Circular No. 08/2006/TT-BTNMT guiding strategic environmental assessment, environmental impact assessment, and environmental protection commitment

Circular No. 08/2006/TT-BTNMT provides detailed guidance on strategic environmental assessment, environmental impact assessment, and environmental protection commitment pursuant to the Environmental Protection Law and Decree No. 80/2006/NĐ-CP. This Circular applies to state agencies, organizations, and individuals both within and outside Vietnam involved in environmental assessment activities.

Số hiệu08/2006/TT-BTNMT
Loại văn bảnCircular
Cơ quan ban hànhMinistry of Agriculture and Environment
Người kýMai Ái Trực — Bộ trưởng
Cập nhật29/06/2026
NgànhNatural Resources and Environment
Lĩnh vựcUncategorized
Ngày ban hành08/09/2006
Ngày áp dụng10/10/2006
Ngày hết hiệu lực07/01/2009
Tình trạngExpired
✦ Tóm lược thông minh

Circular No. 08/2006/TT-BTNMT provides detailed guidance on strategic environmental assessment, environmental impact assessment, and environmental protection commitment pursuant to the Environmental Protection Law and Decree No. 80/2006/NĐ-CP. This Circular applies to state agencies, organizations, and individuals both within and outside Vietnam involved in environmental assessment activities.

Đối tượng áp dụng

State agencies, organizations, and individuals within Vietnam; foreign organizations and individuals (collectively referred to as organizations and individuals) engaged in strategic environmental assessment, environmental impact assessment, and environmental protection commitment.

Các điểm cốt lõi

  • The agency assigned the task of preparing the project falls under the category required to prepare a strategic environmental assessment report (Article 1.1).
  • The project proponent submits the application for review of the strategic environmental assessment report and the specific number and sample of documents (Article 2.2).
  • After receiving all valid documents, the agency organizing the review must complete the review of the strategic environmental assessment report within the prescribed time limit (Article 3.3).
  • The project proponent organizes self-assessment or hires a consulting service organization to conduct the environmental impact assessment work and prepare the environmental impact assessment report of the project (Article 1.2).
  • After receiving all valid documents, the agency organizing the review must complete the review of the environmental impact assessment report through a committee within the prescribed time limit (Article 4.2).

🌐 Tác động xã hội từ văn bản này

  • Positive impacts: Helps raise awareness about environmental protection, ensuring the comprehensiveness and scientific nature of environmental impact assessment reports.
  • Negative impacts: Burden of work and costs for the project proponent due to compliance with complex regulations; prolonged implementation time.

❓ Câu hỏi thường gặp

What documents does the project proponent need to prepare when submitting an application for review of the strategic environmental assessment report?

The project proponent needs to prepare: 1 request for review, 7 copies of the environmental assessment report, and 1 draft strategy (plan, program) according to the model specified in Appendix 2 and 3 attached to this Circular.

What is the deadline for reviewing the environmental impact assessment report?

The agency organizing the review must complete the review within the time limit stipulated in Clause 1 and Clause 2 of Article 12 of Decree No. 80/2006/NĐ-CP, usually 30 working days from the date of receipt of all valid documents.

What does the project proponent need to prepare to establish an environmental protection commitment?

The project proponent needs to prepare: 1 request for registration confirmation, 3 copies of the environmental protection commitment, and 1 draft feasibility study report or investment justification report of the project according to the model specified in Appendix 24 and 25 attached to this Circular.

Where should the project proponent submit the registration application for the environmental protection commitment?

The project proponent submits the application for registration of the environmental protection commitment to the People's Committee of the district where the project is located or the People's Committee of the commune authorized to register and issue a confirmation certificate.

What is the deadline for implementing the contents in the environmental impact assessment report?

The project proponent must implement the contents of the report and comply with the requirements of the decision approving the environmental impact assessment report within the time limit stipulated in the approval decision, generally not exceeding 30 working days from the date of receipt of the decision.

Toàn văn

 

CIRCULAR

Guidelines on Strategic Environmental Assessment,

Environmental Impact Assessment, and Environmental Commitment

_____________________________

 

The Prime Minister issues this Decision amending and supplementing certain provisions of the Regulation on Response Activities to Oil Spill Incidents issued together with Decision No. 02/2013/QĐ-TTg dated January 14, 2013 of the Prime Minister.

Pursuant to the Government Decree No. 80/2006/NĐ-CP dated August 9, 2006 detailing and guiding the implementation of certain provisions of the Environmental Protection Law;

Pursuant to Decree No. 91/2002/NĐ-CP dated November 11, 2002 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Natural Resources and Environment;

The Ministry of Natural Resources and Environment provides detailed guidelines for implementing certain aspects of strategic environmental assessment, environmental impact assessment, and environmental commitment as follows:

This technical regulation sets out technical requirements, testing methods, sampling procedures; management requirements; responsibilities of organizations and individuals producing, trading, and importing cigarettes.

Thông tư này quy định chi tiết khoản 4 Điều 38 Luật Thủy sản số 18/2017/QH14 đã được sửa đổi, bổ sung tại điểm c khoản 21 Điều 14 Luật số 146/2025/QH15.

