Circular No. 24/2016/TT-BCT stipulates certain contents regarding shortening the time to access electricity.

Circular No. 24/2016/TT-BCT stipulates the shortening of time for customers, distribution units, and retail electricity providers to access electricity. This document amends articles related to the implementation procedures for accessing electricity and specifies the responsibilities of the People's Committee of provinces in implementing the contents related to shortening the time to access electricity.

문서 번호24/2016/TT-BCT
문서 유형Circular
발행 기관Ministry of Industry and Trade
서명자Trần Tuấn Anh — Bộ trưởng
업데이트17. 06. 2026
산업Industry and Trade
분야Energy
발행일30. 11. 2016
발효일16. 01. 2017
효력 만료일01. 05. 2026
상태Expired
✦ 스마트 요약

Circular No. 24/2016/TT-BCT stipulates the shortening of time for customers, distribution units, and retail electricity providers to access electricity. This document amends articles related to the implementation procedures for accessing electricity and specifies the responsibilities of the People's Committee of provinces in implementing the contents related to shortening the time to access electricity.

적용 범위

Electricity users, distribution units, retail electricity providers, People's Committees of provinces and centrally governed cities

핵심 사항

  • Amend articles related to the implementation procedures for accessing electricity.
  • Specify the responsibilities of the People's Committee of provinces in implementing the contents related to shortening the time to access electricity.
  • Ensure the deadline for processing procedures to agree on the location of poles/substations and construction permits for power projects.
  • Require annual reports on the results of implementing the time to access electricity.
  • Provide for the organization of implementation and the effectiveness of Circular No. 24/2016/TT-BCT.

🌐 이 문서의 사회적 영향

  • Help shorten the time for customers to access electricity.
  • Strengthen the responsibility of state agencies in managing the planning for the development of electricity.

❓ 자주 묻는 질문

When does this Circular take effect?

Circular No. 24/2016/TT-BCT takes effect from January 16, 2017.

What is the timeframe for processing procedures to agree on the location of poles/substations and construction permits for power projects?

The processing period for the procedure to agree on the location of poles/substations shall not exceed five working days for overhead medium voltage networks and ten working days for underground medium voltage networks. The processing period for the procedure to issue construction permits for power projects shall not exceed seven working days for overhead medium voltage networks and ten working days for underground medium voltage networks.

전문

MINISTRY OF INDUSTRY AND TRADE
--------

SOCIALIST REPUBLIC OF VIET NAM
Independence - Freedom - Happiness
---------------

Number: 24/2016/TT-BCT

Hanoi, November 30, 2016

CIRCULAR

REGULATIONS ON SOME CONTENTS REGARDING SHORTENING THE TIME TO ACCESS ELECTRICITY

----------------

Pursuant to Decree No. 95/2012/NĐ-CP dated November 12, 2012, of the Government, detailing the functions, tasks, powers, and organizational structure of the Ministry of Industry and Trade;

Pursuant to the Electricity Law dated December 3, 2004 and the Law Amending and Supplementing Certain Articles of the Electricity Law dated November 20, 2012; 

Based on Decree No. 137/2013/NĐ-CP dated October 21, 2013, issued by the Government, detailing the implementation of certain provisions of the Electricity Law and the Law Amending and Supplementing Certain Provisions of the Electricity Law;

Implementing Resolution No. 19-2016/NQ-CP dated April 28, 2016 of the Government on tasks and key solutions to improve the business environment and enhance national competitiveness for the two-year period 2016-2017 with a view to 2020;

At the proposal of the General Director of the Energy General Department,

The Minister of Industry and Trade issues this Circular regulating some contents regarding shortening the time to access electricity.

Article 1. Scope of Regulation and Applicability

1. This Circular regulates some contents regarding shortening the time to access electricity, including:

a) Amend and supplement certain provisions related to the procedures for accessing electricity as prescribed in Circular No. 43/2013/TT-BCT dated December 31, 2013 of the Minister of Industry and Trade stipulating the contents, procedures, and formalities for preparing, examining, approving, and adjusting the Power Development Plan (hereinafter referred to as Circular No. 43/2013/TT-BCT).

b) Prescribing the responsibilities of the People's Committee of provinces and centrally governed cities in implementing the contents regarding shortening the time to access electricity.

