Decision No. 11/2007/QĐ-TTg On Amending and Supplementing Certain Provisions on Management Mechanism and Implementation of the Son La Hydropower Project issued together with Decision No. 207/2004/QĐ-TTg dated December 11, 2004

Decision No. 11/2007/QĐ-TTg amends and supplements the management mechanism and implementation of the Son La Hydropower Project. The Decision applies to the Ministry of Industry, the General Contractor, Vietnam Electricity Corporation, related provinces, and relevant organizations. Notably, it adjusts the bidding process, payment procedures, capital management, and investment sources.

Số hiệu11/2007/QĐ-TTg
Loại văn bảnDecision
Cơ quan ban hànhMinistry of Industry and Trade
Người kýNguyễn Tấn Dũng — Thủ tướng Chính phủ
Cập nhật29/06/2026
Lĩnh vựcUncategorized
Ngày ban hành23/01/2007
Ngày áp dụng23/01/2007
Ngày hết hiệu lực18/11/2010
Tình trạngExpired
✦ Tóm lược thông minh

Decision No. 11/2007/QĐ-TTg amends and supplements the management mechanism and implementation of the Son La Hydropower Project. The Decision applies to the Ministry of Industry, the General Contractor, Vietnam Electricity Corporation, related provinces, and relevant organizations. Notably, it adjusts the bidding process, payment procedures, capital management, and investment sources.

Đối tượng áp dụng

The Ministry of Industry, the General Contractor, Vietnam Electricity Corporation, the provinces of Son La, Dien Bien, Lai Chau, and related agencies.

Các điểm cốt lõi

  • The investor selects foreign consultants through limited international bidding and implements or hires supervising consultants for complex construction projects (Article 1.1.a)
  • Vietnam Electricity Corporation is permitted to invest in constructing a concrete admixture production unit from Pha Lai fly ash (Article 1.1.b)
  • The Construction Unit Price Board established by the Ministry of Industry is responsible for setting norms and unit prices, submitting them to the investor for review and issuance after obtaining the unified opinion of the Ministry of Construction (Article 4.1)
  • The investor temporarily advances funds to the General Contractor or contractor according to the provisions of Decree No. 16/2005/NĐ-CP, while simultaneously advancing funds for material reserves (Article 3.2.b)
  • Payment is made at 92% of the value of completed work volume when the contractor has completed payment procedures, with the remainder paid according to the warranty schedule (Article 3.4)

🌐 Tác động xã hội từ văn bản này

  • Positive impact: Reduces costs and increases project management efficiency through adjustments to the bidding process, payment procedures, and capital management.
  • Negative impact: May cause difficulties for small contractors due to requirements for capacity and experience in selecting supervising consultants (Article 1.1.a)
  • Vietnam Electricity Corporation's benefits are expanded investment scope and reduced financial burden through bank loans without the need for loan repayment assessment (Article 6)

❓ Câu hỏi thường gặp

How does the investor select supervising consultants?

The investor selects foreign consultants with experience and capacity through limited international bidding (Article 1.1.a)

What construction unit is Vietnam Electricity Corporation allowed to invest in?

Vietnam Electricity Corporation is permitted to invest in constructing a concrete admixture production unit from Pha Lai fly ash (Article 1.1.b)

Who establishes the Construction Unit Price Board?

The Construction Unit Price Board is established by the Ministry of Industry to set norms and unit prices, submitting them to the investor for review and issuance after obtaining the unified opinion of the Ministry of Construction (Article 4.1)

How does the investor temporarily advance funds to the General Contractor?

The investor temporarily advances funds according to the provisions of Decree No. 16/2005/NĐ-CP, while simultaneously advancing funds for material reserves (Article 3.2.b)

When is payment made to the contractor?

