xuất trình đầy đủ các giấy tờ thao quy định, trên cơ sở ý kiến phản hồi của các cơ quan liên quan, Cảng vụ cấp giấy phép cho phương tiện rời cảng thủy nội địa thông qua phần mềm điện tử;

b) Trường hợp phương tiện đã được cấp giấy phép rời cảng thủy nội địa nhưng ra đến cửa khẩu, cơ quan chức năng tại cửa khẩu không cho phương tiện xuất cảnh thì phải trả lời cho chủ phương tiện biết và nêu rõ lý do, đồng thời thông báo cho Cảng vụ cấp giấy phép rời cảng biết.

Điều 58. Thủ tục đối với tàu biển, phương tiện thủy nước ngoài vào, rời và nhập cảnh, xuất cảnh tại cảng thủy nội địa

1. Phương tiện thủy nước ngoài, tàu biển vào, rời và nhập cảnh, xuất cảnh tại cảng thủy nội địa thực hiện thủ tục theo quy định của pháp luật hàng hải đối với tàu thuyền vào, rời và nhập cảnh, xuất cảnh tại cảng biển và Nghị định này.

2. Mẫu giấy phép vào, rời cảng thủy nội địa và nhập cảnh, xuất cảnh đối với tàu biển, phương tiện thủy nước ngoài thực hiện theo quy định của pháp luật về hàng hải.

Điều 59. Phương tiện, thủy phi cơ, tàu biển vào, rời khu neo đậu

1. Phương tiện, thủy phi cơ, tàu biển vào, rời khu neo đậu để chuyển tải hàng hóa, đón trả hành khách phải thực hiện thủ tục theo quy định như vào, rời cảng, bến thủy nội địa quy định tại Nghị định này.

2. Giấy phép vào, rời khu neo đậu theo Mẫu số 37, Mẫu số 38 tại Phụ lục ban Hành kèm theo Nghị định này.

3. Bộ Tài chính quy định mức thu phí, lệ phí vào, rời khu neo đậu đối với phương tiện, thủy phi cơ, tàu biển quy định tại khoản 1 Điều này.

Điều 60. Miễn, giảm thủ tục vào, rời cảng, bến thủy nội địa, khu neo đậu

1. Các phương tiện sau đây được miễn làm thủ tục vào, rời cảng, bến thủy nội địa, khu neo đậu

a) Phương tiện chữa cháy; phương tiện tìm kiếm, cứu nạn, cứu hộ; phương tiện hộ đê; phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài tránh trú bão, lũ;

b) Phương tiện của cơ quan nhà nước, đơn vị lực lượng vũ trang đang làm nhiệm vụ; phương tiện, đoàn phương tiện có Công an hộ tống hoặc dẫn đường;

c) Phương tiện chuyên dùng của đơn vị quản lý chuyên ngành đường thủy nội địa;

d) Phương tiện đón, trả hoa tiêu, tàu cá;

d) Phương tiện vận tải hành khách ngang sông tại bến khách ngang sông;

e) Phương tiện (tàu con) chuyển tải hành khách, hàng hóa từ phương tiện, tàu biển, phương tiện thủy nước ngoài (tàu mẹ) vào cảng, bến và ngược lại; trong trường hợp này, tàu mẹ phải được làm thủ tục như thủ tục vào, rời cảng, bến, khu neo đậu. Trước khi vào cảng, bến thủy nội địa, thuyền trưởng, người lái phương tiện (tàu con) quy định tại điểm này phải thông báo cho Cảng vụ biết bằng văn bản hoặc bằng hình thức thông tin phù hợp khác;

g) Phương tiện chở người, vật tư, thiết bị đến và rời khu vực nuôi, trồng thủy, hải sản, xây dựng thi công công trình trên sông, hồ, đầm, phá, vụng, vịnh và trên biển;

h) Phương tiện thô sơ không kinh doanh vận tải;

i) Phương tiện vận tải hàng hóa (trừ hàng hóa nguy hiểm) có trọng tải toàn phần dưới 10 tấn;

k) Phương tiện, tàu biển, phương tiện thủy nước ngoài, thủy phi cơ vào, rời cảng thủy nội địa để tiếp nhận nhiên liệu, lương thực, thực phẩm.

2. Phương tiện, tàu biển, thủy phi cơ được giảm thủ tục vào, rời cảng, bến thủy nội địa

a) Phương tiện vận tải hành khách đã đăng ký hoạt động trên tuyến cố định có nhiều cảng, bến thủy nội địa đón, trả hành khách, nếu không thay đổi thuyền viên, người lái phương tiện thì chỉ làm thủ tục vào, rời cảng, bến thủy nội địa đầu và cảng, bến thủy nội địa cuối;

b) Phương tiện, tàu biển, thủy phi cơ trong một chuyến vận tải hàng hóa, hành khách vào, rời nhiều cảng, bến thủy nội địa, khu neo đậu thuộc phạm vi quản lý của một Đại diện cảng vụ mà không thay đổi hành khách, thuyền viên, người lái phương tiện thì chỉ làm thủ tục vào cảng, bến thủy nội địa đầu tiên và làm thủ tục rời tại cảng, bến thủy nội địa cuối cùng. Trong trường hợp này, việc di chuyển giữa các cảng, bến thủy nội địa được Cảng vụ cấp lệnh điều động cho phương tiện, tàu biển, thủy phi cơ. Lệnh điều động theo Mẫu số 49 tại Phụ lục ban hành kèm theo Nghị định này;

c) Phương tiện vận tải hành khách, thủy phi cơ thường xuyên vào, rời một cảng, bến thủy nội địa mà không thay đổi thuyền viên, người lái phương tiện và phương tiện có giấy chứng nhận an toàn kỹ thuật và bảo vệ môi trường còn hiệu lực thì làm thủ tục phương tiện vào, rời cảng, bến thủy nội địa chuyến thứ nhất. Từ chuyến thứ hai trở lên chỉ thực hiện kiểm tra an toàn và cấp giấy phép rời cảng, bến thủy nội địa;

d) Phương tiện vận chuyển nguyên liệu, nông sản, thủy sản từ nơi sản xuất, nuôi trồng đến cảng, bến của nhà máy chế biến mà khi rời cảng, bến này không vận chuyển hàng hóa, không thay đổi thuyền viên, người lái phương tiện thì không phải làm thủ tục rời cảng, bến;

đ) Phương tiện vào, rời cảng, bến thủy nội địa trong phạm vi quản lý của một Đại diện Cảng vụ từ hai lần trở lên trong một ngày mà không thay đổi thuyền viên, người lái phương tiện thì Cảng vụ kiểm tra giấy tờ của phương tiện, thuyền viên lần đầu. Việc kiểm tra điều kiện an toàn các lần vào, rời thực hiện theo quy định tại Nghị định này;

e) Phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài vào cầu, bến cảng biển hoặc khu vực hàng hải sau đó đến cảng, bến thủy nội địa trong vùng nước cảng biển hoặc khu vực hàng hải để rời vùng nước cảng biển hoặc khu vực hàng hải, thì Cảng vụ chỉ làm thủ tục rời cảng, bến thủy nội địa;

g) Phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài vào cảng, bến thủy nội địa trong vùng nước cảng biển hoặc khu vực hàng hải sau đó đến cầu, bến cảng biển trong vùng nước cảng biển hoặc khu vực hàng hải đó, thì Cảng vụ chỉ làm thủ tục vào cảng, bến thủy nội địa;

h) Phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài vào cầu, bến cảng biển, cảng, bến thủy nội địa trong vùng nước cảng biển hoặc khu vực hàng hải sau đó di chuyển giữa các cảng, bến thủy nội địa hoặc cảng biển, trong vùng nước cảng biển hoặc khu vực hàng hải, thì Cảng vụ cấp lệnh điều động cho phương tiện. Lệnh điều động theo Mẫu số 49 tại Phụ lục ban hành kèm theo Nghị định này.

3. Trường hợp phương tiện vận tải hàng hóa vào cảng, bến thủy nội địa có giấy phép rời cảng, bến thủy nội địa, mà trong giấy phép ghi nơi đến là cảng, bến thủy nội địa khác, thì Cảng vụ làm thủ tục cho phương tiện vào cảng, bến thủy nội địa và yêu cầu người làm thủ tục trình bày lý do thay đổi kế hoạch vận tải của phương tiện.

4. Khi phương tiện rời cảng, bến thủy nội địa chưa xác định được cảng, bến thủy nội địa đến, thì Cảng vụ ghi nơi đến (dự kiến) do người làm thủ tục đề xuất trong giấy phép rời cảng, bến.

Chương VI TRÁCH NHIỆM TỔ CHỨC QUẢN LÝ HOẠT ĐỘNG ĐƯỜNG THỦY NỘI ĐỊA

Điều 61. Trách nhiệm phối hợp quản lý hoạt động đường thủy nội địa

1. Các cơ quan quản lý nhà nước chuyên ngành trên đường thủy nội địa về tại cảng, bến thủy nội địa, khu neo đậu phải phối hợp thực hiện nhiệm vụ, tuân theo các quy định của pháp luật bảo đảm an toàn, an ninh và hiệu quả.

2. Các vướng mắc phát sinh liên quan đến chức năng, nhiệm vụ của các cơ quan quản lý nhà nước chuyên ngành khác đều phải được trao đổi thống nhất để giải quyết kịp thời. Trường hợp không thống nhất, phải kịp thời thông báo cho Cục Đường thủy nội địa Việt Nam, Cục Hàng hải Việt Nam, Cục Cảnh sát giao thông, Sở Giao thông vận tải biết để giải quyết theo quy định của pháp luật.