1.1. These Circulars provide detailed guidelines for implementing certain aspects of strategic environmental assessment, environmental impact assessment, and environmental commitment as prescribed in the Law on Environmental Protection dated November 29, 2005 (hereinafter referred to as the Law on Environmental Protection) and Decree No. 80/2006/NĐ-CP dated August 9, 2006 of the Government detailing and guiding the implementation of certain provisions of the Law on Environmental Protection (hereinafter referred to as Decree No. 80/2006/NĐ-CP), including:

a) Preparing and reviewing strategic environmental assessment reports;

b) Preparing, reviewing, and approving environmental impact assessment reports and supplementary environmental impact assessment reports; implementing and monitoring compliance with environmental protection contents in environmental impact assessment reports, supplementary environmental impact assessment reports, and requirements of approval decisions;

c) Preparing, registering, and confirming environmental protection commitments.

1.2. These Circulars do not apply to existing facilities (also known as operating facilities), including those that did not previously comply with regulations on preparing, reviewing, and approving environmental impact assessment reports.

1.3. Strategies, plans, programs, and projects related to national security, defense, and state secrets are guided by other documents.

Thông tư này áp dụng đối với tổ chức, cá nhân có liên quan đến hoạt động kinh doanh đối tượng thủy sản nuôi chủ lực trên lãnh thổ Việt Nam.

These Circulars apply to state agencies, organizations, and individuals within Vietnam; foreign organizations and individuals (hereinafter collectively referred to as organizations and individuals) involved in activities related to the contents specified in Point 1.1, Section 1, Part I of these Circulars.

3. Application of environmental standards and technical regulations

When preparing an environmental impact assessment report or an environmental protection commitment for a project, Vietnamese mandatory environmental standards and technical regulations must be applied; international treaties to which Vietnam is a member also require the application of such standards and technical regulations.

II. PREPARATION AND REVIEW OF STRATEGIC ENVIRONMENTAL ASSESSMENT REPORTS

1. Preparation of strategic environmental assessment reports

1.1. The agency assigned the task of preparing a project subject to the preparation of a strategic environmental assessment report as stipulated in Article 14 of the Law on Environmental Protection (hereinafter referred to as the project proponent) shall establish a working group for strategic environmental assessment comprising environmental experts and relevant scientists with appropriate qualifications and expertise corresponding to the content and nature of the project to conduct strategic environmental assessment work and prepare the strategic environmental assessment report for the strategy (plan, program).

1.2. The strategic environmental assessment report must be structured and meet the content requirements as specified in Appendix 1 attached to these Circulars.

2. Submission of documents for review of strategic environmental assessment reports

2.1. The project proponent submits documents for review of strategic environmental assessment reports to the agency responsible for organizing the review as stipulated in Clause 7, Article 17 of the Law on Environmental Protection.

2.2. The quantity and format of the documents for review are as follows:

a) One document requesting review of the strategic environmental assessment report according to the model specified in Appendix 2 attached to these Circulars;

b) Seven copies of the strategic environmental assessment report of the project bound according to the model specified in Appendix 3 attached to these Circulars, signed with the name, position, and stamped on the cover page of each report;

c) One draft of the strategy (plan, program).

2.3. In cases where the number of members of the review board exceeds seven, or in other necessary cases due to the requirements of the review process, the project proponent shall provide additional copies of the strategic environmental assessment report as required by the agency organizing the review.

3. Review of strategic environmental assessment reports

3.1. After receiving complete and valid documents for review, the agency organizing the review shall establish a review board; the number of board members shall be determined based on the provisions of Clauses 2, 3, and 4, Article 17 of the Law on Environmental Protection, the nature, scale of the project, and environmental requirements, but must ensure at least seven members.

3.2. Within the time limit stipulated in Clause 1 and Clause 2, Article 12 of Decree No. 80/2006/NĐ-CP, the agency organizing the review must complete the review of the strategic environmental assessment report.

3.3. The organization and operation of the review board shall be carried out in accordance with the Regulation on the Organization and Operation of the Strategic Environmental Assessment Report Review Board and the Environmental Impact Assessment Report Review Board issued together with Decision No. 13/2006/QĐ-BTNMT dated September 8, 2006 of the Minister of Natural Resources and Environment.

3.4. The submission of the review results report shall be carried out in accordance with the provisions of Clause 3 and Clause 4, Article 10 of Decree No. 80/2006/NĐ-CP.

III. PREPARATION, REVIEW, AND APPROVAL OF ENVIRONMENTAL IMPACT ASSESSMENT REPORTS; IMPLEMENTATION, MONITORING, AND CONFIRMATION OF COMPLIANCE WITH CONTENTS IN ENVIRONMENTAL IMPACT ASSESSMENT REPORTS

1. Preparation of environmental impact assessment reports

1.1. Organizations and individuals who are project investors subject to the preparation of environmental impact assessment reports as stipulated in Appendices I and II issued together with Decree No. 80/2006/NĐ-CP (hereinafter referred to as the project proponent) shall organize or hire consulting service organizations meeting the conditions stipulated in Article 8 of Decree No. 80/2006/NĐ-CP to conduct environmental impact assessment work and prepare the environmental impact assessment report for the project.