The investor pays 92% of the value of completed work volume when the contractor has completed payment procedures, with the remainder paid according to the warranty schedule (Article 3.4)

Toàn văn

PRIME MINISTER

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 11/2007/QĐ-TTg
Hanoi, January 23, 2007

Pursuant to …;

Regarding the amendment and supplementation of certain provisions on the management mechanism and implementation of the Son La Hydropower Project issued together with Decision No. 207/2004/QĐ-TTg dated December 11, 2004

_____________________________

 

PRIME MINISTER

Pursuant to the Law on Organization of the Government dated December 25, 2001;

Pursuant to the Construction Law dated November 26, 2003;

Pursuant to the Law Amending and Supplementing Certain Provisions of Laws Related to Investment in Construction Projects dated June 19, 2009;

Pursuant to Resolution No. 44/2001/QH10 of the Tenth National Assembly at its ninth session on June 29, 2001 regarding the investment policy for the Son La Hydropower Plant Project; Resolution No. 13/2002/QH11 of the Eleventh National Assembly at its second session on December 16, 2002 regarding the construction plan for the Son La project;

Pursuant to Decree No. 16/2005/NĐ-CP dated February 7, 2005 of the Government on project management for investment in construction works; Decree No. 112/2006/NĐ-CP dated September 29, 2006 amending and supplementing certain articles of Decree No. 16/2005/NĐ-CP; Decree No. 197/2004/NĐ-CP dated December 3, 2004 of the Government on compensation, support, and resettlement when land is reclaimed by the State;

Pursuant to Decision No. 92/QĐ-TTg dated January 15, 2004 of the Prime Minister approving the investment in the Son La Hydropower Project;

Pursuant to Decisions of the Prime Minister No. 09/2004/QĐ-TTg dated January 15, 2004 establishing the National Steering Committee and No. 677/QĐ-TTg dated June 18, 2004 promulgating the Operation Regulation of the National Steering Committee for the Son La Hydropower Project;

Considering the proposal of the Minister of Industry,

DECISION:

Article 1. Amending and supplementing certain provisions on the management mechanism and implementation of the Son La Hydropower Project issued together with Decision No. 207/2004/QĐ-TTg dated December 11, 2004 of the Prime Minister as follows:

1. Amend and supplement Clause 3 of Article 3 as follows:

a) Amend and supplement Point đ as follows:

"d) The investor shall select foreign consultants with experience and capacity through limited international bidding to act as supervisory consultants for the energy transmission line, concrete roller-compacted dam (RCC) section, and other technically complex works; the investor shall organize the implementation or hire supervisory consultants for the remaining sections and tasks according to current regulations."

b) Supplement point g as follows:

g) Permitting the Vietnam Electricity Corporation to invest in constructing the cement additive production unit from Phả Lại fly ash (this unit belongs to the auxiliary area of the Son La Hydropower Project)."

2. Amending and supplementing Clause 4 as follows:

"Article 4. Unit price, total budget estimate, and budget estimates for individual items:

1. The Ministry of Industry shall establish a unit price committee. The unit price committee shall develop standard rates - unit prices, submit them for review by the investor, and submit them for approval by the Ministry of Industry after obtaining the agreement of the Ministry of Construction.

2. The total budget estimate for construction works shall be prepared and approved after the technical design phase 2 and the unit prices are issued, and must be approved no later than when 30% of the construction value in the total investment ceiling is implemented.

3. Acceptance and payment of completed work volumes shall be carried out according to the budget estimate, construction drawings, and construction organization designs that have been approved, consistent with the technical design and total budget estimate.

4. During the period before the technical design phase 2 and the total budget estimate are approved, preparation of designs and budget estimates for individual works that can commence early may be made for approval as the basis for signing contracts to implement those works."

3. Amend and supplement Article 5 as follows:

a) Amend and supplement Clause 2 as follows:

"2. Mechanism for implementing General Contractor Contracts

a) Form and value of General Contractor Contracts:

- A General Contractor Contract is a contract with adjustable prices signed between the investor and the general contractor. Adjustments to the value of the General Contractor Contract shall be made according to current regulations;

- The value of the General Contractor Contract shall be determined based on the construction cost (including contingency) in the approved total budget estimate for corresponding sections within the scope of the General Contractor Contract, reduced by 5%;

b) Advance payments:

- The investor shall temporarily advance funds to the General Contractor or subcontractor according to the provisions of Decree No. 16/2005/NĐ-CP dated February 7, 2005 of the Government on project management for investment in construction works;

- The investor shall temporarily advance a sum of money to the General Contractor to cover material reserves affected by transportation seasonality on the Da River, high construction intensity (sand, gravel, clinker...). The quantity of materials reserved and the amount of temporary advance shall be agreed upon by the investor and the General Contractor.

c) Settlement:

- Allow the investor to pay 92% of the value of completed work when the contractor has completed the payment procedures. The remaining portion will be paid as follows: 5% when there is a completion certificate for the work item from the State Acceptance Board, 2% at the end of the 12-month warranty period, and 1% at the end of the 24-month warranty period.