3. Trách nhiệm phối hợp hoạt động quản lý tại cảng thủy nội địa tiếp nhận phương tiện thủy nước ngoài

a) Các cơ quan quản lý nhà nước chuyên ngành tại cảng thủy nội địa tiếp nhận phương tiện thủy nước ngoài khi thực hiện nhiệm vụ phải tuân theo các quy định của pháp luật, không gây phiền hà, làm ảnh hưởng đến hoạt động bình thường của doanh nghiệp, chủ tàu, chủ hàng, phương tiện và các tổ chức, cá nhân khác trong khu vực cảng thủy nội địa;

b) Cơ quan quản lý nhà nước chuyên ngành tại cảng thủy nội địa có trách nhiệm phối hợp chặt chẽ giải quyết kịp thời, đúng pháp luật các thủ tục liên quan đến phương tiện, hàng hóa, hành khách, thuyền viên khi hoạt động tại cảng thủy nội địa theo quy định tại Nghị định này và quy định của pháp luật khác có liên quan; thông báo cho Cảng vụ biết kết quả giải quyết thủ tục liên quan đến phương tiện, hàng hóa, thuyền viên, hành khách khi hoạt động tại cảng thủy nội địa;

c) Cảng vụ có trách nhiệm chủ trì tổ chức phối hợp hoạt động giữa các cơ quan quản lý nhà nước chuyên ngành tại cảng thủy nội địa tiếp nhận phương tiện thủy nước ngoài; trao đổi với các cơ quan, doanh nghiệp thống nhất việc giải quyết những vướng mắc phát sinh trong hoạt động đường thủy nội địa tại vùng nước cảng thủy nội địa do mình phụ trách; yêu cầu các cơ quan quản lý nhà nước chuyên ngành khác tại cảng thủy nội địa thông báo kịp thời kết quả làm thủ tục; yêu cầu người khai thác cảng thủy nội địa, chủ phương tiện, thuyền trưởng và các cơ quan, tổ chức liên quan khác cung cấp số liệu, thông tin về hoạt động đường thủy nội địa tại cảng thủy nội địa.

4. Cơ quan có thẩm quyền thỏa thuận xây dựng, thiết lập công trình, công bố hoạt động công trình thuộc kết cấu hạ tầng đường thủy nội địa; chấp thuận phương án bảo đảm giao thông; thỏa thuận xây dựng, thiết lập công trình không thuộc kết cấu hạ tầng đường thủy nội địa; cấp giấy phép, cho ý kiến về những vấn đề liên quan đến đường thủy nội địa, quốc phòng, an ninh phải thực hiện đúng trình tự theo quy định tại Nghị định này. Trường hợp không đồng ý phải có văn bản trả lời, nêu rõ lý do.

Điều 62. Trách nhiệm quản lý hoạt động đường thủy nội địa của Bộ Giao thông vận tải

1. Thực hiện quản lý nhà nước về hoạt động giao thông đường thủy nội địa trong phạm vi cả nước; chủ trì, phối hợp với các bộ, ngành và Ủy ban nhân dân cấp tỉnh tổ chức thực hiện Nghị định này.

2. Công bố danh mục cảng thủy nội địa 03 năm/lần, trên cơ sở rà soát, tổng hợp, báo cáo của Cục Đường thủy nội địa Việt Nam.

3. Chỉ đạo Cục Đường thủy nội địa Việt Nam tổ chức thực hiện:

a) Kiểm tra, hướng dẫn việc thực hiện quy hoạch, quản lý, bảo trì kết cấu hạ tầng đường thủy nội địa trên đường thủy nội địa quốc gia, đường thủy nội địa chuyên dùng nối với đường thủy nội địa quốc gia;

b) Lập mẫu báo cáo, hướng dẫn thực hiện báo cáo về quản lý hoạt động khai thác, bảo trì kết cấu hạ tầng đường thủy nội địa; hoạt động cảng, bến thủy nội địa, khu neo đậu;

c) Xây dựng cơ sở dữ liệu để quản lý luồng, cảng, bến thủy nội địa, khu neo đậu; phương tiện ra, vào cảng, bến thủy nội địa, khu neo đậu trong phạm vi cả nước;

d) Công bố danh mục bến thủy nội địa, khu neo đậu hằng năm, trên cơ sở báo cáo tổng hợp của Sở Giao thông vận tải;

đ) Tổ chức thanh tra, kiểm tra việc chấp hành quy định về hoạt động đường thủy nội địa thuộc phạm vi thẩm quyền theo quy định của pháp luật.

4. Công bố tuyến hoạt động của phương tiện thủy nội địa mang cấp VR-SB; quy định về quản lý phương tiện, thuyền viên làm việc trên phương tiện thủy nội địa mang cấp VR-SB và các hoạt động khác theo quy định của pháp luật có liên quan nhằm bảo đảm an toàn, an ninh trong hoạt động đường thủy nội địa.

5. Thực hiện nhiệm vụ, quyền hạn khác theo quy định tại Nghị định này.

Điều 63. Trách nhiệm trong quản lý hoạt động giao thông đường thủy nội địa của các bộ liên quan

1. Bộ Công an có trách nhiệm:

a) Chủ trì phối hợp với Bộ Giao thông vận tải, các bộ, ngành liên quan và Ủy ban nhân dân cấp tỉnh thực hiện các biện pháp bảo đảm trật tự, an toàn giao thông đường thủy nội địa;

b) Tổ chức lực lượng Cảnh sát giao thông tuần tra, kiểm soát, xử lý hành vi vi phạm pháp luật trên đường thủy nội địa đối với người, phương tiện tham gia giao thông đường thủy nội địa theo quy định của pháp luật; điều tra, thống kê, cung cấp dữ liệu về tai nạn giao thông đường thủy nội địa;

c) Chỉ đạo lực lượng Công an các địa phương tăng cường phối hợp bảo vệ kết cấu hạ tầng đường thủy nội địa.

2. Bộ Tài nguyên và Môi trường có trách nhiệm:

a) Chủ trì phối hợp với Ủy ban nhân dân cấp tỉnh, Bộ Giao thông vận tải quản lý hoạt động khai thác cát, sỏi, khoáng sản khác trên sông, kênh, rạch, hồ, đầm, phá có liên quan đến luồng và hành lang bảo vệ luồng, bảo đảm an toàn giao thông, bảo vệ môi trường trên đường thủy nội địa, cảng, bến thủy nội địa;

b) Chỉ đạo Thanh tra chuyên ngành phối hợp với các cơ quan liên quan thanh tra hoạt động khai thác khoáng sản, bảo vệ môi trường trên đường thủy nội địa theo quy định.

3. Bộ Nông nghiệp và Phát triển nông thôn có trách nhiệm:

a) Chỉ đạo, hướng dẫn tổ chức, cá nhân nuôi trồng, đánh bắt thủy, hải sản và tàu cá hoạt động trên đường thủy nội địa thực hiện các biện pháp bảo đảm an toàn giao thông;

b) Chỉ đạo các địa phương tạo điều kiện để chủ cảng, bến thủy nội địa lập kho lưu hàng hóa, tập kết hàng hóa trên diện tích đất của cảng, bến thủy nội địa; kết hợp việc thoát lũ phù hợp với điều kiện thực tế không để cảng, bến thủy nội địa phải ngừng hoạt động khai thác trong thời gian không có lũ;

c) Phối hợp với Ủy ban nhân cấp tỉnh rà soát, giải tỏa các bến bãi tập kết hàng hóa vi phạm hành lang bảo vệ đê, công trình thủy lợi khác.

4. Các bộ, ngành có liên quan có trách nhiệm chỉ đạo, hướng dẫn các cơ quan quản lý nhà nước chuyên ngành trực thuộc thực hiện phối hợp hoạt động quản lý nhà nước trên đường thủy nội địa, cảng, bến thủy nội địa, khu neo đậu.

Điều 64. Trách nhiệm quản lý hoạt động đường thủy nội địa của Ủy ban nhân dân cấp tỉnh

1. Chỉ đạo, hướng dẫn Ủy ban nhân dân cấp huyện, cấp xã tổ chức quản lý, khai thác bến khách ngang sông; thực hiện các biện pháp bảo vệ kết cấu hạ tầng đường thủy nội địa, chống lấn, chiếm hành lang bảo vệ luồng; bảo đảm trật tự an toàn giao thông đường thủy nội địa và chịu trách nhiệm về trật tự, an toàn giao thông đường thủy nội địa tại địa phương.

2. Tổ chức quản lý đối với sông, kênh, hồ, đầm, phá trên địa bàn chưa được đầu tư xây dựng, công bố mở luồng mà có hoạt động vận tải nhằm bảo đảm trật tự, an toàn giao thông.

3. Ưu tiên bố trí đất xây dựng cảng, bến thủy nội địa bảo đảm ổn định. Chỉ đạo các cơ quan tham mưu tạo điều kiện để các tổ chức, cá nhân có nhu cầu xây dựng, kinh doanh cảng, bến thủy nội địa được giao đất, cho thuê đất, lập hồ sơ đề nghị công bố hoạt động theo quy định.

4. Tổ chức giải tỏa các bến tập kết, xếp dỡ hàng hóa không đủ điều kiện để công bố hoạt động và các công trình, nhà hàng nổi, khách sạn nổi hoạt động trái quy định.