1.2. The environmental impact assessment report must be structured and meet the content requirements as specified in Appendix 4 attached to these Circulars.

2. Consultation with the community's opinions

2.1. The project proponent shall send a document to the People's Committee and the People's Council for United Front Work at the commune level to notify the basic contents of the project, the negative environmental impacts of the project, the measures to mitigate such negative environmental impacts that will be applied, and request written comments.

2.2. In case the People's Committee or the People's Council for United Front Work at the commune level requests a dialogue, the project proponent must cooperate in its implementation. The results of the dialogue shall be recorded in minutes, reflecting fully all discussed opinions, the project proponent’s acceptance or non-acceptance of these opinions; the minutes shall bear signatures (with full name and position) of the chairperson of the dialogue and the project proponent or their representative, accompanied by a list of attendees.

2.3. The opinions supporting or opposing the project from the People's Committee, the People's Council for United Front Work at the commune level, and the representatives attending the dialogue must be reflected in the content of the environmental impact assessment report.

2.4. Written comments from the People's Committee, the People's Council for United Front Work at the commune level, the minutes of the dialogue, and other community consultation documents (if any) must be copied and attached as appendices to the environmental impact assessment report of the project.

3. Submitting the dossier for the review of the environmental impact assessment report

3.1. The project proponent shall submit the dossier for the review of the environmental impact assessment report to the agency organizing the review of the environmental impact assessment report as stipulated in Clause 7, Article 21 of the Environmental Protection Law.

3.2. The quantity and format of the dossier for the review are specified as follows:

a) One (1) document from the project proponent requesting the review and approval of the environmental impact assessment report according to the model attached as Appendix 5 to this Circular;

b) Seven (7) copies of the environmental impact assessment report of the project bound into volumes according to the model prescribed in Appendix 6 to this Circular, signed with the full name and position of the project proponent and stamped on the back cover page of each report;

c) One (1) draft feasibility study report or investment report of the project.

3.3. In cases where the number of members of the Review Board needs to exceed seven (7) people, or in other necessary cases due to the requirements of the review work, the project proponent must provide additional copies of the environmental impact assessment report as required by the agency organizing the review.

4. Reviewing the environmental impact assessment report through a Review Board

4.1. After receiving a valid dossier meeting the requirements for review, the agency organizing the review shall establish a Review Board; the number of Review Board members shall be determined based on the provisions of Clauses 2, 3, and 4, Article 21 of the Environmental Protection Law, the nature, scale of the project, and environmental requirements, but must ensure at least seven (7) members.

4.2. The organization and operation of the Review Board shall be carried out in accordance with the Regulation on the Organization and Operation of the Strategic Environmental Assessment Review Board and the Environmental Impact Assessment Report Review Board issued together with Decision No. 13/2006/QĐ-BTNMT dated September 8, 2006, of the Minister of Natural Resources and Environment.

5. Reviewing the environmental impact assessment report through a service review organization

5.1. The organization selected to perform the service of reviewing the environmental impact assessment report must meet the following conditions:

a) Having a team of staff with appropriate qualifications and expertise in line with the requirements for reviewing the environmental impact assessment report of the project;

b) Having sufficient equipment, devices, technical facilities, laboratories with quality and reliability needed for measurement, sampling, processing, and analysis of environmental samples and related samples suitable for the nature of the project and the location of the project implementation; in cases where requirements are not met, contracts must be signed to hire organizations or individuals meeting the requirements set forth;

c) Meeting other conditions as prescribed by relevant laws.

5.2. The activities of the service review organization shall be carried out in accordance with the regulations of the Ministry of Natural Resources and Environment.

6. Completing the environmental impact assessment report

6.1. Within no more than three (3) working days from the date of receipt of the results of the Review Board or the service review organization, the agency organizing the review shall issue a notification to the project proponent regarding the review results and the requirements for completing or redrafting the environmental impact assessment report.

6.2. In cases where the environmental impact assessment report needs to be further completed, the project proponent shall proceed to complete it, sign at the bottom left corner of each page, and reproduce it in the following quantities to be sent to the agency organizing the review along with a detailed explanation document about the completion for consideration and approval:

a) For environmental impact assessment reports within the approval authority of the Ministry of Natural Resources and Environment, the number of reports must be sufficient to be sent to the following addresses: Ministry of Natural Resources and Environment (four copies, including one copy recorded on a CD); Provincial People's Committee within the project area (one copy); the managing ministry or sector of the project (one copy). In cases where the project covers areas of two provinces or centrally-administered cities or more, additional copies of the environmental impact assessment report equal to the number of additional provinces shall be sent;

b) For environmental impact assessment reports within the approval authority of ministries, ministerial-level agencies, or government agencies, the number of reports must be sufficient to be sent to the following addresses: Managing ministry or sector of the project (three copies, including one copy recorded on a CD); Provincial People's Committee within the project area (one copy); Ministry of Natural Resources and Environment (one copy);

c) For environmental impact assessment reports within the approval authority of the provincial People's Committee, the number of reports must be sufficient to be sent to the provincial People's Committee where the project is located, consisting of three copies, including one copy recorded on a CD.