Article 2. This Circular applies to the following entities:

a) Customers using electricity who request connection to the distribution network;

b) Distribution companies;

c) Distribution companies and retail companies;

d) Vietnam Electricity Corporation;

đ) Relevant agencies, organizations, and individuals.

Article 2. Amend and supplement Article 25 of Circular No. 43/2013/TT-BCT

"Article 25. Procedures and formalities for adjusting the provincial power development plan not according to the cycle

1. Regarding the adjustment of the Component of the Power Development Plan for the 110 kV system:

a) The project investors or provincial People's Committees that have the need to supplement or adjust within the Component of the Power Development Plan for the 110 kV system shall organize the preparation of the plan adjustment dossier according to the content stipulated in Clause 1, Article 22 of this Circular;

b) During the process of preparing the plan adjustment, the investor shall be responsible for soliciting opinions from the Provincial Electricity Company to complete the content of the plan adjustment before submitting it to the Department of Industry and Trade for examination and reporting to the provincial People's Committee to issue a document sent to the Energy General Department for review and reporting to the Minister of Industry and Trade for approval;

c) Within five working days from the date of receipt of the dossier, the Energy General Department must issue a document requesting additional information if the planning dossier is incomplete or invalid;

d) The dossier for the plan adjustment:

- A report proposing the adjustment and supplementation of the planning component from the People's Committee of the province;

- Five copies of the adjusted planning report;

- Opinions in writing from the provincial power company, the People's Committees of districts/cities, and relevant departments and agencies.

đ) Within twenty-five working days from the date of receipt of the valid dossier, the Energy General Department shall be responsible for completing the review of the plan adjustment dossier before submitting it to the Minister of Industry and Trade for approval;

e) During the review process, the Energy General Department shall solicit written opinions from the Southern Power Corporation and the National Power Transmission Corporation (if necessary);

2. Regarding the adjustment of the Component of the Detailed Power Development Plan for the Medium and Low Voltage Grids after 110 kV Substations:

a) For medium voltage transformer stations with total capacity exceeding 2,000 kVA, the project investors who have the need to supplement or adjust within the Component of the Detailed Power Development Plan for the Medium and Low Voltage Grids after 110 kV Substations shall organize the preparation of the plan adjustment dossier according to the content stipulated in Clause 2, Article 22 of this Circular and submit it to the Department of Industry and Trade for examination and reporting to the provincial People's Committee for approval.

- The plan adjustment dossier includes: The request for plan adjustment and supplementation submitted by the investor; five copies of the Report on the Plan Adjustment Component.

- Within ten working days from the date of receipt of the valid dossier, the Department of Industry and Trade shall be responsible for completing the examination of the plan adjustment dossier before submitting it to the provincial People's Committee for approval. During the examination process, if necessary, the Department of Industry and Trade shall solicit written opinions from the Provincial Electricity Company, the district People's Committee, and relevant agencies and organizations.

b) For medium voltage transformer stations with total capacity up to 2,000 kVA, based on the capacity of the regional power grid, the Distribution Unit shall connect to the grid and report to the competent authority for planning management according to Clause 4, Article 27 of this Circular.

Article 3. Amending and supplementing Article 27 of Circular No. 43/2013/TT-BCT

"Article 27. Management and Implementation of Power Development Plans at Various Levels

1. The Energy General Department shall be responsible for:

a) Announcing the National Power Development Plan, including any adjusted plans that have been approved;

b) Organizing monitoring and inspection of the implementation of the National Power Development Plan;

c) Annually summarizing and evaluating the results, impacts, and influences of the implementation of the National Power Development Plan to report to the Minister of Industry and Trade for consideration;

d) Serving as the focal point to direct the implementation of power projects according to the approved National Power Development Plan.

2. The People's Committee of provinces and centrally governed cities shall be responsible for:

a) Announcing the Provincial Power Development Plan, including any adjusted plans that have been approved;

b) Directing the Department of Industry and Trade to organize monitoring and inspection of the implementation of the Provincial Power Development Plan in the locality;

c) Annually summarizing and evaluating the results, impacts, and influences of the implementation of the Provincial Power Development Plan in the locality to report to the Ministry of Industry and Trade;

d) Directing the implementation of power projects according to the approved Provincial Power Development Plan.

3. Project investors in the power sector shall be responsible for:

a) Implementing investment and construction of power facilities according to the approved Power Development Plan;

b) Annually reporting to the competent state agency managing the implementation of the Power Development Plan on the progress of implementing the project.