5. Tổ chức tuyên truyền, phổ biến, giáo dục pháp luật về giao thông đường thủy nội địa; áp dụng các biện pháp bảo đảm trật tự, an toàn giao thông đường thủy nội địa tại địa phương.

6. Chỉ đạo, tổ chức quản lý nhà nước chuyên ngành về giao thông vận tải đường thủy nội địa tại cảng, bến thủy nội địa, khu neo đậu trên đường thủy nội địa địa phương, đường thủy nội địa chuyên dùng nối với đường thủy nội địa địa phương.

7. Chỉ đạo Sở Giao thông vận tải tổ chức thực hiện:

a) Kiểm tra, hướng dẫn việc thực hiện quy hoạch, quản lý, bảo trì kết cấu hạ tầng đường thủy nội địa thuộc phạm vi trách nhiệm được giao;

b) Lập danh bạ luồng địa phương, luồng chuyên dùng nối với luồng địa phương, cảng, bến thủy nội địa, khu neo đậu thuộc phạm vi quản lý, bến khách ngang sông trên địa bàn địa phương, báo cáo Ủy ban nhân dân cấp tỉnh và Cục Đường thủy nội địa Việt Nam; tổ chức thực hiện quản lý nhà nước tại cảng, bến thủy nội địa, khu neo đậu thuộc phạm vi trách nhiệm;

c) Tổ chức lực lượng Thanh tra giao thông thanh tra, kiểm tra việc chấp hành quy định về hoạt động đường thủy nội địa thuộc phạm vi thẩm quyền theo quy định của pháp luật.

8. Thực hiện nhiệm vụ, quyền hạn khác theo quy định tại Nghị định này.

Điều 65. Quản lý nhà nước chuyên ngành tại cảng, bến thủy nội địa, khu neo đậu

1. Hoạt động quản lý nhà nước chuyên ngành tại cảng, bến thủy nội địa, khu neo đậu theo quy định tại Điều 71, Điều 72 Luật Giao thông đường thủy nội địa và Nghị định này.

2. Cảng vụ thuộc Cục Đường thủy nội địa Việt Nam thực hiện chức năng quản lý nhà nước chuyên ngành tại cảng, bến thủy nội địa (trừ bến khách ngang sông), khu neo đậu đã được công bố, cấp phép hoạt động trên đường thủy nội địa quốc gia, đường thủy nội địa chuyên dùng nối với đường thủy nội địa quốc gia, cảng, bến thủy nội địa, khu neo đậu có vùng đất, vùng nước vừa trên đường thủy nội địa quốc gia và đường thủy nội địa địa phương, cảng, bến thủy nội địa, khu neo đậu trong vùng nước cảng biển nối với đường thủy nội địa quốc gia và trường hợp khác do Bộ Giao thông vận tải quyết định.

3. Cảng vụ thuộc Sở Giao thông vận tải hoặc cơ quan, đơn vị được Ủy ban nhân dân cấp tỉnh giao thực hiện tại địa phương chưa có tổ chức Cảng vụ đường thủy nội địa trực thuộc Sở Giao thông vận tải thực hiện chức năng quản lý nhà nước chuyên ngành tại cảng, bến thủy nội địa (trừ bến khách ngang sông), khu neo đậu đã được công bố, cấp phép hoạt động trên đường thủy nội địa địa phương, đường thủy nội địa chuyên dùng nối với đường thủy nội địa địa phương, cảng, bến thủy nội địa, khu neo đậu trong vùng nước cảng biển nối với đường thủy nội địa địa phương và trường hợp khác do Bộ Giao thông vận tải quyết định.

Điều 66. Trách nhiệm của chủ cảng, bến, người quản lý khai thác cảng, bến thủy nội địa, khu neo đậu

Chủ cảng, bến thủy nội địa, khu neo đậu, người quản lý khai thác cảng, bến, khu neo đậu có trách nhiệm thực hiện những quy định sau đây:

1. Duy trì hoạt động an toàn, an ninh của cảng, bến thủy nội địa, khu neo đậu, các thiết bị neo đậu phương tiện và báo hiệu đường thủy nội địa tại cảng, bến thủy nội địa; tổ chức thực hiện các nhiệm vụ trong kế hoạch an ninh cảng thủy nội địa tiếp nhận phương tiện thủy nước ngoài.

2. Xây dựng nội quy hoạt động của cảng, bến thủy nội địa, khu neo đậu; niêm yết giá bốc xếp hàng hóa và các dịch vụ khác. Nội quy hoạt động, bảng niêm yết giá bốc xếp hàng hóa phải bố trí ở nơi thuận lợi dễ thấy, nội dung rõ ràng, dễ đọc.

3. Lắp đèn chiếu sáng khi hoạt động ban đêm; xây dựng nơi chờ cho hành khách đối với cảng, bến đón trả hành khách; đối với cảng, bến hành khách bố trí giao thông kết nối hỗ trợ người khuyết tật, người cao tuổi.

4. Thiết bị xếp dỡ bảo đảm tiêu chuẩn an toàn kỹ thuật và phù hợp với kết cấu, sức chịu lực của công trình. Bố trí người điều khiển thiết bị xếp dỡ phải có giấy chứng nhận, chứng chỉ điều khiển theo quy định của pháp luật.

5. Không tiếp nhận phương tiện không có giấy chứng nhận đăng ký, giấy chứng nhận an toàn kỹ thuật và bảo vệ môi trường hoặc giấy chứng nhận an toàn kỹ thuật và bảo vệ môi trường đã hết hạn sử dụng.

6. Không xếp hàng hóa vượt quá kích thước hoặc quá vạch dấu mớn nước an toàn của phương tiện hoặc xếp ô tô quá số lượng, vượt quá trọng tải xuống phương tiện; không xếp hành khách quá số lượng theo quy định xuống phương tiện; không xếp hàng hóa lên ô tô quá tải trọng cho phép.

7. Chấp hành đầy đủ các quy định của pháp luật về xếp dỡ hàng hóa độc hại, nguy hiểm.

8. Không cho phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài vào, rời cảng, bến thủy nội địa, khu neo đậu khi chưa có giấy phép vào, rời cảng, bến, khu neo đậu do Cảng vụ cấp.

9. Duy trì chuẩn tắc luồng chuyên dùng vào cảng, bến thủy nội địa, vùng nước cảng, bến thủy nội địa, khu neo đậu.

10. Chịu trách nhiệm bảo đảm an toàn, an ninh công trình cảng, bến thủy nội địa, khu neo đậu và hành khách, phương tiện neo đậu tại cảng, bến thủy nội địa, khu neo đậu.

11. Bố trí nhân lực quản lý, khai thác cảng, bến thủy nội địa, khu neo đậu bảo đảm trật tự, an toàn, an ninh và môi trường.

12. Trường hợp cảng, bến thủy nội địa, khu neo đậu được cho thuê, ủy quyền khai thác thì người thuê, người được ủy quyền quản lý khai thác phải tuân theo quy định của pháp luật về quản lý, khai thác kết cấu hạ tầng đường thủy nội địa quy định tại Nghị định này và quy định khác có liên quan của pháp luật.

13. Chủ động cứu người, hàng hóa, phương tiện khi xảy ra tai nạn; báo cáo và phối hợp với cơ quan chức năng có thẩm quyền giải quyết, khắc phục hậu quả tai nạn và ô nhiễm môi trường; tuân thủ sự điều động của Cảng vụ hoặc cơ quan liên quan trong việc cứu người, hàng hóa, phương tiện bị nạn trong vùng nước cảng, bến thủy nội địa và phòng chống thiên tai.

14. Tiếp nhận, bảo quản danh sách hành khách do người làm thủ tục giao.

15. Cập nhật thường xuyên dữ liệu cảng, bến thủy nội địa, khu neo đậu đang khai thác, số liệu phương tiện, hàng hóa, hành khách qua cảng, bến thủy nội địa, khu neo đậu trên cơ sở dữ liệu của Cục Đường thủy nội địa Việt Nam.

Điều 67. Trách nhiệm của thuyền trưởng, người lái phương tiện của phương tiện, tàu biển, phương tiện thủy nước ngoài, thủy phi cơ hoạt động trong vùng nước cảng, bến thủy nội địa và khu neo đậu

Thuyền trưởng, người lái phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài hoạt động trong vừng nước cảng, bến thủy nội địa và khu neo đậu có trách nhiệm thực hiện những quy định sau:

1. Neo đậu phương tiện tại nơi do Cảng vụ bố trí.

2. Tuân thủ nội quy cảng, bến thủy nội địa, khu neo đậu và các quy định về phòng chống thiên tai, phòng chống cháy, nổ, sự cố môi trường; chấp hành lệnh điều động của Cảng vụ trong các trường hợp khẩn cấp.

3. Phân công người trực ca để duy trì hoạt động của động cơ, thiết bị an toàn; thiết bị thông tin liên lạc; động cơ chính của phương tiện luôn ở trạng thái sẵn sàng hoạt động để xử lý kịp thời sự cố mất an toàn.

4. Trường hợp phát hiện trên phương tiện có người, động vật mắc bệnh truyền nhiễm hoặc thực vật có khả năng gây bệnh phải báo ngay cho Cảng vụ hoặc chính quyền địa phương nơi có cảng, bến thủy nội địa, khu neo đậu, cơ quan chức năng có liên quan và đưa phương tiện neo đậu tại khu vực riêng để có biện pháp xử lý.