- Allow the investor to directly pay the subcontractors when the authorized representative of the General Contractor and the Project Management Board sign off on the quality acceptance and quantity confirmation.

- Allow the investor to pay up to 85% of the design budget estimate before the total budget estimate is approved."

b) Amend and supplement Clause 3 as follows:

"3. Mechanism for allocating and paying auxiliary items:

- Auxiliary items such as traffic systems, construction power supply systems within the construction site, water supply, access roads to material quarries, contractors' working houses shall be allocated as a lump sum based on the approved budget estimate. Auxiliary items shall be accepted based on scale and functionality. The scale of these items shall be determined based on the approved construction site layout. Camp costs shall be allocated as a lump sum according to current regulations.

There shall be no reduction of 5% for auxiliary items such as traffic systems, power supply, water supply, basic construction of material quarries, leveling and construction of auxiliary areas, camps, working houses, construction materials provided through competitive bidding or tendering.

- The capital transfer and payment plan shall be carried out according to the agreement between the investor and the General Contractor. Allow the investor to pay up to 95% of the allocated value of preparatory works depending on the degree of completion of the works, the remaining 5% shall be paid when the allocated works have been completed and confirmed by the Project Management Board."

"c) Supplement Clause 6 as follows:"

"6. Allow the investor to borrow funds from banks without having to conduct a loan repayment plan assessment."

4. AMENDING AND SUPPLEMENTING ARTICLE 6 AS FOLLOWS:

"1. The method of selecting suppliers of electromechanical equipment and hydraulic machinery for the main works shall be carried out according to the bidding plan

2. The Ministry of Finance shall provide guarantees for the project investor to borrow foreign capital; organize the issuance of international bonds to purchase equipment, materials, and technology that have not yet been produced domestically.

5. Amend and supplement Clause 1 of Article 12 as follows:

"1. Comprehensive relocation planning: carried out in accordance with Decision No. 196/2004/QĐ-TTg dated November 29, 2004, and subsequent Decisions approving adjustments and supplements by the Prime Minister."

6. Amend and supplement Article 13 as follows:

"Article 13. Work on establishing investment projects, designing, and preparing estimates for projects and works under the relocation resettlement project

1. Economic and technical report preparation for infrastructure works (transportation, water conservancy, electricity supply, water supply...), project establishment, and design stages shall be conducted in accordance with Government Decree No. 16/2005/NĐ-CP dated February 7, 2005, on managing construction investment projects; and Decree No. 112/2006/NĐ-CP dated September 29, 2006, amending and supplementing certain articles of Decree No. 16/2005/NĐ-CP.

2. Allow the People's Committee of the province to designate consulting units with sufficient capacity and experience to undertake detailed planning, project establishment, and design-estimate work for sub-projects and components within the relocation resettlement project.

3. The People's Committees of the provinces shall stipulate the classification and approval procedures for detailed planning, design, and projects and components within the relocation resettlement project.

7. Amending and supplementing Article 16 as follows:

a) Amend and supplement Clause 4 as follows:

"4. Management of funds, advance payments, settlement, and final accounts for compensation and relocation resettlement work shall be carried out in accordance with Decision No. 02/2007/QĐ-TTg dated January 9, 2007, issued by the Prime Minister on compensation, support, and relocation resettlement for the Son La Hydropower Project, and the Circular guiding this by the Ministry of Finance regarding compensation for relocation resettlement.

b) Amend and supplement Clause 5 as follows:

"5. The project investor shall make advance payments to contractors in accordance with the provisions of Government Decree No. 16/2005/NĐ-CP dated February 7, 2005, on managing construction investment projects.

c) Amending and supplementing Clause 6 as follows:

"6. The Chairmen of the People's Committees of Son La, Dien Bien, and Lai Chau Provinces shall be responsible for ensuring the effective and appropriate use of relocation resettlement funds, and shall not use them to settle items funded from other sources.