4. Before July 15 and January 15 each year, the Distribution Unit shall be responsible for submitting periodic six-monthly and annual reports to the planning management authority on the investment and construction of power facilities and the connection of customers using the distribution network with their own substations.

5. The funds for managing and implementing the Power Development Plan annually as stipulated in Point b and Point c of Clause 1 and Point b and Point c of Clause 2 of this Article shall be allocated from the state budget and implemented in accordance with the regulations of the Ministry of Finance and the Ministry of Industry and Trade."

Article 4. Connection at Medium Voltage Level

The procedures and formalities for agreement and connection at medium voltage level shall be carried out in accordance with Circular No. 39/2015/TT-BCT dated November 18, 2015 of the Minister of Industry and Trade on the distribution system.

Article 5. Responsibilities of Provincial People's Committees under Central Cities

Provincial People's Committees under Central Cities shall be responsible for ensuring:

a) The processing time for the procedure to agree on pole/substation location and power line corridor (if applicable) shall not exceed five working days for overhead medium voltage lines and ten working days for underground medium voltage lines.

b) The processing time for the procedure to grant construction permits for power projects (if applicable) shall not exceed seven working days for overhead medium voltage lines and ten working days for underground medium voltage lines.

2. Annually, the People's Committee of provinces and centrally governed cities shall be responsible for reporting to the Ministry of Industry and Trade on the results and assessment of the implementation of electricity access time.

Article 6. Implementation Organization

1. Vietnam Electricity Corporation shall be responsible for directing its subordinate units to implement this Circular.

2. The General Department of Energy shall be responsible for disseminating, guiding, and supervising the implementation of this Circular.

Article 7. Effective Date

1. This Circular shall take effect from January 16, 2017.

2. This Circular replaces Circular No. 33/2014/TT-BCT dated October 10, 2014 issued by the Minister of Industry and Trade on certain contents regarding shortening the time for electricity access.

3. During the implementation process, if there are any difficulties, organizations and individuals shall reflect them to the Ministry of Industry and Trade for consideration and resolution./.

THE MINISTER
(Signed and stamped)
Tran Tuan Anh

원본 문서(PDF)