5. Trong quá trình xếp, dỡ hàng hóa hoặc đón trả hành khách phải kiểm tra, chuẩn bị các điều kiện cần thiết bảo đảm an toàn lao động, nếu phát hiện dấu hiệu không an toàn, phải dừng ngay việc xếp, dỡ hàng hóa để có biện pháp khắc phục. Không xếp hàng hóa vượt quá kích thước của phương tiện, quá vạch dấu mớn nước an toàn, không nhận hành khách quá số lượng theo quy định.

6. Chỉ được cho phương tiện rời cảng, bến thủy nội địa, khu neo đậu khi phương tiện bảo đảm ổn định, điều kiện thời tiết, khí hậu thuận lợi. Thuyền trưởng, người lái phương tiện phải chịu trách nhiệm về sự an toàn, an ninh của hành khách, phương tiện, tàu biển, thủy phi cơ, phương tiện thủy nước ngoài khi rời cảng, bến thủy nội địa, khu neo đậu; sau khi rời cảng, bến thủy nội địa nếu có thay đổi về thuyền viên, thuyền trưởng phải thông báo cho Cảng vụ nơi cấp giấy phép rời cảng, bến thủy nội địa.

7. Không cản trở hoặc gây khó khăn cho người thi hành công vụ, thuyền viên của phương tiện khác đi qua phương tiện mình.

8. Khi phương tiện bị trôi dạt hoặc bị thay đổi nơi neo đậu do các nguyên nhân khách quan, phải tiến hành ngay các biện pháp bảo đảm an toàn và báo cho Cảng vụ biết.

9. Thuyền trưởng, thuyền viên, người lái phương tiện đang hoạt động tại cảng, bến thủy nội địa, khu neo đậu có nghĩa vụ bắt buộc cứu người và phương tiện thủy bị tai nạn xảy ra trong vùng nước cảng, bến thủy nội địa, khu neo đậu.

10. Khi phát hiện tai nạn hoặc nguy cơ xảy ra tai nạn, thuyền trưởng, thuyền viên hoặc người lái phương tiện bị nạn phải lập tức phát tín hiệu cấp cứu theo quy định và tiến hành ngay các biện pháp cứu người, tài sản, đồng thời thông báo cho Cảng vụ hoặc Công an, Ủy ban nhân dân cấp xã nơi có cảng, bến thủy nội địa để có biện pháp xử lý kịp thời.

11. Chấp hành sự huy động của Cảng vụ, Công an, chính quyền địa phương đưa phương tiện, thiết bị, dụng cụ tham gia tìm kiếm, cứu nạn.

12. Trường hợp phương tiện bị chìm đắm, sau khi cứu người, tài sản, thuyền trưởng hoặc người lái phương tiện bị đắm phải đặt báo hiệu theo quy định, tổ chức cảnh báo và báo cáo ngay cho chủ phương tiện để tiến hành trục vớt. Việc xử lý phương tiện, tài sản chìm đắm tại vùng nước cảng, bến thủy nội địa áp dụng theo quy định của Chính phủ về xử lý tài sản chìm đắm trên đường thủy nội địa.

13. Thuyền trưởng phương tiện thủy nước ngoài phải treo quốc kỳ nước Cộng hòa xã hội chủ nghĩa Việt Nam ở đỉnh cột cao nhất; trường hợp cần treo cờ lễ, cờ tang, kéo còi trong các dịp nghỉ lễ của nước mình, phải thông báo trước cho Cảng vụ.

Chương VII ĐIỀU KHOẢN THI HÀNH

Điều 68. Hiệu lực thi hành

1. Nghị định này có hiệu lực thi hành từ ngày 15 tháng 3 năm 2021.

2. Bãi bỏ Điều 3, Điều 4, Điều 5, Điều 10 Nghị định số 24/2015/NĐ-CP ngày 27 tháng 02 năm 2015 của Chính phủ quy định chi tiết và biện pháp thi hành một số điều của Luật Giao thông đường thủy nội địa và Luật sửa đổi, bổ sung một số điều của Luật Giao thông đường thủy nội địa.

3. Bãi bỏ quy định liên quan đến thủ tục điện tử đối với phương tiện thủy nội địa của Vương quốc Campuchia nhập cảnh, xuất cảnh tại cảng thủy nội địa Việt Nam và phương tiện thủy nội địa Việt Nam xuất cảnh tại cảng thủy nội địa đi Campuchia tại Quyết định số 34/2016/QĐ-TTg ngày 23 tháng 8 năm 2016 của

Điều 69. Điều khoản chuyển tiếp

1. Đối với luồng quốc gia đã được công bố đưa vào hoạt động trước ngày Nghị định này có hiệu lực thi hành, Cục Đường thủy nội địa Việt Nam tiếp tục tổ chức quản lý, bảo trì; đồng thời rà soát, phân loại, điều chuyển tài sản để đáp ứng các quy định tại khoản 2 Điều 7 Nghị định này.

2. Trường hợp các dự án đầu tư xây dựng công trình thuộc kết cấu hạ tầng đường thủy nội địa đã được chấp thuận chủ trương xây dựng trước ngày Nghị định này có hiệu lực thi hành và còn thời hạn thì tiếp tục được thực hiện theo nội dung của văn bản đã chấp thuận; trường hợp, thời hạn của văn bản chấp thuận đã hết mà chưa triển khai thực hiện dự án, nếu tiếp tục đầu tư xây dựng thì thực hiện theo quy định tại Nghị định này.

3. Cảng, bến thủy nội địa đã công bố, cấp phép hoạt động trước ngày Nghị định này có hiệu lực thi hành, được khai thác theo thời hạn ghi trong quyết định, giấy phép. Khi hết thời hạn, nếu tiếp tục khai thác thì thực hiện công bố lại hoạt động theo quy định tại Nghị định này.

4. Đối với cảng, bến thủy nội địa trong vùng nước cảng biển do các Cảng vụ thực hiện chức năng quản lý chuyên ngành tại cảng, bến thủy nội địa trước ngày Nghị định này có hiệu lực thi hành thì tiếp tục thực hiện chức năng quản lý đến hết ngày 31 tháng 12 năm 2023, từ ngày 01 tháng 01 năm 2024, hoạt động quản lý cảng, bến thủy nội địa trong vùng nước cảng biển thực hiện theo quy định tại Nghị định này.

5. Đối với cảng, bến thủy nội địa trong vùng nước cảng biển đã được chấp thuận chủ trương xây dựng trước ngày Nghị định này có hiệu lực thi hành thì tiếp tục thực hiện theo văn bản chấp thuận; cơ quan chấp thuận chủ trương xây dựng cảng, bến thủy nội địa công bố hoạt động của cảng, bến thủy nội địa.

6. Thời hạn lưu trữ của giấy phép vào, rời cảng, bến thủy nội địa, giấy phép rời cảng biển đã được cấp trước ngày Nghị định này có hiệu lực thi hành được tính theo quy định tại khoản 7 Điều 54 Nghị định này.

Điều 70. Trách nhiệm thi hành

Các Bộ trưởng, Thủ trưởng cơ quan ngang bộ, Thủ trưởng cơ quan thuộc Chính phủ, Chủ tịch Ủy ban nhân dân các tỉnh, thành phố trực thuộc trung ương và các tổ chức, cá nhân có liên quan chịu trách nhiệm thi hành Nghị định này.