7. Re-reviewing the environmental impact assessment report

7.1. In cases where the environmental impact assessment report is not approved by the Review Board or the service review organization, re-reviewing shall be conducted upon the project proponent's request.

7.2. The re-evaluation of the environmental impact assessment report shall be conducted by the Evaluation Council or the evaluation service organization that carried out the initial evaluation; if necessary, the competent authority approving the environmental impact assessment report may establish a new Evaluation Council or select another evaluation service organization to conduct the re-evaluation.

8. Approval of the environmental impact assessment report

8.1. The decision approving the environmental impact assessment report shall be prepared according to the model prescribed in Appendix 7 attached hereto.

8.2. In cases where there is a possibility of adverse environmental impacts not fully assessed in the environmental impact assessment report due to objective reasons such as lack of detailed project data, current status and carrying capacity of the surrounding environment data, insufficiently reliable risk assessment, and other force majeure reasons up to the time of approval of the environmental impact assessment report, the competent authority approving the report must note this in the section on accompanying requirements of the approval decision.

9. Confirmation and submission of the approved environmental impact assessment report

9.1 After the environmental impact assessment report has been approved, the competent authority approving the report shall confirm on the back cover page of each copy of the environmental impact assessment report according to the model prescribed in Appendix 8 attached hereto.

9.2. The competent authority approving the report shall be responsible for sending the confirmed environmental impact assessment report along with the decision approving the environmental impact assessment report to the project proponent and other relevant agencies as stipulated in point 6.2 item 6 Part III of this Circular; send the original and copies of the decision approving the environmental impact assessment report in accordance with Clause 1 and Clause 2 Article 15 of Decree No. 80/2006/NĐ-CP.

10. Preparation, evaluation, and approval of supplementary environmental impact assessment reports

10.1. Project proponents falling under the provisions of Clause 1 Article 13 of Decree No. 80/2006/NĐ-CP shall be responsible for preparing supplementary environmental impact assessment reports to submit to the authority that approved the original environmental impact assessment report of the project for evaluation and approval before implementation.

10.2. Supplementary environmental impact assessment reports shall be structured and meet the content requirements prescribed in Appendix 9 attached hereto.

10.3. The number and format of the application dossier for the evaluation and approval of supplementary environmental impact assessment reports are specified as follows:

a) One (1) request for evaluation and approval of supplementary environmental impact assessment reports according to the model prescribed in Appendix 10 attached hereto;

b) Five (5) copies of the supplementary environmental impact assessment report bound into volumes according to the model prescribed in Appendix 11 attached hereto, signed with the name and position of the project proponent and stamped on the back cover page. In case additional copies are required for the evaluation process, the project proponent must provide them according to the requirements of the evaluating authority;

c) One (1) copy of the previously approved environmental impact assessment report;

d) One (1) certified copy of the decision approving the previously submitted environmental impact assessment report;

đ) One (1) explanation of the adjusted contents of the project.

10.4. The evaluation of supplementary environmental impact assessment reports shall be conducted through the form of written opinions from experts and managers with appropriate expertise and qualifications; if necessary, additional opinions from local state management authorities on environmental protection where the project is located may also be sought. Comments and evaluations shall be expressed according to the model prescribed in Appendix 12 attached hereto.

10.5. If the dossier does not comply with the requirements for evaluation, within no more than five (5) working days from the date of receipt of the dossier, the organization conducting the evaluation must issue a written notice to the project proponent detailing the reasons for supplementation and completion.

10.6. The decision approving the supplementary environmental impact assessment report shall be prepared according to the model prescribed in Appendix 13 attached hereto and shall accompany the previous decision approving the environmental impact assessment report. In case of non-approval, the competent authority approving the report must respond in writing to the project proponent and specify the reasons.

10.7. The approved supplementary environmental impact assessment report must be confirmed on the back cover page according to the model prescribed in Appendix 8 attached hereto.

10.8. The number of copies of the supplementary environmental impact assessment report that have been approved and confirmed must be sufficient to be sent together with the original of the supplementary approval decision to the addresses that received the previous decision approving the environmental impact assessment report.

11. Content and form of reports and notifications by the project proponent regarding the implementation of contents in the environmental impact assessment report

11.1 The report to the People's Committee of the district where the project is implemented on the content of the decision approving the environmental impact assessment report of the project shall be prepared according to the model prescribed in Appendix 14 attached hereto.

11.2. A summary of the approved environmental impact assessment report shall be prepared according to the model prescribed in Appendix 15 attached hereto.

11.3. The report on the plan to construct environmental treatment facilities and environmental protection facilities shall be prepared according to the model prescribed in Appendix 16 attached hereto.

