Circular No. 159/2011/TT-BTC Amending and Supplementing Certain Provisions of Circular No. 138/2007/TT-BTC dated November 29, 2007 of the Ministry of Finance guiding the management, payment, and settlement of investment capital for compensation, support, and resettlement of the Son La Hydropower Project

Circular No. 159/2011/TT-BTC amends and supplements certain provisions on the management, payment, and settlement of investment capital for compensation, support, and resettlement of the Son La Hydropower Project. This document applies to agencies implementing the resettlement project, the Vietnam Development Bank, and the Vietnam Electricity Corporation.

文号159/2011/TT-BTC
文件类型Circular
发布机关Ministry of Finance
签署人Phạm Sỹ Danh — Thứ trưởng
更新26/06/2026
行业Unclassified
领域Budget Management
发布日期16/11/2011
生效日期01/01/2012
失效日期
状态In effect
✦ 智能摘要

Circular No. 159/2011/TT-BTC amends and supplements certain provisions on the management, payment, and settlement of investment capital for compensation, support, and resettlement of the Son La Hydropower Project. This document applies to agencies implementing the resettlement project, the Vietnam Development Bank, and the Vietnam Electricity Corporation.

适用范围

Agencies implementing the resettlement project, the Vietnam Development Bank, the Vietnam Electricity Corporation

要点

  • Agencies implementing the resettlement project → ensure investment and construction procedures according to legal regulations.
  • Before December 25 each year → adjust the allocation plan of investment capital, payment up to December 31 of the planning year; the payment period for the investment plan is up to January 31 of the following year. In special cases requiring an extension of the payment period, the People's Committee of the province reports to the Ministry of Finance.
  • Urban resettlement area → implemented according to Circular No. 86/2011/TT-BTC of the Ministry of Finance.
  • Duration of food support → implemented according to Decision No. 43/2011/QĐ-TTg of the Prime Minister.
  • One-time payment for resettled households → based on the production plan approved by the competent authority at the district level.
  • Settlement of expenses for compensation, support, and resettlement when the State recovers land → according to Circular No. 57/2010/TT-BTC of the Ministry of Finance.
  • Construction contracts → abolish the provision regarding contract settlement.
  • Settlement of costs for compensation, support, and resettlement paid directly to households → supplemented in Appendix No. 06.
  • The Vietnam Development Bank → report settlement to the Ministry of Finance and the Vietnam Electricity Corporation on April 1 of the following year regarding the situation of receiving and using project funds up to January 31 of the following year.
  • Report to the Vietnam Development Bank → abolish the quarterly IV reporting requirement, supplement the 13-month report on February 20 of the following year.

🌐 本文件的社会影响

  • Positive impact: Reducing administrative procedures, facilitating management and payment of investment capital.
  • Negative impact: May cause difficulties in tracking and controlling the effective use of funds.

❓ 常见问题

What is the deadline for adjusting the allocation plan of investment capital?

The deadline for adjusting the allocation plan of investment capital is before December 25 each year.

Which agency is responsible for paying construction projects in urban resettlement areas?

Payment of construction projects in urban resettlement areas is carried out according to the provisions of Circular No. 86/2011/TT-BTC of the Ministry of Finance.

How is the duration of food support implemented?

The duration of food support is implemented according to Decision No. 43/2011/QĐ-TTg of the Prime Minister.

On what basis is a one-time payment made to resettled households?

A one-time payment to resettled households is based on the production plan approved by the competent authority at the district level.

When does the Vietnam Development Bank need to report settlement?

The Vietnam Development Bank reports settlement to the Ministry of Finance and the Vietnam Electricity Corporation on April 1 of the following year regarding the situation of receiving and using project funds up to January 31 of the following year.

全文

MINISTRY OF FINANCE

SOCIALIST REPUBLIC OF VIET NAM
Independence – Freedom – Happiness

Number: 159/2011/TT-BTC
Hanoi, November 16, 2011

CIRCULAR

Amending and supplementing certain provisions of Circular No. 138/2007/TT-BTC dated November 29, 2007 of the Ministry of Finance guiding management, payment, and settlement of capital for compensation, support, and resettlement for the Son La Hydropower Project

guidelines for managing, settling, and finalizing capital investment for compensation, support, and resettlement for the Son La Hydropower Project

_____________________________

 

Pursuant to the Construction Law No. 16/2003/QH11 dated November 26, 2003; the Law Amending and Supplementing Certain Provisions of Laws Related to Basic Construction Investment No. 38/2009/QH12 dated June 19, 2009;