TM. CHÍNH PHỦ
THỦ TƯỚNG CHÍNH PHỦ
(Đã ký)
Nguyễn Xuân Phúc
Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 76
76/2015/QH13 Luật Tổ chức Chính phủ số 76/2015/QH13 Hết hiệu lực 47/2019/QH14 Luật sửa đổi, bổ sung một số điều của Luật Tổ chức Chính phủ và Luật Tổ chức chính quyền địa phương số 47/2019/QH14 Hết hiệu lực 23/2004/QH11 Luật Giao thông đường thủy nội địa số 23/2004/QH11 Hết hiệu lực 48/2014/QH13 Luật Sửa đổi, bổ sung một số điều của Luật Giao thông đường thủy nội địa số 48/2014/QH13 Hết hiệu lực 42/2021/TT-BGTVT Thông tư số 42/2021/TT-BGTVT Quy định về công tác điều tiết khống chế bảo đảm an toàn giao thông, chống va trôi và hạn chế giao thông đường thủy nội địa Còn hiệu lực 19/2021/QĐ-UBND Quyết định số 19/2021/QĐ-UBND Quy định việc tổ chức thực hiện kế hoạch bảo trì công trình đường thủy nội địa trong phạm vi quản lý của tỉnh Kiên Giang Hết hiệu lực 33/2023/TT-BGTVT Thông tư số 33/2023/TT-BGTVT Quy định về phân cấp quản lý nhà nước chuyên ngành về giao thông vận tải đường thủy nội địa tại cảng, bến thủy nội địa, khu neo đậu Hết hiệu lực 57/2025/QĐ-UBND Quyết định số 57/2025/QĐ-UBND Ban hành Quy định về tổ chức quản lý hoạt động kinh doanh vận tải hành khách trong các khu du lịch và bến khách ngang sông trên địa bàn tỉnh Quảng Ngãi Còn hiệu lực 10/2021/TT-BGTVT Thông tư số 10/2021/TT-BGTVT Sửa đổi, bổ sung một số điều của Thông tư số 46/2016/TT-BGTVT ngày 29 tháng 12 năm 2016 của Bộ trưởng Bộ Giao thông vận tải quy định cấp kỹ thuật đường thủy nội địa Còn hiệu lực 126/2024/QĐ-UBND Quyết định số 126/2024/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy định về quản lý hoạt động vận tải khách du lịch đường thủy trên địa bàn Thành phố Hồ Chí Minh ban hành kèm theo Quyết định số 15/2021/QĐ-UBND ngày 20 tháng 5 năm 2021 của Ủy ban nhân dân Thành phố Hồ Chí Minh Còn hiệu lực 18/2025/TT-BXD Thông tư số 18/2025/TT-BXD Quy định về tổ chức và hoạt động của Cảng vụ hàng hải, Cảng vụ đường thủy nội địa Còn hiệu lực 33/2022/TT-BGTVT Thông tư số 33/2022/TT-BGTVT Sửa đổi, bổ sung một số điều của Thông tư số 39/2019/TT-BGTVT ngày 15 tháng 10 năm 2019 của Bộ trưởng Bộ Giao thông vận tải quy định trách nhiệm của chủ phương tiện, thuyền viên, người lái phương tiện, đảm nhiệm chức danh thuyền viên và định biên an toàn tối thiểu trên phương tiện thủy nội địa Còn hiệu lực 253/2025/QĐ-UBND Quyết định số 253/2025/QĐ-UBND Ban hành Quy chế quản lý hoạt động du lịch và phương tiện thủy nội địa phục vụ khách du lịch trên các vịnh thuộc quần đảo Cát Bà, đặc khu Cát Hải, thành phố Hải Phòng Còn hiệu lực 18/2021/TT-BGTVT Thông tư số 18/2021/TT-BGTVT Quy định về tổ chức và hoạt động của Cảng vụ đường thủy nội địa Hết hiệu lực 36/2021/TT-BGTVT Thông tư số 36/2021/TT-BGTVT Quy định công tác khảo sát luồng đường thủy nội địa Còn hiệu lực 22/2021/TT-BGTVT Thông tư số 22/2021/TT-BGTVT Quy định về phương pháp và tiêu chuẩn đánh giá hồ sơ dự thầu lựa chọn nhà đầu tư thực hiện dự án nạo vét vùng nước cảng biển, vùng nước đường thủy nội địa kết hợp thu hồi sản phẩm Hết hiệu lực 61/2024/TT-BGTVT Thông tư số 61/2024/TT-BGTVT Sửa đổi, bổ sung một số điều của Thông tư số 18/2021/TT-BGTVT ngày 14 tháng 9 năm 2021 của Bộ trưởng Bộ Giao thông vận tải quy định về tổ chức và hoạt động của Cảng vụ đường thủy nội địa Hết hiệu lực 56/2022/TT-BCA Thông tư số 56/2022/TT-BCA Quy định về quản lý hoạt động cảng, bến thủy nội địa của lực lượng Công an nhân dân Còn hiệu lực 21/2022/TT-BGTVT Thông tư số 21/2022/TT-BGTVT Quy định về quản lý, bảo trì công trình thuộc kết cấu hạ tầng đường thủy nội địa Còn hiệu lực 39/2026/TT-BTC Thông tư 39/2026/TT-BTC Quy định mức thu, chế độ thu, nộp phí, lệ phí áp dụng tại cảng, bến thủy nội địa Còn hiệu lực 16/2021/QĐ-UBND Quyết định số 16/2021/QĐ-UBND Quy định cấp kỹ thuật đường thủy nội địa thuộc phạm vi quản lý của tỉnh Kiên Giang Còn hiệu lực 01/2026/NQ-HĐND Nghị quyết số 01/2026/NQ-HĐND Quy định nội dung chi thường xuyên hoạt động kinh tế giao thông đường thủy nội địa do địa phương quản lý trên địa bàn thành phố Cần Thơ Còn hiệu lực 14/2026/QĐ-UBND Quyết định số 14/2026/QĐ-UBND Phân cấp quản lý, bảo trì kết cấu hạ tầng đường thủy nội địa trên địa bàn tỉnh Vĩnh Long Còn hiệu lực '40/2025/QĐ-UBND Quyết định số '40/2025/QĐ-UBND Ban hành quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Cảng vụ đường thủy nội địa thuộc Sở Xây dựng tỉnh Ninh Bình Còn hiệu lực 90/2025/QĐ-UBND Quyết định số 90/2025/QĐ-UBND Phân cấp một số nội dung về quản lý hoạt động giao thông đường thủy nội địa trên địa bàn tỉnh Hà Tĩnh Còn hiệu lực 202/2025/QĐ-UBND Quyết định số 202/2025/QĐ-UBND Ban hành quy định một số nội dung về quản lý, vận hành, khai thác, bảo trì kết cấu hạ tầng đường thủy nội địa, hàng hải trên địa bàn thành phố Hải Phòng Còn hiệu lực 195/2025/QĐ-UBND Quyết định số 195/2025/QĐ-UBND Ban hành Quy định về quản lý hoạt động của cảng, bến thủy nội địa, khu neo đậu trên tuyến đường thủy nội địa trên địa bàn thành phố Hải Phòng Còn hiệu lực 58/2025/QĐ-UBND Quyết định số 58/2025/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Cảng vụ đường thủy nội địa thành phố Đà Nẵng trực thuộc Sở Xây dựng thành phố Đà Nẵng Còn hiệu lực 65/2025/QĐ-UBND Quyết định số 65/2025/QĐ-UBND Quy định thẩm quyền trong lĩnh vực quản lý nhà nước về xây dựng trên địa bàn tỉnh Quảng Ninh Còn hiệu lực 79/2025/QĐ-UBND Quyết định số 79/2025/QĐ-UBND Sửa đổi, bổ sung một số điều của Quyết định số 25/2021/QĐ-UBND ngày 08/10/2021 của UBND tỉnh về việc phân cấp cho UBND các huyện, thị xã, thành phố thực hiện một số nhiệm vụ được quy định tại Nghị định số 08/2021/NĐ-CP ngày 28/01/2021 của Chính phủ quy định về quản lý hoạt động đường thuỷ nội địa trên địa bàn tỉnh. Còn hiệu lực 70/2025/QĐ-UBND Quyết định số 70/2025/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Trung tâm Điều hành giao thông thuộc Sở Xây dựng tỉnh Ninh Bình Hết hiệu lực 77/2025/QĐ-UBND Quyết định số 77/2025/QĐ-UBND Ban hành Quy định quản lý nhà nước trong lĩnh vực giao thông đường thủy nội địa theo Nghị định số 84/2024/NĐ-CP ngày 10 tháng 7 năm 2024 của Chính phủ về thí điểm phân cấp quản lý nhà nước một số lĩnh vực cho chính quyền Thành phố Hồ Chí Minh Còn hiệu lực 53/2025/QĐ-UBND Quyết định số 53/2025/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Cảng vụ Đường thủy nội địa tỉnh An Giang trực thuộc Sở Xây dựng tỉnh An Giang Còn hiệu lực 56/2025/QĐ-UBND Quyết định số 56/2025/QĐ-UBND Ban hành Quy định về quản lý, sử dụng hành lang bảo vệ trên bờ sông, kênh, rạch, mương, hồ và ao thuộc địa bàn Thành phố Hồ Chí Minh Còn hiệu lực 43/2025/QĐ-UBND Quyết định số 43/2025/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy chế phối hợp quản lý phương tiện thủy hoạt động trên địa bàn Thành phố Hồ Chí Minh ban hành