11.4. The report on the trial operation plan for environmental treatment and protection facilities shall be prepared according to the model prescribed in Appendix 17 attached hereto.

11.5. The report on the implementation of the contents of the report and the requirements of the decision approving the environmental impact assessment report of the project shall be prepared according to the model prescribed in Appendix 18 attached hereto.

11.6. The request for confirmation of the implementation of the contents of the report and the requirements of the decision approving the environmental impact assessment report of the project shall be prepared according to the model prescribed in Appendix 19 attached hereto.

12. Inspection of the implementation of contents in the environmental impact assessment report, supplementary environmental impact assessment report.

12.1. The competent authority approving the environmental impact assessment report shall send representatives to cooperate with the local state management agency for environmental protection to inspect the implementation of the approved environmental impact assessment report in accordance with points c and d, Clause 3, Article 15 of Decree No. 80/2006/NĐ-CP. If necessary, the competent authority approving the environmental impact assessment report may establish an inspection team. The decision to establish the inspection team shall be made according to the form prescribed in Appendix 20 attached hereto.

12.2. The activities of inspection and examination to confirm the implementation of the contents of the report and the requirements of the decision approving the environmental impact assessment report of the project in accordance with Clause 3, Article 16 of Decree No. 80/2006/NĐ-CP include:

a) Studying and examining the application for confirmation submitted by the project proponent;

b) Conducting an on-site inspection of the project location.

12.3. The inspection results shall be recorded in a record according to the form prescribed in Appendix 21 attached hereto and must be signed by the representative of the responsible inspection agency, the project proponent, and the representative of the local state management agency for environmental protection.

13. Confirmation of the implementation of the contents of the report and the requirements of the decision approving the environmental impact assessment report.

13.1. The certificate confirming that the project has implemented the contents of the report and the requirements of the decision approving the environmental impact assessment report shall be issued according to the form prescribed in Appendix 22 attached hereto. In cases where the conditions for confirmation have not been met, the competent authority responsible for confirmation shall notify the project proponent of the reasons.

13.2. The certificate shall be attached to the decision approving the environmental impact assessment report of the project for easy inspection and monitoring.

14. Technical appraisal of environmental treatment works and protection works.

14.1. The technical appraisal of environmental treatment works and protection works shall be carried out in accordance with the laws on investment and construction.

14.2. Organizations that have designed and installed environmental treatment works and protection works of the project shall not conduct the technical appraisal of such works or components.

IV. PREPARATION, REGISTRATION, AND CONFIRMATION OF ENVIRONMENTAL PROTECTION COMMITMENTS

1. Preparation of environmental protection commitments.

1.1. Project proponents who are required to prepare environmental protection commitments under Article 24 of the Law on Environmental Protection (hereinafter referred to as the project proponent) shall be responsible for preparing the environmental protection commitment.

1.2. The structure and content requirements of the environmental protection commitment shall be implemented in accordance with the provisions set forth in Appendix 23 attached hereto.

2. Registration of environmental protection commitments.

2.1. The project proponent shall be responsible for submitting the registration application for the environmental protection commitment to the People's Committee of the district where the project is located or the People's Committee of the commune authorized to register and issue the confirmation certificate.

2.2. In cases where the project is located within the jurisdiction of two or more districts, towns, cities under provinces, the project proponent shall choose the People's Committee of one district, town, city under province to submit the registration application for the environmental protection commitment.

2.3. The number and format of the registration application for the environmental protection commitment are as follows:

a) One application for registration confirmation of the environmental protection commitment according to the form prescribed in Appendix 24 attached hereto;

b) Three copies of the environmental protection commitment according to the form prescribed in Appendix 25 attached hereto, signed by the name and position of the project proponent and stamped on the back cover of each copy; if the commune People's Committee is authorized to confirm, an additional copy of the environmental protection commitment shall be sent (for projects located within the jurisdiction of one district); in cases where the project is located within the jurisdiction of two or more districts, additional copies of the environmental protection commitment equal to the number of additional districts shall be sent.

c) One draft feasibility study report or investment justification report of the project.

3. Confirmation of registration of environmental protection commitments.

3.1. In cases where the application is valid, the People's Committee of the district or the commune authorized to register must complete the issuance of the confirmation certificate for the registration of the environmental protection commitment for the project proponent according to the form prescribed in Appendix 26 attached hereto.

3.2. The competent authority issuing the confirmation certificate for registration must confirm on the back cover of each registered environmental protection commitment according to the form prescribed in Appendix 8 attached hereto.

4. Submission of confirmed environmental protection commitments.

4.1. In cases where registration and confirmation are conducted at the district level, the People's Committee of the district shall send the confirmed application to the project proponent one copy of the environmental protection commitment along with the confirmation certificate for implementation.

In cases where the project is located within the jurisdiction of two or more districts, the People's Committee of the district where the environmental protection commitment is confirmed shall be responsible for sending one copy of the environmental protection commitment along with the confirmation certificate to the People's Committee of the related district.