8. Amend and supplement Clause 1 of Article 17 as follows:

"1. The scope and scale of the Son La Hydropower Flood Avoidance Transportation Works Project are defined in Point 3 of Circular No. 2120/TTg-CN dated December 28, 2005, issued by the Prime Minister.

9. Sửa đổi, bổ sung khoản 1 Điều 18 như sau:

"1. The funding source for the Son La Hydropower Flood Avoidance Transportation Works Project shall be implemented according to Circulars No. 2120/TTg-CN dated December 28, 2005, and No. 1887/TTg-CN dated November 17, 2006, issued by the Prime Minister.

Article 2. This Decision shall take effect from the date of signing.

Article 3. The National Steering Committee for the Son La Hydropower Project, Ministers, Heads of Ministries equivalent to Ministries, Heads of agencies under the Government, Heads of related agencies, Chairmen of the People's Committees of Son La, Dien Bien, and Lai Chau Provinces, Vietnam Electricity Corporation, and Song Da Corporation shall be responsible for implementing this Decision./.

 

PRIME MINISTER
(Signed)
Nguyen Tan Dung
Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Tải văn bản

Văn bản này đang được cập nhật văn bản gốc, vui lòng xem nội dung toàn văn và kiểm tra lại sau.

Bản đồ quan hệ

↑ Cơ sở & văn bản tác động lên văn bản này
Căn cứ 11
44/2001/NQ-QH10 Nghị quyết số 44/2001/NQ-QH10 Về chủ trương đầu tư dự án nhà máy thủy điện Sơn La Còn hiệu lực 13/2002/QH11 Nghị quyết số 13/2002/QH11 Về phương án xây dựng công trình thủy điện Sơn La Còn hiệu lực 32/2001/QH10 Luật Tổ chức Chính phủ số 32/2001/QH10 Hết hiệu lực 112/2006/NĐ-CP Nghị định số 112/2006/NĐ-CP Về sửa đổi, bổ sung một số điều của Nghị định số 16/2005/NĐ-CP về quản lý dự án đầu tư xây dựng công trình Hết hiệu lực 16/2003/QH11 Nghị quyết số 16/2003/QH11 Về việc thực hiện thí điểm chủ trương tổ chức quản lý, dạy nghề và giải quyết việc làm cho người sau cai nghiện ma tuý ở Thành phố Hồ Chí Minh và một số tỉnh, thành phố khác trực thuộc Trung ương Còn hiệu lực 16/2005/NĐ-CP Nghị định số 16/2005/NĐ-CP Về quản lý dự án đầu tư xây dựng công trình Hết hiệu lực 197/2004/NĐ-CP Nghị định số 197/2004/NĐ-CP Về bồi thường, hỗ trợ và tái định cư khi Nhà nước thu hồi đất Hết hiệu lực 61/2005/QH11 Luật Đấu thầu số 61/2005/QH11 Hết hiệu lực
Được dẫn chiếu bởi 2
Bị sửa đổi, bổ sung bởi 1
11/2007/QĐ-TTg
Decision No. 11/2007/QĐ-TTg On Amending and Supplementing Certain Provisions on Management Mechanism and Implementation of the Son La Hydropower Project issued together with Decision No. 207/2004/QĐ-TTg dated December 11, 2004
Expired
↓ Văn bản chịu tác động từ văn bản này
Hướng dẫn 2
138/2007/TT-BTC Thông tư số 138/2007/TT-BTC Hướng dẫn quản lý, thanh toán, quyết toán vốn đầu tư bồi thường, hỗ trợ và tái định cư Dự án thủy điện Sơn La Hết hiệu lực
Thay thế 1

Bấm vào một văn bản để mở. Viền đỏ = quan hệ làm thay đổi hiệu lực.