kèm theo Quyết định số 29/2020/QĐ-UBND ngày 24 tháng 11 năm 2020 của Ủy ban nhân dân Thành phố Còn hiệu lực 13/2025/QĐ-UBND Quyết định số 13/2025/QĐ-UBND Về tổ chức quản lý hoạt động của phương tiện phục vụ vui chơi, giải trí dưới nước trên địa bàn Thành phố Hồ Chí Minh Còn hiệu lực 72/2024/QĐ-UBND Quyết định số 72/2024/QĐ-UBND Ban hành Quy định về quản lý hoạt động vận tải khách du lịch bằng đường thủy nội địa và hoạt động của phương tiện phục vụ vui chơi, giải trí dưới nước trên địa bàn tỉnh Nghệ An Còn hiệu lực 43/2024/QĐ-UBND Quyết định số 43/2024/QĐ-UBND Về việc ban hành Quy định các biện pháp quản lý hoạt động của phương tiện thủy nội địa phục vụ khách du lịch trên vịnh Hạ Long, vịnh Bái Tử Long Còn hiệu lực 32/2024/QĐ-UBND Quyết định số 32/2024/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy định tổ chức, quản lý các phương tiện hoạt động phục vụ khách du lịch trên địa bàn tỉnh Bến Tre ban hành kèm theo Quyết định số 20/2019/QĐ-UBND ngày 02 tháng 5 năm 2019 của Ủy ban nhân dân tỉnh Bến Tre Còn hiệu lực 20/2024/QĐ-UBND Quyết định số 20/2024/QĐ-UBND Bãi bỏ Quyết định số 20/2021/QĐ-UBND ngày 17 tháng 6 năm 2021 của Ủy ban nhân dân tỉnh Bạc Liêu về việc phân cấp cho Ủy ban nhân dân các huyện, thị xã, thành phố thỏa thuận xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính trên địa bàn thuộc phạm vi quản lý Còn hiệu lực 15/2024/QĐ-UBND Quyết định số 15/2024/QĐ-UBND Bãi bỏ Quyết định số 57/2021/QĐ-UBND ngày 20/12/2021 của UBND tỉnh phân cấp thỏa thuận xây dựng bến khách ngang sông trên địa bàn tỉnh Long An Còn hiệu lực 02/2024/QĐ-UBND Quyết định số 02/2024/QĐ-UBND Ban hành Quy định quản lý và khai thác Hồ Tây Còn hiệu lực 06/2024/QĐ-UBND Quyết định số 06/2024/QĐ-UBND Bãi bỏ Quyết định số 13/2021/QĐ-UBND ngày 10 tháng 8 năm 2021 của Ủy ban nhân dân tỉnh Phú Thọ về phân cấp thẩm quyền thỏa thuận thông số kỹ thuật xây dựng, công bố, công bố lại, gia hạn hoạt động bến khách ngang sông trên địa bàn tỉnh Phú Thọ Hết hiệu lực 43/2023/QĐ-UBND Quyết định số 43/2023/QĐ-UBND Phân cấp thẩm quyền quản lý bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính trên địa bàn tỉnh Bình Dương Hết hiệu lực 28/2023/QĐ-UBND Quyết định số 28/2023/QĐ-UBND Sửa đổi một số điều của Quy định về quản lý hoạt động bến khách ngang sông trên địa bàn tỉnh Tiền Giang ban hành kèm theo Quyết định số 30/2019/QĐ-UBND ngày 25/11/2019 của Ủy ban nhân dân tỉnh Tiền Giang Hết hiệu lực 36/2023/QĐ-UBND Quyết định số 36/2023/QĐ-UBND Quy định khung giá dịch vụ sử dụng bến thủy nội địa được đầu tư bằng nguồn vốn ngân sách nhà nước trên địa bàn huyện Cát Hải Hết hiệu lực 17/2023/QĐ-UBND Quyết định số 17/2023/QĐ-UBND Phân cấp thẩm quyền quản lý bến khách ngang sông trên địa bàn thành phố Cần Thơ Hết hiệu lực 24/2023/QĐ-UBND Quyết định số 24/2023/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Cảng vụ Đường thủy nội địa tỉnh An Giang trực thuộc Sở Giao thông vận tải tỉnh An Giang Hết hiệu lực 38/2022/QĐ-UBND Quyết định số 38/2022/QĐ-UBND Ban hành Quy định tiêu chí đánh giá tần suất khảo sát định kỳ luồng đường thủy nội địa địa phương trên địa bàn tỉnh Nghệ An Còn hiệu lực 56/2022/QĐ-UBND Quyết định số 56/2022/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Cảng vụ đường thuỷ nội địa trực thuộc Sở Giao thông vận tải tỉnh Ninh Bình Hết hiệu lực 29/2022/QĐ-UBND Quyết định số 29/2022/QĐ-UBND Phân cấp thẩm quyền thỏa thuận thông số kỹ thuật xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính trên địa bàn tỉnh Ninh Bình Còn hiệu lực 37/2022/QĐ-UBND Quyết định số 37/2022/QĐ-UBND Phân cấp thực hiện một số nhiệm vụ quản lý hoạt động đường thủy nội địa trên địa bàn tỉnh Gia Lai Hết hiệu lực 23/2022/QĐ-UBND Quyết định số 23/2022/QĐ-UBND Về việc phân cấp thực hiện thỏa thuận xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính và chấp thuận phương án bảo đảm an toàn giao thông đối với công trình, hoạt động trên vùng nước chưa được tổ chức quản lý nhưng có hoạt động vận tải trên địa bàn tỉnh Hết hiệu lực 29/2022/QĐ-UBND Quyết định số 29/2022/QĐ-UBND Phân cấp thẩm quyền quản lý bến khách ngang sông trên địa bàn thành phố Cần Thơ Hết hiệu lực 19/2022/QĐ-UBND Quyết định số 19/2022/QĐ-UBND Sửa đổi, bổ sung một số điều của Quyết định số 15/2021/QĐ-UBND ngày 20 tháng 5 năm 2021 của Ủy ban nhân dân Thành phố ban hành Quy định về quản lý hoạt động vận tải khách du lịch đường thủy trên địa bàn Thành phố Hồ Chí Minh Còn hiệu lực 22/2022/QĐ-UBND Quyết định số 22/2022/QĐ-UBND Về việc phân cấp quản lý các tuyến đường thủy nội địa trên địa bàn tỉnh Long An Còn hiệu lực 02/2022/QĐ-UBND Quyết định số 02/2022/QĐ-UBND Về quản lý hoạt động, bảo trì công trình đường thuỷ nội địa và vùng nước trên địa bàn tỉnh Thừa Thiên Huế Còn hiệu lực 02/2022/QĐ-UBND. Quyết định số 02/2022/QĐ-UBND. Ban hành Quy định về quản lý hoạt động, bảo trì công trình đường thủy nội địa và Vùng nước trên địa bàn tỉnh Thừa Thiên Huế Còn hiệu lực 03/2022/QĐ-UBND Quyết định số 03/2022/QĐ-UBND Phân cấp thẩm quyền quản lý hoạt động đường thủy nội địa trên địa bàn tỉnh Vĩnh Long Hết hiệu lực 57/2021/QĐ-UBND Quyết định số 57/2021/QĐ-UBND Phân cấp thỏa thuận xây dựng bến khách ngang sông trên địa bàn tỉnh Long An Hết hiệu lực 32/2021/QĐ-UBND Quyết định số 32/2021/QĐ-UBND Phân cấp thẩm quyền thực hiện thỏa thuận thông số kỹ thuật xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính trên địa bàn tỉnh Bắc Giang Hết hiệu lực 36/2024/QĐ-UBND Quyết định số 36/2024/QĐ-UBND Bãi bỏ Quyết định số 32/2021/QĐ-UBND ngày 30 tháng 7 năm 2021 của Ủy ban nhân dân tỉnh Bắc Giang phân cấp thẩm quyền thực hiện thoả thuận thông số kỹ thuật xây dựng bến khách ngang sông, bến thuỷ nội địa phục vụ thi công công trình chính trên địa bàn tỉnh Bắc Giang Còn hiệu lực 58/2022/QĐ-UBND Quyết định số 58/2022/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy định quản lý hoạt động bến khách ngang sông trên địa bàn tỉnh An Giang ban hành kèm theo Quyết định số 54/2021/QĐ-UBND Hết hiệu lực 47/2022/QĐ-UBND Quyết định số 47/2022/QĐ-UBND Phân cấp thẩm quyền quản lý hoạt động đường thủy nội địa trên địa bàn tỉnh Hậu Giang Hết hiệu lực 42/2022/QĐ-UBND Quyết định số 42/2022/QĐ-UBND Phân cấp thẩm quyền thỏa thuận thông số kỹ thuật xây dựng, công bố, công bố lại, gia hạn hoạt động bến khách ngang sông trên địa bàn tỉnh Tuyên Quang Còn hiệu lực 31/2021/NQ-HĐND Nghị quyết số 31/2021/NQ-HĐND Quy định các nội dung chi thường xuyên hoạt động kinh tế giao thông đường thủy nội địa do địa phương quản lý trên địa bàn tỉnh Hậu Giang Hết hiệu lực 54/2021/QĐ-UBND Quyết định số 54/2021/QĐ-UBND Ban hành Quy định quản lý hoạt động bến khách ngang sông trên địa bàn tỉnh An Giang Hết hiệu lực 25/2021/QĐ-UBND Quyết định số 25/2021/QĐ-UBND Về việc phân cấp cho UBND