4.2. In cases where registration and confirmation are conducted at the commune level, the People's Committee of the commune shall send the confirmed application to the following addresses:

a) The project proponent one copy of the environmental protection commitment along with the confirmation certificate for implementation;

b) The People's Committee of the district one copy of the environmental protection commitment along with the confirmation certificate.

5. Delegation of authority to confirm registration of environmental protection commitments.

5.1. The People's Committee of the district shall delegate the authority to confirm registration of environmental protection commitments to the People's Committee of the commune in writing according to the form prescribed in Appendix 27 attached hereto.

5.2. The procedures, formalities, and deadlines for registration and confirmation at the commune level shall be carried out in accordance with the provisions of Sections 2, 3, and 4 of Part IV of this Circular.

5.3. The People's Committee of the district shall not delegate the authority to confirm registration of environmental protection commitments to the People's Committee of the commune in cases where the project is located within the jurisdiction of two or more districts, towns, cities under provinces.

V. IMPLEMENTATION PROVISIONS

1. Ministries, ministerial-level agencies, government agencies, and People's Committees at all levels shall organize the implementation of this Circular.

2. This Circular shall take effect fifteen days from the date of publication in the Official Gazette and shall replace Circular No. 490/1998/TT-BKHCNMT dated April 29, 1998 of the Ministry of Science, Technology and Environment guiding the preparation and examination of environmental impact assessment reports for investment projects.

3. Any difficulties encountered during implementation shall be promptly reported to the Ministry of Natural Resources and Environment for consideration and resolution./.

Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Tải văn bản

Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 23
52/2005/QH11 Nghị quyết số 52/2005/QH11 Về việc phê chuẩn Hiệp ước giữa nước Cộng hòa xã hội chủ nghĩa Việt Nam và Vương quốc Campuchia bổ sung Hiệp ước hoạch định biên giới quốc gia năm 1985 Còn hiệu lực 80/2006/NĐ-CP Nghị định số 80/2006/NĐ-CP Về việc quy định chi tiết và hướng dẫn thi hành một số điều của Luật Bảo vệ môi trường Hết hiệu lực 91/2002/NĐ-CP Nghị định số 91/2002/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Tài nguyên và Môi trường. Hết hiệu lực 856/2007/QĐ-UBND Quyết định số 856/2007/QĐ-UBND Về việc ủy quyền tổ chức thẩm định và phê duyệt báo cáo đánh giá tác động môi trường Còn hiệu lực 3485/2007/QĐ-UBND Quyết định số 3485/2007/QĐ-UBND Quy định một số điểm cụ thể về bảo vệ môi trường và kiểm soát ô nhiễm đối với các cơ sở sản xuất, kinh doanh, dịch vụ và khu sản xuất, kinh doanh, dịch vụ tập trung trên địa bàn tỉnh Phú Thọ. Còn hiệu lực 3333/QĐ-UBND Quyết định số 3333/QĐ-UBND V/v uỷ quyền xác nhận các tập Báo cáo đánh giá tác động môi trường, Báo cáo đánh giá tác động môi trường bổ sung sau khi Uỷ ban nhân dân tỉnh ký quyết định phê duyệt Còn hiệu lực 618/2007/QĐ-UBND Quyết định số 618/2007/QĐ-UBND Về việc ban hành quy định tạm thời về liên thông giải quyết hồ sơ, thủ tục hành chính đối với các nhà đầu tư đến đầu tư sản xuất, kinh doanh trên địa bàn tỉnh Quảng Ninh Hết hiệu lực 55/2007/QĐ-UBND Quyết định số 55/2007/QĐ-UBND Về việc ban hành mức thu, mức trích, cơ quan thuvà đối tượng miễn giảm phí, lệ phí thuộc lĩnh vực tài nguyên và môi trường trên địa bàn tỉnh Đồng Nai Hết hiệu lực 29/2006/CT-UBND Chỉ thị số 29/2006/CT-UBND Về việc tăng cường công tác quản lý nhà nước về bảo vệ môi trường Hết hiệu lực 46/2007/QĐ-UBND Quyết định số 46/2007/QĐ-UBND Ban hành quy định về việc thu phí thẩm định báo cáo đánh giá tác động môi trường trên địa bàn tỉnh Tiền Giang Hết hiệu lực 133/2007/NQ-HĐND Nghị quyết số 133/2007/NQ-HĐND Quy định thu phí thẩm định báo cáo đánh giá tác động môi trường trên địa bàn tỉnh Tiền Giang Hết hiệu lực 06/2007/QĐ-UBND Quyết định số 06/2007/QĐ-UBND V/v quy định mức thu, quản lý và sử dụng phí thẩm định báo cáo đánh giá tác động môi trường Hết hiệu lực 40/2007/QĐ-UBND Quyết định số 40/2007/QĐ-UBND Về ban hành Quy định về bảo vệ môi trường trên địa bàn tỉnh Quảng Nam Hết hiệu lực 68/2008/QĐ-UBND Quyết định số 68/2008/QĐ-UBND Về việc ban hành Quy định bảo vệ môi trường tỉnh Bình Dương Hết hiệu lực 66/2008/QĐ-UBND Quyết định số 66/2008/QĐ-UBND Quy định chế độ thu, quản lý và sử dụng Phí thẩm định báo cáo đánh giá tác động môi trường trên địa bàn tỉnh Bình Thuận Hết hiệu lực 1809/QĐ-UBND Quyết định số 1809/QĐ-UBND Về việc uỷ quyền cho Giám đốc Sở Tài nguyên và Môi trường xác nhận thực hiện các nội dung của báo cáo đánh giá tác động môi trường của dự án được cấp có thẩm quyền phê duyệt Còn hiệu lực 03/2008/QĐ-UBND Quyết định số 03/2008/QĐ-UBND V/v Ban hành Quy định bảo vệ môi trường trên địa bàn tỉnh Hà Nam Hết hiệu lực 17/2007/QĐ.UBND Quyết định số 17/2007/QĐ.UBND Ban hành quy định tạm thời về bảo vệ môi trường trong chăn nuôi gia súc, gia cầm Hết hiệu lực 2386/QĐ.UBND Quyết định số 2386/QĐ.UBND Phê duyệt kế hoạch triển khai công tác đánh giá môi trường chiến lược, đánh giá tác động môi trường và cam kết bảo vệ môi trường Còn hiệu lực 1281/QĐ.UBND Quyết định số 1281/QĐ.UBND Về việc uỷ quyền cho Giám đốc Sở Tài nguyên và Môi trường quyết định phê duyệt báo cáo công tác bảo vệ môi trường Còn hiệu lực 3333/QĐ-UBND Quyết định số 3333 /QĐ-UBND V/v uỷ quyền xác nhận các tập Báo cáo đánh giá tác động môi trường, Báo cáo đánh giá tác động môi trường bổ sung sau khi Uỷ ban nhân dân tỉnh ký quyết định phê duyệt Còn hiệu lực 27/2007/QĐ-UBND Quyết định số 27/2007/QĐ-UBND Về việc ban hành quy định quản lý nhà nước về đánh giá tác động môi trường trên địa bàn tỉnh An Giang Còn hiệu lực 18/2007/QĐ-UBND Quyết định số 18/2007/QĐ-UBND v/v Quy chế Bảo vệ môi trường trên địa bàn tỉnh Điện Biên do Ủy ban nhân dân tỉnh Điện Biên ban hành Hết hiệu lực
Được dẫn chiếu bởi 16