새 탭에서 PDF 열기 ↗

관계도

↑ 근거 및 이 문서에 영향을 주는 문서
근거 23
28/2004/QH11 Nghị quyết số 28/2004/QH11 Về việc phê chuẩn "Hiệp định giữa nước Cộng hoà xã hội chủ nghĩa Việt Nam và nước Cộng hoà nhân dân Trung Hoa về phân định lãnh hải, vùng đặc quyền kinh tế và thềm lục địa của hai nước trong vịnh Bắc Bộ" 발효 중 137/2013/NĐ-CP Nghị định số 137/2013/NĐ-CP Quy định chi tiết thi hành một số điều của Luật Điện lực và Luật sửa đổi, bổ sung một số điều của Luật Điện lực 만료됨 24/2012/QH13 Nghị quyết số 24/2012/QH13 Thi hành Luật Xử lý vi phạm hành chính 발효 중 95/2012/NĐ-CP Nghị định số 95/2012/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Công Thương 만료됨 28/2019/QĐ-UBND Quyết định số 28/2019/QĐ-UBND Ban hành Quy định quy trình thực hiện cơ chế một cửa liên thông trong giải quyết các thủ tục cấp điện qua lưới điện trung áp trên địa bàn tỉnh Thanh Hoá 발효 중 60/2025/QĐ-UBND Quyết định số 60/2025/QĐ-UBND Quy định quy trình thực hiện cơ chế một cửa liên thông trong giải quyết các thủ tục cấp điện qua lưới điện trung áp trên địa bàn tỉnh Thanh Hóa 발효 중 47/2023/QĐ-UBND Quyết định số 47/2023/QĐ-UBND Bãi bỏ các quyết định của Ủy ban nhân dân tỉnh Bắc Giang 발효 중 01/2022/QĐ-UBND Quyết định số 01/2022/QĐ-UBND Sửa đổi điểm b, khoản 1 và điểm c, khoản 2 Điều 5 của Quy định một cửa liên thông giữa các cơ quan nhà nước và Công ty điện lực Trà Vinh trong giải quyết các thủ tục cấp điện qua lưới trung áp trên địa bàn tỉnh Trà Vinh được ban hành kèm theo Quyết định số 17/2019/QĐ-UBND ngày 04 tháng 9 năm 2019 của Ủy ban nhân dân tỉnh 발효 중 17/2019/QĐ-UBND Quyết định số 17/2019/QĐ-UBND Ban hành Quy định “một cửa liên thông” giữa các cơ quan nhà nước và Công ty Điện lực Trà Vinh trong giải quyết các thủ tục cấp điện qua lưới trung áp trên địa bàn tỉnh Trà Vinh 발효 중 20/2019/QĐ-UBND Quyết định số 20/2019/QĐ-UBND Ban hành Quy định về một cửa liên thông trong giải quyết các thủ tục cấp điện qua lưới trung áp trên địa bàn tỉnh Đồng Tháp 발효 중 11/2019/QĐ-UBND Quyết định số 11/2019/QĐ-UBND Ban hành Quy trình thí điểm về cơ chế phối hợp giữa các Cơ quan nhà nước và Điện lực trong giải quyết các thủ tục cấp điện qua lưới trung áp 만료됨 17/2019/QĐ-UBND Quyết định số 17/2019/QĐ-UBND Ban hành Quy định về một cửa liên thông giữa cơ quan nhà nước và ngành điện trong giải quyết các thủ tục cấp điện qua lưới điện trung áp trên địa bàn tỉnh 만료됨 24/2018/QĐ-UBND Quyết định số 24/2018/QĐ-UBND Bãi bỏ văn bản quy phạm pháp luật của Ủy ban nhân dân tỉnh Tiền Giang 발효 중 16/2018/QĐ-UBND Quyết định số 16/2018/QĐ-UBND Sửa đổi, bổ sung, bãi bỏ một số điều của Quy định một số thủ tục liên quan đến tiếp cận điện năng trên địa bàn tỉnh Bắc Giang và bãi bỏ phụ lục 1 ban hành kèm theo Quyết định số 118/2015/QĐ-UBND ngày 03/4/2015 của UBND tỉnh Bắc Giang 발효 중 19/2018/QĐ-UBND Quyết định số 19/2018/QĐ-UBND Sửa đổi, bổ sung một số điều của Quy định về hoạt động điện lực và sử dụng điện trên địa bàn tỉnh Trà Vinh ban hành kèm theo Quyết định số 23/2016/QĐ-UBND ngày 28/6/2016 của Ủy ban nhân dân tỉnh 발효 중 81/2017/QĐ-UBND Quyết định số 81 /2017/QĐ-UBND Bãi bỏ Quyết định ban hành quy định một số thủ tục liên quan đến quy trình tiếp cận điện năng đối với lưới điện trung áp trên địa bàn tỉnh An Giang 발효 중 10/2017/NQ-HĐND Nghị quyết số 10/2017/NQ-HĐND Về Quy hoạch phát triển điện lực tỉnh Ninh Thuận giai đoạn đến năm 2025, có xét đến năm 2035 (Hợp phần I: Quy hoạch phát triển hệ thống điện 110kV) 발효 중 06/2017/QĐ-UBND Quyết định số 06/2017/QĐ-UBND Ban hành Quy định về