các huyện, thị xã, thành phố thực hiện một số nhiệm vụ được quy định tại Nghị định số 08/2021/NĐ-CP ngày 28/01/2021 của Chính phủ quy định về quản lý hoạt động đường thủy nội địa trên địa bàn tỉnh Thanh Hóa Còn hiệu lực 19/2021/QĐ-UBND Quyết định số 19/2021/QĐ-UBND Phân cấp cho Ủy ban nhân dân các huyện, thành phố Cà Mau trong quản lý hoạt động đường thủy nội địa Còn hiệu lực 13/2021/QĐ-UBND Quyết định số 13/2021/QĐ-UBND Phân cấp thẩm quyền thỏa thuận thông số kỹ thuật xây dựng, công bố, công bố lại, gia hạn hoạt động bến khách ngang sông trên địa bàn tỉnh Phú Thọ Hết hiệu lực 20/2021/QĐ-UBND Quyết định số 20/2021/QĐ-UBND Về việc phân cấp cho Ủy ban nhân dân các huyện, thị xã, thành phố thỏa thuận xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính trên địa bàn thuộc phạm vi quản lý Hết hiệu lực 13/2021/QĐ-UBND Quyết định số 13/2021/QĐ-UBND Sửa đổi Điều 10 của Quy định về phối hợp, phân cấp quản lý, bảo vệ hành lang an toàn đường bộ và đường thủy nội địa địa phương trên địa bàn tỉnh Bạc Liêu ban hành kèm theo Quyết định số 23/2016/QĐ-UBND ngày 29/9/2016 của Ủy ban nhân dân tỉnh Còn hiệu lực 31/2024/QĐ-UBND Quyết định số 31/2024/QĐ-UBND Quy định việc lập, phê duyệt và tổ chức thực hiện kế hoạch bảo trì công trình đường thuỷ nội địa thuộc phạm vi quản lý của tỉnh Kiên Giang Còn hiệu lực 98/2024/QĐ-UBND Quyết định số 98/2024/QĐ-UBND Quy định một số nội dung về cung ứng dịch vụ sự nghiệp công sử dụng ngân sách nhà nước trong quản lý, bảo trì kết cấu hạ tầng giao thông đường bộ, đường thủy nội địa trên địa bàn tỉnh Ninh Bình Hết hiệu lực 39/2026/QĐ-UBND Quyết định số 39/2026/QĐ-UBND Ban hành Quy định về phân cấp cho Sở Nông nghiệp và Môi trường, Sở Xây dựng, Ủy ban nhân dân xã, phường, đặc khu quản lý, khai thác các tuyến sông, suối, kênh, rạch, hồ, đập thuộc thẩm quyền quản lý của Ủy ban nhân dân Thành phố Hồ Chí Minh Còn hiệu lực 46/2026/NQ-HĐND Nghị quyết Quy định nội dung chi thường xuyên hoạt động kinh tế giao thông đường thủy nội địa do địa phương quản lý trên địa bàn tỉnh Thái Nguyên Còn hiệu lực
Được dẫn chiếu bởi 7
02/2022/QĐ-UBND Quyết định số 02/2022/QĐ-UBND V/v ban hành Quy chế phối hợp thực hiện nhiệm vụ quản lý nhà nước đối với khu kinh tế Đình Vũ Cát Hải và các khu công nghiệp trên địa bàn thành phố Hải Phòng Hết hiệu lực 06/2024/QĐ-UBND Quyết định số 06/2024/QĐ-UBND Ban hành Quy định về chức năng, nhiệm vụ, quyền hạn và tổ chức của Phòng Tài chính – Kế hoạch thuộc Ủy ban nhân dân Quận 11 Còn hiệu lực 42/2022/QĐ-UBND QUYẾT ĐỊNH SỐ 42/2022/QĐ-UBND BÃI BỎ QUYẾT ĐỊNH SỐ 14/2018/QĐ-UBND NGÀY 03 THÁNG 5 NĂM 2018 CỦA UỶ BAN NHÂN DÂN TỈNH VỀ BAN HÀNH QUY ĐỊNH VỀ XỬ LÝ VI PHẠM TRONG GIẢI QUYẾT HỒ SƠ THỦ TỤC HÀNH CHÍNH LIÊN QUAN ĐẾN CÁ NHÂN, TỔ CHỨC TẠI CÁC CƠ QUAN, ĐƠN VỊ, ĐỊA PHƯƠNG TRÊN ĐỊA BÀN TỈNH PHÚ YÊN Còn hiệu lực 42/2023/QĐ-UBND Quyết định số 42/2023/QĐ-UBND Ban hành Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Sở Kế hoạch và Đầu tư Thành phố Hồ Chí Minh Hết hiệu lực 140/2025/NĐ-CP Nghị định số 140/2025/NĐ-CP Quy định về phân định thẩm quyền của chính quyền địa phương 02 cấp trong lĩnh vực quản lý nhà nước của Bộ Xây dựng Còn hiệu lực 06/2024/QĐ-UBND Quyết định số 06/2024/QĐ-UBND Ban hành Quy chế quản lý kiến trúc đô thị Phong Điền, tỉnh Thừa Thiên Huế Còn hiệu lực 42/2023/QĐ-UBND Quyết định số 42/2023/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy chế quản lý hoạt động du lịch trên các vịnh thuộc quần đảo Cát Bà, huyện Cát Hải, thành phố Hải Phòng ban hành kèm theo Quyết định số 26/2020/QĐ-UBND ngày 02/10/2020 của Ủy ban nhân dân thành phố Hải Phòng Hết hiệu lực
Bị bãi bỏ bởi 1
08/2021/NĐ-CP
Decree No. 08/2021/ND-CP on management of inland waterway activities
In effect
↓ Văn bản chịu tác động từ văn bản này
Liên quan 46
03/2022/QĐ-UBND Quyết định số 03/2022/QĐ-UBND Ban hành Quy chế về tổ chức và hoạt động của Phòng Tư pháp thuộc Ủy ban nhân dân huyện Nhà Bè Hết hiệu lực 37/2026/QĐ-UBND Quyết định số 37/2026/QĐ-UBND Ban hành Quy chế đào tạo, bồi dưỡng đối với công chức trên địa bàn tỉnh Đồng Tháp Còn hiệu lực 29/2022/QĐ-UBND Quyết định số 29/2022/QĐ-UBND Ban hành Khung giá các loại rừng trên địa bàn tỉnh Khánh Hòa Hết hiệu lực 202/2025/QĐ-UBND Quyết định số 202/2025/QĐ-UBND Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Trường Trung học phổ thông Hàm Giang thuộc Sở Giáo dục và Đào tạo tỉnh Vĩnh Long Còn hiệu lực 02/2024/QĐ-UBND Quyết định số 02/2024/QĐ-UBND Ban hành quy định về chức năng, nhiệm vụ, quyền hạn và tổ chức của Phòng Tài nguyên và Môi trường thuộc Ủy ban nhân dân Quận 11 Còn hiệu lực 15/2024/QĐ-UBND Quyết định số 15/2024/QĐ-UBND quy định về phân cấp quản lý đối với cán bộ, công chức cấp xã trên địa bàn tỉnh Hết hiệu lực 77/2025/QĐ-UBND Quyết định số 77/2025/QĐ-UBND Quy định mật độ chăn nuôi trên địa bàn tỉnh Đồng Nai đến năm 2030. Còn hiệu lực 79/2025/QĐ-UBND Quyết định số 79/2025/QĐ-UBND Ban hành Quy chế phối hợp giữa các cơ quan quản lý nhà nước tại địa phương trong công tác quản lý nhà nước đối với doanh nghiệp, hộ kinh doanh sau đăng ký thành lập trên địa bàn tỉnh Gia Lai Còn hiệu lực 54/2021/QĐ-UBND Quyết định số 54/2021/QĐ-UBND Về việc quy định hệ số điều chỉnh giá đất để xác định giá đất cụ thể tính tiền sử dụng đất đối với các trường hợp giao đất, công nhận quyền sử dụng đất, chuyển mục đích sử dụng đất năm 2022 trên địa bàn tỉnh Hà Nam Còn hiệu lực 72/2024/QĐ-UBND Quyết định số 72/2024/QĐ-UBND Ban hành Quy chế quản lý các hoạt động tại không gian đi bộ khu vực hồ Hoàn Kiếm và phụ cận Còn hiệu lực 23/2022/QĐ-UBND Quyết định số 23/2022/QĐ-UBND Về việc quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Sở Khoa học và Công nghệ tỉnh Thanh Hóa Còn hiệu lực 28/2023/QĐ-UBND Quyết định số 28/2023/QĐ-UBND Ban hành Quy chế quản lý, vận hành, khai thác cơ sở dữ liệu về giá trên địa bàn tỉnh Thái Nguyên Hết hiệu lực 13/2021/QĐ-UBND Quyết định số 13/2021/QĐ-UBND Ban hành quy định một số nội dung và mức hỗ trợ doanh nghiệp, tổ chức, cá nhân trong hoạt động khoa học và công nghệ; hệ sinh thái khởi nghiệp và đổi mới sáng tạo trên địa bàn tỉnh Ninh Thuận giai đoạn 2021-2025 Còn hiệu lực 37/2022/QĐ-UBND Quyết định số 37/2022/QĐ-UBND Ban hành Định mức kinh tế kỹ thuật trong công tác quản lý, khai thác và bảo vệ công trình thủy lợi trên địa bàn tỉnh Đắk Nông Còn hiệu lực 36/2023/QĐ-UBND Quyết định số 36/2023/QĐ-UBND Phân cấp thẩm quyền cho các sở, ban, ngành, đoàn thể cấp tỉnh và UBND các huyện, thành phố ban hành tiêu chuẩn, định mức sử dụng máy móc, thiết bị chuyên dùng của các đơn vị thuộc phạm vi quản lý Hết hiệu lực 20/2024/QĐ-UBND Quyết định số 20/2024/QĐ-UBND Về điều chỉnh Quy định giá các loại đất định kỳ 05 năm giai đoạn 2020-2024 trên địa bàn tỉnh Khánh Hòa ban hành kèm theo Quyết định