Pursuant to Decree No. 12/2009/NĐ-CP dated February 12, 2009 of the Government on Management of Investment Projects for Construction Works; Decree No. 83/2009/NĐ-CP dated October 15, 2009 amending and supplementing certain provisions of Decree No. 12/2009/NĐ-CP dated February 12, 2009; Decree No. 112/2009/NĐ-CP dated December 14, 2009 of the Government on Management of Construction Costs; Decree No. 48/2010/NĐ-CP dated May 7, 2010 of the Government on Contracts in Construction Activities; Decree No. 52/1999/NĐ-CP dated July 8, 1999 of the Government promulgating the Regulation on Investment and Construction Management; Decree No. 12/2000/NĐ-CP dated May 5, 2000 and Decree No. 07/2003/NĐ-CP dated January 30, 2003 of the Government amending and supplementing certain provisions of the Regulation on Investment and Construction Management issued together with Decree No. 52/1999/NĐ-CP dated July 8, 1999; Decree No. 85/2009/NĐ-CP dated October 15, 2009 of the Government guiding the implementation of the Law on Bidding and Selection of Contractors under the Construction Law;

Pursuant to the Decree No. 118/2008/NĐ-CP dated November 27, 2008 of the Government stipulating the functions, tasks, powers, and organizational structure of the Ministry of Finance;

Pursuant to Decision No. 02/2007/QĐ-TTg dated January 9, 2007 of the Prime Minister promulgating the Provision on Compensation, Support, and Resettlement for the Son La Hydropower Project; Decision No. 141/2007/QĐ-TTg dated August 24, 2007, Decision No. 31/2008/QĐ-TTg dated February 25, 2008, Decision No. 72/2009/QĐ-TTg dated May 4, 2009, and Decision No. 43/2011/QĐ-TTg dated August 10, 2011 of the Prime Minister amending and supplementing certain provisions of the Provision on Compensation, Support, and Resettlement for the Son La Hydropower Project promulgated together with Decision No. 02/2007/QĐ-TTg dated January 9, 2007 of the Prime Minister;

Implementing Decision No. 2107/QĐ-TTg dated November 18, 2010 of the Prime Minister promulgating the management mechanism and implementation of the Son La Hydropower Project;

The Ministry of Finance amends and supplements certain provisions of Circular No. 138/2007/TT-BTC dated November 29, 2007 of the Ministry of Finance guiding management, payment, and settlement of capital for compensation, support, and resettlement for the Son La Hydropower Project (hereinafter referred to as Circular No. 138/2007/TT-BTC) as follows:

Article 1. Amending and supplementing certain provisions of Circular No. 138/2007/TT-BTC as follows:

1. Amending and supplementing item 5, point 1, Part I as follows:

Ensuring investment and construction procedures in accordance with current laws.

2. Amending and supplementing the regulation on adjustment of capital investment plan allocation at point 2, Part II as follows:

- The deadline for adjusting the capital investment plan allocation is before December 25 each year.

- The annual capital investment plan is paid for the completed volume accepted up to December 31 of the planning year; the payment deadline for the annual capital investment plan (including adjusted plans) is until January 31 of the following year. In special cases requiring extension of the capital payment period, the People's Committee of the province shall report to the Ministry of Finance in writing before January 31 of the following year for coordination in handling.

3. Regarding payment for construction works in urban resettlement areas:

Abolishing the provision on payment for construction works in urban resettlement areas at point 4, Part IV; implementing according to the provisions of Circular No. 86/2011/TT-BTC dated June 17, 2011 of the Ministry of Finance on management, payment, and capital investment and state budget investment funds with operational nature.

4. Adding item 4 to sub-point a, point 7.4, Part IV as follows:

Duration of food support: implemented according to Decision No. 43/2011/QĐ-TTg dated August 10, 2011 of

5. Amending and supplementing sub-point a, point 7.5, Part IV as follows:

Based on the production plan approved by the competent authority at the district level, make a one-time payment to the resettled households.

6. Amending and supplementing point 8.2, Part IV as follows:

Implemented according to the provisions of Circular No. 57/2010/TT-BTC dated April 16, 2010 of the Ministry of Finance on the preparation, use, and settlement of expenses for organizing the implementation of compensation, support, and resettlement when the State recovers land.

7. Abolishing the provision on settlement of construction contracts stipulated at point 1, Part V.

8. Adding content in Appendix No. 06 regarding the settlement of compensation, support, and resettlement costs directly paid to households.

9. Amending and supplementing point 2, Part V as follows:

On April 1 of the following year, the Vietnam Development Bank reports to the Ministry of Finance and the Vietnam Electricity Corporation on the receipt and use of project funds up to January 31 of the following year.