13/2006/QĐ-BTNMT Quyết định số 13/2006/QĐ-BTNMT Ban hành Quy chế về tổ chức và hoạt động của Hội đồng thẩm định báo cáo đánh giá môi trường chiến lược, Hội đồng thẩm định báo cáo đánh giá tác động môi trường Hết hiệu lực 19/2007/QĐ-UBND Quyết định số 19/2007/QĐ-UBND Về việc ban hành Đề án kiện toàn, củng cố tổ chức, bộ máy, biên chế của Trung tâm trợ giúp pháp lý nhà nước tỉnh Quảng Trị Hết hiệu lực 883/2008/QĐ-BKH Quyết định số 883/2008/QĐ-BKH Về việc ban hành kế hoạch hành động cải thiện tình hình thực hiện các chương trình, dự án ODA thời kỳ 2008 - 2009 Còn hiệu lực 22/2007/QĐ-UBND Quyết định số 22/2007/QĐ-UBND Về việc tăng mức phụ cấp cho nhân viên y tế thôn Hết hiệu lực 12/2009/QĐ-UBND Quyết định số 12/2009/QĐ-UBND Về việc Ban hành tiêu chuẩn Trưởng phòng, Phó trưởng phòng và chức vụ tương đương cơ quan chuyên môn thuộc UBND huyện, thị xã Hết hiệu lực 19/2007/QĐ-BTNMT Quyết định số 19/2007/QĐ-BTNMT Về việc ban hành quy định về điều kiện và hoạt động dịch vụ thẩm định báo cáo đánh giá tác động môi trường Còn hiệu lực 55/2008/QĐ-UBND Quyết định số 55/2008/QĐ-UBND Về việc bổ sung và điều chỉnh kế hoạch năm 2008 chương trình mục tiêu quốc gia và các chương trình đề án của tỉnh Hết hiệu lực 23/2007/QĐ-UBND Quyết định số 23/2007/QĐ-UBND V/v Ban hành Kế hoạch hành động Vì sự tiến bộ phụ nữ Quảng Trị, đến năm 2010 Hết hiệu lực 52/2008/QĐ-BCT Quyết định số 52/2008/QĐ-BCT Ban hành Quy chế tạm thời về bảo vệ môi trường ngành công thương Hết hiệu lực 22/2009/QĐ-UBND Quyết định số 22/2009/QĐ-UBND Về việc ban hành quy định về khai thác, sử dụng tài nguyên nước, xả nước thải vào nguồn nước quy mô nhỏ trên địa bàn tỉnh Đăk Nông Hết hiệu lực 22/2009/QĐ-UBND Quyết định số 22/2009/QĐ-UBND Ban hành quy định trình tự, thủ tục triển khai dự án đầu tư phát triển du lịch sinh thái tại các khu rừng đặc dụng, rừng phòng hộ và rừng sản xuất trên địa bàn tỉnh Bà Rịa - Vũng Tàu Hết hiệu lực 10966/BCT-TTTN Thông tư số 10966/ BCT-TTTN hướng dẫn thực hiện TT số 10/2008/TT-BCT Còn hiệu lực 23/2007/QĐ-UBND Quyết định số 23/2007/QĐ-UBND Về việc ban hành Quy định về trình tự, thủ tục triển khai dự án đầu tư bên ngoài các khu công nghiệp, khu chế xuất và khu công nghệ cao trên địa bàn tỉnh Bà Rịa - Vũng Tàu Hết hiệu lực 19/2007/QĐ-UBND Quyết định số 19/2007/QĐ-UBND Ban hành Chương trình quản lý ô nhiễm công nghiệp thành phố Đà Nẵng, giai đoạn 2006 – 2010 Hết hiệu lực 12/2009/QĐ-UBND Quyết định số 12/2009/QĐ-UBND về việc sửa đổi, bổ sung một số điều của Quy định bảo vệ môi trường tỉnh Bình Dương ban hành kèm theo Quyết định số: 68/2008/QĐ-UBND ngày 12 tháng 12 năm 2008 của ủy ban nhân dân tỉnh Bình Dương Hết hiệu lực 22/2007/QĐ-UBND Quyết định số 22/2007/QĐ-UBND Ban hành quy định về quy trình giải quyết một số thủ tục hành chính trong quản lý các dự án đầu tư sử dụng nguồn vốn ngoài ngân sách nhà nước trên địa bàn thành phố Hà Nội Hết hiệu lực
08/2006/TT-BTNMT
Circular No. 08/2006/TT-BTNMT guiding strategic environmental assessment, environmental impact assessment, and environmental protection commitment
Expired
↓ Văn bản chịu tác động từ văn bản này
Liên quan 12
68/2008/QĐ-UBND Quyết định số 68/2008/QĐ-UBND Về việc giao chi tiết danh mục sử dụng nguồn chi hoàn trả tạm ứng đã bố trí trong dự toán ngân sách năm 2008 Hết hiệu lực 03/2008/QĐ-UBND Quyết định số 03/2008/QĐ-UBND Về việc ban hành quy chế quản lý và sử dụng kinh phí sự nghiệp kinh tế đối với hoạt động khuyến công trên địa bàn tỉnh Hết hiệu lực 1809/QĐ-UBND Quyết định số 1809/QĐ-UBND Về việc ban hành Quy chế phối hợp giữa các cơ quan tham gia tiếp công dân tại Trụ sở tiếp công dân thành phố Hải Phòng Còn hiệu lực 66/2008/QĐ-UBND Quyết định số 66/2008/QĐ-UBND Về chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bảo tàng Hồ Chí Minh chi nhánh Gia Lai và Kon Tum Hết hiệu lực 55/2007/QĐ-UBND Quyết định số 55/2007/QĐ-UBND Ban hành quy định tạm thời thực hiện đăng ký giá, niêm yết giá hàng hóa, dịch vụ trên địa bàn tỉnh Bà Rịa Vũng Tàu Hết hiệu lực 133/2007/NQ-HĐND Nghị quyết số 133/2007/NQ-HĐND về việc sử dụng nguồn tăng thu ngân sách năm 2007 và dự phòng ngân sách năm 2007 do Hội đồng nhân dân quận Bình Tân ban hành Còn hiệu lực 18/2007/QĐ-UBND Quyết định số 18/2007/QĐ-UBND Về việc thu hồi Quyết định số 871/1998/QĐ/UBT ngày 25/5/1998 của Uỷ ban nhân dân tỉnh Vĩnh Long Còn hiệu lực 40/2007/QĐ-UBND Quyết định số 40/2007/QĐ-UBND Củng cố Ban quản lý rừng phòng hộ Nam Phú Nhơn Còn hiệu lực 46/2007/QĐ-UBND Quyết định số 46/2007/QĐ-UBND Củng cố Ban quản lý rừng phòng hộ Mang Yang Còn hiệu lực 06/2007/QĐ-UBND Quyết định số 06/2007/QĐ-UBND Về việc công bố công khai số liệu quyết toán ngân sách nhà nước năm 2005 và dự toán ngân sách nhà nước năm 2007 của tỉnh Quảng Trị Hết hiệu lực 27/2007/QĐ-UBND Quyết định số 27/2007/QĐ-UBND Về việc ban hành Quy định về một số chính sách phát triển khoa học, công nghệ và nhân lực có trình độ Hết hiệu lực
Dẫn chiếu 2
29/2006/CT-UBND Chỉ thị số 29/2006/CT-UBND Về tăng cường các biện pháp cấp bách phòng, chống rầy nâu, bệnh vàng lùn và bệnh lùn xoắn lá hại lúa trên địa bàn thành phố Hồ Chí Minh. Hết hiệu lực

Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.