số 04/2020/QĐ-UBND ngày 18/02/2020 của Ủy ban nhân dân tỉnh Hết hiệu lực 43/2024/QĐ-UBND Quyết định số 43/2024/QĐ-UBND Sửa đổi, bổ sung khoản 2, Điều 3 Quyết định số 23/2019/QĐ-UBND ngày 26 tháng 11 năm 2019 của Ủy ban nhân dân tỉnh Bắc Kạn về việc ban hành tiêu chuẩn, định mức sử dụng diện tích chuyên dùng nhà làm việc của các cơ quan, tổ chức, đơn vị và diện tích các công trình sự nghiệp thuộc cơ sở hoạt động sự nghiệp thuộc phạm vi quản lý của tỉnh Bắc Kạn Hết hiệu lực 13/2025/QĐ-UBND Quyết định số 13/2025/QĐ-UBND Phân cấp thực hiện quy định về người lao động nước ngoài làm việc trên địa bàn tỉnh An Giang Còn hiệu lực 47/2022/QĐ-UBND Quyết định số 47/2022/QĐ-UBND Về việc ban hành hệ số điều chỉnh giá đất năm 2023 theo quy định của pháp luật làm căn cứ tính: thu tiền sử dụng đất khi giao đất không thông qua đấu giá, thu tiền sử dụng đất khi tổ chức được công nhận quyền sử dụng đất, chuyển mục đích sử dụng đất; thu tiền sử dụng đất khi bán lại nhà ở xã hội; xác định giá khởi điểm để đấu giá quyền sử dụng đất ở trên địa bàn thành phố Hà Nội Hết hiệu lực 40/2025/QĐ-UBND Quyết định số 40/2025/QĐ-UBND Quy định tỷ lệ (mức) khoán chi phí quản lý, xử lý tài sản là tang vật, phương tiện vi phạm hành chính bị tịch thu được xác lập quyền sở hữu toàn dân trên địa bàn tỉnh Lâm Đồng Còn hiệu lực 53/2025/QĐ-UBND Quyết định số 53/2025/QĐ-UBND Ban hành Quy định phân cấp quản lý nhà nước về an toàn thực phẩm thuộc trách nhiệm quản lý của ngành Công Thương trên địa bàn tỉnh Quảng Trị Còn hiệu lực 24/2023/QĐ-UBND Quyết định số 24/2023/QĐ-UBND Phân cấp quản lý công trình thủy lợi và quy mô thủy lợi nội đồng trên địa bàn tỉnh Thái Nguyên Hết hiệu lực 58/2022/QĐ-UBND QUYẾT ĐỊNH SỐ 58/2022/QĐ-UBND QUY ĐỊNH CHỨC NĂNG, NHIỆM VỤ, QUYỀN HẠN VÀ CƠ CẤU TỔ CHỨC CỦA VĂN PHÒNG ỦY BAN NHÂN DÂN TỈNH NGHỆ AN Hết hiệu lực 20/2021/QĐ-UBND Quyết định số 20/2021/QĐ-UBND Quy định khung giá dịch vụ sử dụng cảng cá trên địa bàn tỉnh Kiên Giang Còn hiệu lực 90/2025/QĐ-UBND Quyết định số 90/2025/QĐ-UBND Ban hành Quy định chi tiết một số nội dung về quản lý đường bộ trên địa bàn tỉnh Điện Biên Còn hiệu lực 56/2025/QĐ-UBND Quyết định số 56/2025/QĐ-UBND Ban hành Quy định một số nội dung về quản lý hệ thống đường bộ thuộc phạm vi quản lý của Ủy ban nhân dân tỉnh Quảng Trị Còn hiệu lực 58/2025/QĐ-UBND Quyết định số 58/2025/QĐ-UBND Ban hành Quy định thời gian, phạm vi hoạt động vận chuyển hành khách bằng xe bốn bánh có gắn động cơ, hoạt động vận chuyển hàng hóa bằng xe chở hàng bốn bánh có gắn động cơ; phạm vi hoạt động của xe thô sơ, xe chở hàng bốn bánh có gắn động cơ, xe chở người bốn bánh có gắn động cơ trên địa bàn tỉnh Quảng Ngãi Còn hiệu lực 65/2025/QĐ-UBND Quyết định số 65/2025/QĐ-UBND Ban hành quy chế phối hợp trong công tác quản lý nhà nước đối với doanh nghiệp, hộ kinh doanh sau đăng ký thành lập trên địa bàn tỉnh Bắc Ninh Còn hiệu lực 32/2021/QĐ-UBND Quyết định số 32/2021/QĐ-UBND Phân cấp thỏa thuận thông số kỹ thuật xây dựng bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính và phân cấp công bố hoạt động bến khách ngang sông, bến thủy nội địa phục vụ thi công công trình chính cho Ủy ban nhân dân các huyện, thị xã, thành phố trên địa bàn tỉnh Hải Dương Hết hiệu lực 36/2024/QĐ-UBND Quyết định số 36/2024/QĐ-UBND Quy định mức tỷ lệ phần trăm (%) để tính đơn giá thuê đất; mức đơn giá thuê đất xây dựng công trình ngầm; mức đơn giá thuê đất đối với đất có mặt nước trên địa bàn tỉnh Bắc Kạn Hết hiệu lực 31/2024/QĐ-UBND Quyết định số 31/2024/QĐ-UBND Ban hành Quy định định mức kinh tế - kỹ thuật để tổ chức xây dựng bảng giá đất, xác định giá đất cụ thể trên địa bàn tỉnh Yên Bái Còn hiệu lực 70/2025/QĐ-UBND Quyết định số 70/2025/QĐ-UBND Sửa đổi, bổ sung một số nội dung của Quyết định số 48/2024/QĐ-UBND ngày 22/7/2024 của UBND thành phố Hà Nội về ban hành định mức kinh tế - kỹ thuật dịch vụ sự nghiệp công sử dụng ngân sách nhà nước trong lĩnh vực người có công của thành phố Hà Nội Còn hiệu lực 57/2021/QĐ-UBND Quyết định số 57/2021/QĐ-UBND Sửa đổi khoản 2 Điều 3 Quyết định số 32/2020/QĐ-UBND ngày 25 tháng 11 năm 2020 của Ủy ban nhân dân tỉnh Hà Giang Hết hiệu lực 195/2025/QĐ-UBND Quyết định số 195/2025/QĐ-UBND Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Trường Trung học phổ thông Trương Vĩnh Ký thuộc Sở Giáo dục và Đào tạo tỉnh Vĩnh Long Còn hiệu lực 22/2022/QĐ-UBND QUYẾT ĐỊNH SỐ 22/2022/QĐ-UBND SỬA ĐỔI, BỔ SUNG MỘT SỐ ĐIỀU CỦA QUYẾT ĐỊNH SỐ 25/2021/QĐ-UBND NGÀY 10 THÁNG 8 NĂM 2021 CỦA UBND TỈNH SỬA ĐỔI, BỔ SUNG MỘT SỐ ĐIỀU CỦA QUY ĐỊNH HẠN MỨC GIAO ĐẤT, CÔNG NHẬN QUYỀN SỬ DỤNG ĐẤT CHO MỖI HỘ GIA ĐÌNH, CÁ NHÂN TRÊN ĐỊA BÀN TỈNH PHÚ YÊN BAN HÀNH KÈM THEO QUYẾT ĐỊNH SỐ 38/2014/QĐ-UBND NGÀY 14 THÁNG 10 NĂM 2014, QUYẾT ĐỊNH SỐ 38/2018/QĐ-UBND NGÀY 10 THÁNG 9 NĂM 2018 CỦA UBND TỈNH PHÚ YÊN Hết hiệu lực 43/2025/QĐ-UBND Quyết định số 43/2025/QĐ-UBND Quy định định mức số lượng học sinh trên lớp đối với những trường hợp đặc biệt tại các cơ sở giáo dục phổ thông công lập trên địa bàn tỉnh Quảng Trị Còn hiệu lực 19/2022/QĐ-UBND QUYẾT ĐỊNH SỐ 19/2022/QĐ-UBND SỬA ĐỔI, BỔ SUNG MỘT SỐ ĐIỀU CỦA QUYÊT ĐINH SÔ 53/2019/QĐ-UBND NGAY 20/12/2019 CỦA UBND TỈNH PHÚ YÊN VỀ VIỆC BAN HÀNH BANG GIA CAC LOAI ĐÂT TRÊN ĐIA BAN TINH PHU YÊN 05 NĂM (2020-2024) Hết hiệu lực 17/2023/QĐ-UBND Quyết định số 17/2023/QĐ-UBND Về chính sách ưu đãi tiền thuê đất trong các lĩnh vực: Giáo dục - đào tạo, dạy nghề, y tế, văn hóa, thể dục thể thao, môi trường, giám định tư pháp trên địa bàn thành phố Hà Nội Hết hiệu lực 43/2023/QĐ-UBND Quyết định số 43/2023/QĐ-UBND Ban hành Quy định và Hướng dẫn xét công nhận Tiêu chí cơ sở hạ tầng thương mại nông thôn trong Bộ tiêu chí quốc gia về xã nông thôn mới và xã nông thôn mới nâng cao giai đoạn 2023-2025 trên địa bàn tỉnh Vĩnh Phúc Hết hiệu lực 56/2022/QĐ-UBND Quyết định số 56/2022/QĐ-UBND Ban hành quy định quản lý, vận hành và bảo trì công trình đối với các dự án đầu tư xây dựng theo cơ chế đặc thù thuộc chương trình mục tiêu quốc gia giai đoạn 2021-2025 trên địa bàn tỉnh Thừa Thiên Huế Còn hiệu lực 32/2024/QĐ-UBND Quyết định số 32/2024/QĐ-UBND Quy định diện tích đất, vị trí, mục đích của công trình xây dựng phục vụ trực tiếp sản xuất nông nghiệp trên địa bàn tỉnh Phú Thọ Hết hiệu lực 31/2021/NQ-HĐND Nghị quyết số 31/2021/NQ-HĐND Quy định mức chi tổ chức Hội thi sáng tạo kỹ thuật, Cuộc thi sáng tạo Thanh thiếu niên nhi đồng trên địa bàn tỉnh Nghệ An Còn hiệu lực 98/2024/QĐ-UBND Quyết định số 98/2024/QĐ-UBND Quy định mức nộp tiền để Nhà nước bổ sung diện tích đất chuyên trồng lúa bị mất hoặc tăng hiệu quả sử dụng đất trồng lúa khi chuyển từ đất chuyên trồng lúa sang mục đích phi nông nghiệp trên địa bàn tỉnh Hết hiệu lực

Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.