rút ngắn thời gian tiếp cận điện năng trên địa bàn tỉnh Hưng Yên 만료됨 31/2017/QĐ-UBND Quyết định số 31/2017/QĐ-UBND Ban hành Quy định về trình tự, thủ tục, thời gian tiếp cận điện năng trên địa bàn tỉnh Đồng Tháp 만료됨 08/2017/QĐ-UBND Quyết định số 08/2017/QĐ-UBND Ban hành Quy định một số thủ tục liên quan đến tiếp cận điện năng trên địa bàn tỉnh Bạc Liê 만료됨 08/2017/QĐ-UBND Quyết định số 08/2017/QĐ-UBND Điều chỉnh nội dung quy định của một số thủ tục liên quan đến quy trình tiếp cận điện năng đối với lưới điện trung áp trên địa bàn tỉnh An Giang 만료됨 53/2022/QĐ-UBND Quyết định số 53/2022/QĐ-UBND Bãi bỏ các Quyết định của Ủy ban nhân dân tỉnh Lâm Đồng ban hành thuộc lĩnh vực quản lý nhà nước của Sở Công Thương 발효 중 10/2022/QĐ-UBND Quyết định số 10/2022/QĐ-UBND Bãi bỏ Quyết định số 18/2016/QĐ-UBND ngày 27 tháng 6 năm 2016 của Ủy ban nhân dân tỉnh Thái Nguyên ban hành Quy định về trình tự, thủ tục, thời gian tiếp cận điện năng đối với lưới điện trung áp trên địa bàn tỉnh Thái Nguyên 발효 중
24/2016/TT-BCT
Circular No. 24/2016/TT-BCT stipulates certain contents regarding shortening the time to access electricity.
Expired
↓ 이 문서의 영향을 받는 문서
관련 13
24/2018/QĐ-UBND Quyết định số 24/2018/QĐ-UBND Ban hành Quy định về công tác thi đua, khen thưởng trên địa bàn tỉnh Kiên Giang 만료됨 19/2018/QĐ-UBND Quyết định số 19/2018/QĐ-UBND Sửa đổi Điều 4 Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Sở Văn hóa, Thể thao và Du lịch, ban hành kèm theo Quyết định số 42/2016/QĐ-UBND ngày 04/11/2016 của Ủy ban nhân dân tỉnh Yên Bái 만료됨 11/2019/QĐ-UBND Quyết định số 11/2019/QĐ-UBND Quy định hệ số điều chỉnh giá đất năm 2019 trên địa bàn tỉnh Hà Tĩnh 만료됨 47/2023/QĐ-UBND Quyết định số 47/2023/QĐ-UBND Ban hành Điều lệ tổ chức và hoạt động của Quỹ Bảo lãnh tín dụng cho doanh nghiệp nhỏ và vừa tỉnh Vĩnh Phúc 발효 중 10/2022/QĐ-UBND Quyết định số 10/2022/QĐ-UBND Ban hành Quy chế về tổ chức và hoạt động của Phòng Văn hóa và Thông tin thuộc Ủy ban nhân dân huyện Nhà Bè 만료됨 2017/QĐ-UBND Quyết định 2017/QĐ-UBND năm 2013 thành lập Ban Chỉ đạo về đẩy mạnh cải cách chế độ công vụ, công chức trên địa bàn Thành phố Hồ Chí Minh 발효 중 10/2017/NQ-HĐND Nghị quyết số 10/2017/NQ-HĐND Về việc bổ sung Điều 5 Quy định về phân cấp nguồn thu, nhiệm vụ chi và tỷ lệ phần trăm (%) phân chia các khoản thu giữa các cấp ngân sách tỉnh Nghệ An năm 2017, ổn định đến năm 2020 ban hành kèm theo Nghị quyết số 31/2016/NQ-HĐND ngày 16/12/2016 của Hội đồng nhân dân tỉnh 만료됨 31/2017/QĐ-UBND Quyết định số 31/2017/QĐ-UBND Ban hành Quy định một số chính sách hỗ trợ, ưu đãi phát triển Kinh tế tập thể trên địa bàn tỉnh Bình Dương giai đoạn 2018-2020 발효 중 20/2019/QĐ-UBND Quyết định số 20/2019/QĐ-UBND Bãi bỏ các Quyết định, Chỉ thị do Ủy ban nhân dân tỉnh Kiên Giang ban hành không còn phù hợp với quy định của pháp luật hiện hành 발효 중 17/2019/QĐ-UBND Quyết định số 17/2019/QĐ-UBND Quy định chế độ báo cáo định kỳ thực hiện trên địa bàn tỉnh Yên Bái 발효 중 60/2025/QĐ-UBND Quyết định số 60/2025/QĐ-UBND Ban hành Quy định về cơ cấu tổ chức quản lý, bảo vệ đê điều và phân cấp công tác quản lý duy tu, bảo dưỡng đê điều trên địa bàn tỉnh Quảng Ngãi 발효 중 53/2022/QĐ-UBND Quyết định số 53/2022/QĐ-UBND Ban hành Quy định vị trí, chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Ban Tôn giáo tỉnh Lào Cai 만료됨 01/2022/QĐ-UBND Quyết định số 01/2022/QĐ-UBND Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Sở Khoa học và công nghệ tỉnh Nghệ An 만료됨

문서를 클릭하면 열립니다. 빨간 테두리=효력을 변경하는 관계.