10. Amending and supplementing the reporting requirements for the Vietnam Development Bank at point 2, Part VI as follows:

- Abolishing the provision that "the fourth quarter report is replaced by an annual report due on January 20 of the following year."

- Adding a 13-month report (replacing the annual report) to be prepared on February 20 of the following year.

11. Amending and supplementing item 2, point 3, Part VI as follows:

Before preparing the final report on the receipt and use of project funds, the Vietnam Development Bank shall reconcile with the Ministry of Finance and the Vietnam Electricity Corporation on the amount of funds received and paid out during the year.

Article 2. This Circular takes effect from January 1, 2012.

During the implementation process, if there are difficulties or obstacles, localities and agencies are requested to promptly reflect them to the Ministry of Finance for study and appropriate amendments.

DEPUTY MINISTER
DEPUTY MINISTER
(Signed)
Pham Sy Danh

原始文件(PDF)

在新标签页打开PDF ↗

关系图

↑ 依据及影响本文件的文件
依据 18
52/1999/NĐ-CP Nghị định số 52/1999/NĐ-CP Về việc ban hành Quy chế Quản lý đầu tư và xây dựng 生效中 07/2003/NĐ-CP Nghị định số 07/2003/NĐ-CP Về sửa đổi, bổ sung một số điều của Quy chế quản lý đầu tư và xây dựng ban hành kèm theo Nghị định số 52/1999/NĐ-CP ngày 08 tháng 7 năm 1999 và Nghị định số 12/2000/NĐ-CP ngày 05 tháng 5 năm 2000 của Chính phủ 生效中 16/2003/QH11 Nghị quyết số 16/2003/QH11 Về việc thực hiện thí điểm chủ trương tổ chức quản lý, dạy nghề và giải quyết việc làm cho người sau cai nghiện ma tuý ở Thành phố Hồ Chí Minh và một số tỉnh, thành phố khác trực thuộc Trung ương 生效中 85/2009/NĐ-CP Nghị định số 85/2009/NĐ-CP Hướng dẫn thi hành Luật Đấu thầu và lựa chọn nhà thầu xây dựng theo Luật Xây dựng 已失效 112/2009/NĐ-CP Nghị định số 112/2009/NĐ-CP Về quản lý chi phí đầu tư xây dựng công trình 已失效 12/2000/NĐ-CP Nghị định số 12/2000/NĐ-CP Về việc sửa đổi, bổ sung một số điều của Quy chế quản lý đầu tư và xây dựng ban hành kèm theo Nghị định số 52/1999/NĐ-CP ngày 08 tháng 7 năm 1999 của Chính phủ 生效中 48/2010/NĐ-CP Nghị định số 48/2010/NĐ-CP Về hợp đồng trong hoạt động xây dựng 已失效 83/2009/NĐ-CP Nghị định số 83/2009/NĐ-CP Về sửa đổi, bổ sung một số điều Nghị định số 12/2009/NĐ-CP ngày 12 tháng 02 năm 2009 của Chính phủ về quản lý dự án đầu tư xây dựng công trình 已失效 38/2009/QH12 Nghị quyết số 38/2009/QH12 Về phân bổ ngân sách trung ương năm 2010 已失效 12/2009/NĐ-CP Nghị định số 12/2009/NĐ-CP Về quản lý dự án đầu tư xây dựng công trình 已失效 118/2008/NĐ-CP Nghị định số 118/2008/NĐ-CP Quy định chức năng, nhiệm vụ, quyền hạn và cơ cấu tổ chức của Bộ Tài chính 已失效 16/2014/QĐ-UBND Quyết định số 16/2014/QĐ-UBND Sửa đổi, bổ sung một số điều trong “Cơ chế quản lý, điều hành, tổ chức thực hiện Dự án di dân, tái định cư thủy điện Sơn La” ban hành kèm theo Quyết định số 17/2011/QĐ-UBND ngày 03 tháng 11 năm 2011 của UBND tỉnh Sơn La 生效中 19/2013/QĐ-UBND Quyết định số 19/2013/QĐ-UBND V/v sửa đổi, bổ sung một số điều của các Quyết định của UBND tỉnh Điện Biên về việc ban hành quy định cụ thể hóa một số điều về bồi thường, hỗ trợ và tái định cư Dự án thủy điện Sơn La theo Quyết định số 02/2007/QĐ-TTg ngày 09/01/2007 của Thủ tướng Chính phủ 生效中
159/2011/TT-BTC
Circular No. 159/2011/TT-BTC Amending and Supplementing Certain Provisions of Circular No. 138/2007/TT-BTC dated November 29, 2007 of the Ministry of Finance guiding the management, payment, and settlement of investment capital for compensation, support, and resettlement of the Son La Hydropower Project
In effect